PWS for Water Fountains Amendment 1 dated 31 July 2017.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3: Statement of Work

FA5004-17-Q-0026

PERFORMANCE WORK STATEMENT

FOR

BAKER FIELD HOUSE WATER FOUNTAINS

EIELSON AFB ALASKA

10 July 2017

WATER FOUTAIN PWS

TABLE OF CONTENTS

1. DESCRIPTION OF REQUIREMENT 3

2. GOVERNMENT SPECIAL INSTRUCTIONS, TERMS AND CONDITIONS 4

3. SERVICE SUMMARY 6

SECTION 1

Description of Requirement

1. Background

This requirement is a quality of life initiative to upgrade the water fountains at the Baker Field

House at Eielson AFB, Alaska. The water fountains will be upgraded to consist of water cooling, water filtration, and have water bottle fillers.

2. Objectives

Replace existing water fountains at Baker Field House with upgraded water fountains that will have water coolers, water filters, and water bottle fillers.

3. Scope

Contractor shall provide all management, tools, supplies, equipment, labor, and transportation necessary to deliver and install drinking fountains at the Baker Field House to the locations below, in Section 12, on Eielson AFB, Alaska.

4. Delivery and Installation

4.1 OR EQUAL ITEMS ACCEPTED: Contractor will supply and install three (3) standing water fountains (name brand is not necessary but three (3) fountains quoted must be matching). Water fountains shall have a bottle filler nozzle (or equal) and a water filtration system and cooler (or equal), able to cool a minimum of 7 gallons per hour. Fountains must be securely installed to floor, or wall, and able to withstand incidental contact.

4.2 BRAND NAME/EXACT MATCH REQUIRED: Contractor shall supply and install one

Elkay model LZSTL8WS ADA compliant dual level water fountain with water filtration system and cooler, water fountain also has sensor operated bottle filler Elkay model LZWSR1C attached to lower level water fountain.

4.3 INSTALL ONLY: Contractor shall also install one (1), Government furnished, Elkay model

LZSTL8WS, ADA compliant dual level water fountain with water filtration system and cooler, water fountain shall also have sensor operated bottle filler attached to lower level water fountain.

Contractor is responsible for all plumbing and electrical connections. All install locations currenlty have working plumbing and electrical connections. Contractor shall verify connections are still valid and serviceable before installing new fountains. Any unservicable lines will be brought to the attention of the Contracting Officer and Technical Representative for resolution.

Incidental/small issues commonly found in new fountain and/or plumbing/fixture installs will be the responsibility of the Contractor to rectify as part of installation. Major electrical/plumbing infrastructure defeciencies shall be the responsibilty of the Government. Contractor shall dispose of all previous existing water fountains, and refuse created from install, and leave work area to previous standard.

5. Government-Furnished Property (GFP)

None

6. Security Considerations

Personnel must gain access to Eielson AFB, Alaska.

7. Travel

Delivery and Installation at Eielson AFB, Alaska 99702, Baker Field House Bldg. 3343

8. Special Material Requirement

Materials and handling equipment as necessary to perform the delivery and installation. Water fountains located on second floor can be accessed by stairway or elevator pending operability.

9. Other Unique Requirements and Considerations

The work requires installation with plumbing and electrical connections.

10. Place of Performance

All work shall be accomplished within the Baker Field House at Eielson AFB, 99702

11. Period of Performance

Date of award through 30 September 2017

12. Locations of water fountains

Building Location

3343 First Floor Entrance

3343 First Floor Ab Room

3343 Second Floor Basketball Bleachers

3343 Second Floor Running Track

3343 Second Floor Running Track

13. Salient Characteristics

A. Deliver/Installation of Three (3) standing floor mounted water fountains with water cooler and bottle filler. Products must match.

B. Delivery/Installation of One (1) ADA compliant dual water fountain Elkay Model

LZSTL8WS with bottle Filler Model LZWSR1C.

C. Installation of One (1) ADA compliant dual water fountain Elkay Model LZSTL8WS with bottle Filler Model LZWSR1C.

D. Three filters for all fountains supplied.