Q_ _A_Hangar_Flooring__6.pdf

PDF 93 KB Posted

Attached to
Hangar Floor Repaint Federal contract opportunity
Solicitation number
FA5004-15-B-C007
Issued by
Department of the Air Force Pacific Air Forces

About this file

Q A Hangar Flooring 6

View the file

Other files for this federal contract opportunity

Other files attached to Hangar Floor Repaint, newest first.
File Type Posted
JA_1_-_Specifications_4_June_2015.pdf PDF
Q__A_Hangar_Floor__5.pdf PDF
Q_ _A_Hangar_Flooring__7.pdf PDF
JA-0_-_Statement_of_Work_4_June_2015.pdf PDF
FA5004-15-B-C007-0004.pdf PDF
JA-4_-_AF_Form_66_Schedule_of_Material_Submittals_4_June_2015.xls XLS spreadsheet
JA-1_-_Specifications.pdf PDF
FA5004-15-B-C007-0003.pdf PDF
JA-4_-_AF_Form_66_FTQW_15-1021.xls XLS spreadsheet
JA-0_-_Statement_of_Work.pdf PDF
Amendment__2.pdf PDF
Q_ _A__Hangar_Flooring__4.pdf PDF
Q__A_Hangar_Floor__3.pdf PDF
Site_Visit_Sign_in_Sheet_Hangar_Floor.pdf PDF
Q__A_Hangar_Flooring__2.pdf PDF
Q__A_Hangar_Flooring__1.pdf PDF
FA5004-15-B-C007_Mod_00001.pdf PDF
JA-1_-_Specifications_14_May_2015.pdf PDF
JA-6_-_Photos.pdf PDF
FA5004-15-B-C007_-_Hangar_Floor_IFB.pdf PDF
JA-2_-_Taxiway_and_stationary_line_markings.pdf PDF
JA-4_-_Floorplan.pdf PDF
JA-1_-_Specifications.pdf PDF
JA-0_-_Statement_of_Work.pdf PDF
JA-3_-_ETL_96-5.pdf PDF
JA-7_-_Wage_Determination.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Answers to Questions #6

Project FTQW 15-1021

Repaint Hangar Floor (B1232)

3 June, 2015

Q1. Section 09-67-23.16, Page 17 asks for a cove strip installation. Is this required on the Eielson

Floor Repaint project?

A1. A cove strip is not required for this project.

Q2. Will an acetone-based paint for the striping be acceptable?

A2. Acetone shall not be used to due to the fact that it may damage the prep work. Our counterparts in Anchorage recommend we stick with the shot blasting.

Q3. Is all required striping inside the hangar or is there any outside?

A3. The only striping to be done is inside the hangar. The bay floor will be the only thing being touched. Nothing outside shall be striped.