Replace Gate V‐78

Q: It appears the lead time from various manufactures exceeds the 45 day performance period of the contract. The best estimate was 14 weeks and worst estimate was 25 weeks for gate manufacturing. Would JBER consider extending the performance period so the gate can be procured over the winter and installed in the summer?

A: Yes, it is acceptable to change based on material lead time.