SOW_-_Ship_Creek_Fence(revised).pdf
PDF 345 KB Posted
- Attached to
- Security Forces Fence JBER
- Solicitation number
- FA500018Q0206
About this file
Ship Creek Fence SOW/Drawings
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REVISED_MWD_Fence_Drawings.pdf | ||
| REVISED_MWD_Fence_SOW.pdf | ||
| Drawings.jpg | JPG image | |
| FA500018Q0206.pdf | ||
| Wage_Determination.pdf | ||
| SOW_Fencing_bldg_4917.DOCX | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
INSTALL SECURITY FENCE AT SHIP CREEK
JOINT BASE ELMENDORF-RICHARDSON (JBER), ALASKA
1. Scope of Project: The contractor shall perform all services, including furnishing all personnel, equipment, materials, and transportation required in connection with the task described in Section 2. The scope is to install approximately 150 feet of chain link security fencing to prevent unauthorized access from the pedestrian bridge over Ship Creek (please see drawings on pages 2 and 3).
2. Major Tasks: The Contractor shall complete the following tasks:
2.1. Install 7-ft high chain link security fencing with 3-strand barbed wire on the north and south sides of Ship Creek (per attached map and diagram). The fence on the north side of Ship Creek is approximately 80 ft long and on the south side about 70-ft long.
2.2. The fence will be tied to the existing boundary fence on each side and extend to the edges of Ship Creek. An outrigger with barbed wire will be attached to the end of the fence and extend out over Ship Creek a minimum of 2 ft.
3. Work Hours: Work hours on this project shall be limited to Monday through Friday inclusive, between 0700 hours through 1600 hours, excluding federal holidays, unless approved otherwise in writing by the Contracting Officer.
4. Safety and Access: Access to the work area is restricted and monitored. The Contractor will be responsible for coordinating access with JBER Security Forces by contacting the Resource Protection Team at 384-0812. The contractor shall make every effort to secure the work site, allowing only authorized personnel to enter the work site.
5. Workmanship: All work shall be accomplished in accordance with all applicable building and fire codes. Contractor shall field verify all measurements, quantities, or value stated by the Government.
6. Work Site: The contractor shall limit the work to the areas indicated by the government. The contractor shall make efforts to minimize interference to Government operations. The contractor shall dispose of all construction debris off base at an approved disposal facility. Work area shall clear of waste and excess construction material prior to acceptance.
7. Health/Safety: The contractor shall be responsible for compliance with OSHA and AFOSH standards. The contractor shall maintain a clean and debris free site at all times.
8. Technical Point of Contact (POC): The Contractor will direct technical questions and request any pre-work site visits with the JBER technical POC, Mark Prieksat, 384-3003.
9. Period of Performance (POP): The project shall be completed within 30 days from date of award.
North Fence Section ~ 80 ft
South Fence Section ~ 70 ft
Ship Creek
Outrigger Over Creek Tied to existing perimeter fence
Steel Bars
Barbed Wire
| Fence PPT.pdf |
| Slide Number 1 |
| Slide Number 2 |
| Fence PPT.pdf |
| Slide Number 1 |
| Slide Number 2 |
File details come from the government source that posted it.