This document is a Performance Work Statement (PWS) for an asbestos abatement project at Building 1300 on Mountain Home Air Force Base (MHAFB) in Idaho. The contractor shall provide all labor, equipment, and supplies necessary to abate and remove approximately 5,200 sq. ft. of asbestos-containing materials from the office space, in accordance with all applicable federal, state, and local regulations. Key requirements include constructing a two-phase containment process, removing the suspended ceiling system, stud walls, and floor coverings, and conducting clearance air sampling upon completion. The work shall be performed Monday through Friday, 7:00 am to 4:30 pm local time, excluding federal holidays. The contractor shall comply with OPSEC requirements and obtain necessary base access for personnel. The related federal contract opportunity, Solicitation #FA489724QC034, is being issued by the Department of the Air Force Air Combat Command for these asbestos abatement services.

View the file

Other files for this federal contract opportunity

Other files attached to Asbestos Abatement, newest first.
File Type Posted
Amendment 2 combo final.pdf PDF
Amendment 2 Bldg 1300 measurements.pdf PDF
Amendment 1 PWS-Rev 3 B1300 Abatement-Final.docx DOCX document
Amendment 1 MHAFB Building 1300 Pre-renovation Survey ACM.pdf PDF
Combo_Final.pdf PDF
WD 2015-5513 REV 22.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number

Performance Work Statement (PWS) For

Asbestos Abatement (Bldg. 1300)

Mountain Home AFB (MHAFB), ID

7 May 2024

1. GENERAL INFORMATION.

1.1. Description of Work. The contractor shall provide all personnel, labor, supervision, management, supplies, tools, equipment, parts, materials, transportation, shipping & delivery, and all other items and services necessary to abate and remove asbestos for approximately 5,200 sq. ft. of office space at building 1300, Mountain Home AFB, Idaho. All work shall be accomplished in accordance with this Performance Work Statement (PWS), all applicable federal, state, local laws, regulations, manufacturer’s specifications, and commercial practices.

1.2. Contract Changes/Additional Work. At future dates, the government reserves the right to incorporate, add, remove, and/or modify quantities of work within the scope of this requirement. At times, due to the nature of work, it may be necessary to modify this requirement on an as-needed basis. Additionally, there may be a need for ‘one-time’ requirements or special sub-contracting opportunities in order to fulfill the requirement needs. Any future changes to this requirement will be negotiated and incorporated in the contact via contract modification, whether by negotiation, or based on priced line items currently incorporated within the contract.

1.3. Publications. The contractor shall perform all work associated with this requirement detailed within this PWS, in accordance with the applicable publications below. The latest editions of the following publications and standards shall apply:

1.3.1. Environmental. Perform work in accordance with 40 CFR Part 61 – National Emission Standards for Hazardous Air Pollutants, Subpart M – National Emission Standard for Asbestos.

1.3.2. Permits and Notifications. The Contractor shall identify and obtain all required permits/notifications per 40 CFR Part 61 – National Emission Standards for Hazardous Air Pollutants, Subpart M – National Emission Standard for Asbestos for demolition and renovation prior to conducting any work on Mountain Home AFB. Regulatory Notifications (Validation/documentation) - Provide regulatory notification requirements in accordance with federal, state, and local regulations. In cases where the Government will also provide public notification (such as stormwater permitting), coordinate with the Contracting Officer. Submit copies of regulatory notifications to the Contracting Officer at least 10 days prior to commencement of work activities. Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).

1.3.3. Submittals. All submittals/permits obtained as part of this project shall be provided to the Project Manager (PM) for review. The contractor shall submit copies of all waste manifests and reports to the CO and CE representative upon completion of the project.

1.3.3.1 With Quote/Proposal:

Environmental Protection Plan (EPP) Environmental Manager Qualifications - Appoint in writing an Environmental Manager for the project site. The Environmental Manager is directly responsible for coordinating contractor compliance with federal, state, local, and installation requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements (including hazardous waste handling, storage, manifesting, and disposal); implement the EPP; ensure environmental permits are obtained, maintained, and closed out; ensure compliance with Stormwater Program requirements; ensure compliance with Hazardous Materials (storage, handling, and reporting) requirements; and coordinate any remediation of regulated substances (lead, asbestos, PCB transformers). This can be a collateral position; however, the person in this position must be trained to adequately accomplish the following duties: ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure Contractor personnel are trained in 40 CFR requirements in accordance with their position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out. Submit Environmental Manager Qualifications to the Contracting Officer.

1.3.3.2 Post-Award (prior to performance/as applicable):

Employee Training Records - Prepare and maintain Employee Training Records throughout the term of the contract meeting applicable 40 CFR, Chapter 1, Subchapter C, Part 61, Subpart M, 81.145 Standard for demolition and renovation requirements.

1.3.3.3 Post-performance / Prior to invoice submittal:

Disposal Documentation for Hazardous and Regulated Waste/ waste manifests.

1.4. Hours of Operation. The contractor shall be available between Monday through Friday 7:00 am to 4:30 pm (local) time (MST). These are the “normal” hours of operation. Weekends or holidays shall not be counted as a business day.

1.4.1. Holidays. The contractor shall not be required to provide normal services/work during federal holidays. Federal holidays are defined as follows:

New Year’s DayJuneteenthVeteran’s Day
Martin Luther King’s BirthdayIndependence Day (July 4th)Thanksgiving Day President’s DayLabor DayChristmas Day
Memorial DayColumbus Day

NOTE: Holidays occurring on Saturday will be observed the preceding Friday. Those occurring on Sunday will be observed the following Monday

2. REQUIREMENTS. The contractor shall abate/remove all Asbestos Containing Material (ACM) located in building 1300, highlighted on floorplan. See attachment 1. Contracting will conform to industry standard for the period of performance.

2.1. Logical order of salient characteristics:

2.2. The contractor shall construct a 2 phase containment processes so that occupants may gain access to the buildings main entrance while containing abatement area. Abatement shall start on the Southwest end of the building at the Ladies restroom.

2.3. The contractor will remove the suspended ceiling system.

2.4. The contractor will remove 300 linear feet of stud walls.

2.5. The contractor will remove the floor coverings and mastic to reveal bare concrete.

2.6. Upon completion of abatement, a third-party testing firm shall provide CLEARANCE AIR SAMPLING.

3. SURVEILLANCE & QUALITY ASSURANCE.

3.1. SERVICE SUMMARY

3.2. Quality Control. The contractor shall employ their commercial quality control program and procedures to identify, prevent, and ensure non-recurrence of defective services. Through implementation of the contractor’s quality control program/procedures, the Government shall receive quality services meeting the requirements of this contract. All quality control records shall be kept and made available to the Government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract.

3.3. Quality Assurance. The Government may use various quality assurance methods to determine the contractor’s compliance with the PWS and the contract requirements in accordance with FAR Clause 52.212-4, Contract Terms and Conditions – Commercial Items (a) Inspection/Acceptance.

3.4. Re-Performance of Non-Conforming Work. Upon inspection of work, any work found to not be in accordance with this PWS/contract shall be re-performed by the contractor at no additional cost to the government.

4. CONTRACT ADMINISTRATION. During performance under contract, the contractor shall participate in administrative tasks inherent to the administration, surveillance, and oversight of contract performance.

4.1. Contract Employees. All contract personnel must be able to read, write, speak, and understand English fluently. Contract personnel shall present a neat appearance, and be easily identified as a contract employee. The contractor shall obtain base identification and vehicle passes for all employees who make frequent visits to, or perform work on Mountain Home AFB in accordance with the current installation access/entry requirements. Contractor personnel are required to wear or prominently display installation identification while visiting or performing work on the installation. The contractor shall not employ persons for work on this contract identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. Each employee will be easily identified by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name(s). The contractor shall not employ any person who is an employee of the Government, if employing that person would create a conflict of interest. The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the service provider’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.

4.2. Interferences. The contractor shall not unduly interfere with regular scheduled government operational activities in the performance of contract requirements. In the event a government supervisor so requests, the contractor shall temporarily cease work in the area and report the issue, to include the name of the government personnel involved to Contracting Officer immediately. The contractor shall notify the Contracting Officer verbally of disputes with customers or other base contractors and follow-up in writing.

4.3. Records Management. The contractor shall create, handle, and maintain records for the Air Force, regardless of medium, in accordance with the requirements established in AFRIMS Records Disposition Schedule (RDS), AFI 33-322, Records Manage Program, AFI 33-364, Records Disposition Procedures and Responsibilities, and AFM 33-363, Management of Records. Full text versions of these publications are available for free download at http://www.e-publishing.af.mil. Inquiries as to the specific actions necessary to meet the requirements established in the above referenced publication may be directed to the Mountain Home Records Management Office at 366 CS/SCOKR, Bldg. 512, Mountain Home AFB, ID, 83648.

5.0. ENVIRONMENTAL CONTROLS.

5.1. Hazardous Material Inventory and Safety Data Sheets(SDS). SDS are required as specified in the latest version of Federal Standard No. 313 for all potentially hazardous materials. SDSs must be submitted by the Contractor upon contract award to the Hazardous Materials Program Manager (366 FW/A7IE) at 208-828-1684/6351 for a determination of whether or not a product is a HAZMAT and what additional requirements may be applicable/necessary. Approval is required before bringing any hazardous materials (HAZMAT) onto the installation. The government (HAZMART personnel) will inventory all chemicals that the Contractor brings on to Mountain Home AFB or any property under the control of Mountain Home AFB. Any products that meet the criteria of “Hazardous Waste” must be bar coded and tracked until permanently removed from government property. The inventory will be performed prior to commencement of work. Criteria for identifying hazardous waste, is contained in Subpart C of 40 CFR, Part 261.

5.2. Material Storage and Use. The contractor shall follow manufacturer's guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.

5.3. Notification of Environmental Spills. If a spill occurs, the person discovering the spill will make every effort to stop the product flow (if possible), warn personnel, shut off ignition sources, contain the spill, make notifications, and begin cleanup. If the spill is considered an emergency and there is a potential life, health, fire, or other safety hazard, the MHAFB Fire Department will be notified IMMEDIATELY. Responsible units/activities will clean up small spills safety and within their capabilities to do so. Generally, a spill of only a few gallons will recovered by the responsible unit/activity using absorbent materials or a spill kit located by the site. Recovered product and contaminated materials will be packaged and staged for disposal in accordance with the installations hazardous waste procedures. Contact the Environmental Office (208-828-6351) for guidance. The liability for the spill or release of such substances rests solely with the contractor and its agent.

5.4. Waste. Identify, label, handle, store, and dispose of hazardous waste or debris in accordance with federal, state, and local regulations. Ensure all waste has undergone the appropriate hazardous waste determination and documentation is retained for these determinations. If hazardous wastes are generated the contractor will be required to setup and maintain a hazardous waste accumulation point. All hazardous waste generated must be disposed of at a RCRA permitted treatment storage or disposal facility. Do not dispose of hazardous waste on Government property. Do not discharge any waste to a sanitary sewer, storm drain, or to surface waters or conduct waste treatment or disposal on Government property without written approval of the Contracting Officer and Environmental. Consult with the Hazardous Waste Program Manager (366 FW/A7IE) at 208-828-1684/6351 prior to disposal of any waste.

5.5. Historic Preservation. MHAFB houses numerous historic properties (buildings, structures, objects, archaeological sites) managed in compliance with the National Historic Preservation Act (NHPA), and its implementing regulations at 36 CFR 800. In order to avoid inadvertent adverse effects to historic properties, coordination with 366FW A7IE Cultural Resources Manager, Ms. Noelle Shaver (828-8003/6351) is required prior to implementation.

6. SECURITY, OPSEC, & ANTITERRORISM. The contractor shall comply with all requirements and procedures IAW AF FAR 5353.242-9000, Contractor Access to Air Force Installations included herein. All contract employees shall carry contractor photo identification at all times. Contractor employees shall comply with any base security measures implemented at all times. This includes, but is not limited to, vehicle and goods searches and identification checks during times of increased security.

6.1. Operations Security: The contractor shall comply with 366 FW OPSEC requirements and countermeasures to protect critical information as defined in AFI 10-701, Operations Security. Contractors shall receive unit-specific OPSEC training within 90 days of assignment to a contract. Training documentation must be completed by the respective unit OPSEC coordinator. The unit OPSEC personnel will provide guidance on protecting critical information, training materials and other instructions as needed. The contractor will comply with the 366 FW OPSEC Policy that imposes a 100% shred requirement of all government related paper products using NSA approved devices only.

APPENDIX 1 – MAP / Floor Plan image1.png