Attachment_3_Temporary_Environmental_Controls.pdf
PDF 142 KB Posted
- Attached to
- Refuse Collection Services Federal contract opportunity
- Solicitation number
- FA489718B0001
About this file
Attachment 3 - Environmental Controls
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4897-18-B-0001-0002.pdf | ||
| FA4897-18-B-0001-0001.pdf | ||
| Appendix_B.tif | TIF image | |
| Attachment_5_Financial_Institution_Reference_Sheet.pdf | ||
| Attachment_1_PWS.pdf | ||
| Attachment_2_-_CDR.pdf | ||
| FA4897-18-B-0001.pdf | ||
| Attachment_4_WD_2015-5513_Rev_6.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01 57 19 Page 1
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
11/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SW-846 (Third Edition; Update IV) Test Methods for Evaluating Solid Waste: Physical/Chemical Methods
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.120 Hazardous Waste Operations and Emergency Response
40 CFR 112 Oil Pollution Prevention
40 CFR 122.26 Storm Water Discharges (Applicable to State NPDES Programs, see section 123.25)
40 CFR 241 Guidelines for Disposal of Solid Waste
40 CFR 243 Guidelines for the Storage and Collection of Residential, Commercial, and Institutional Solid Waste
40 CFR 258 Subtitle D Landfill Requirements
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 261.7 Residues of Hazardous Waste in Empty Containers
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 262.31 Standards Applicable to Generators of Hazardous Waste-Labeling
FA4897-18-B-0001
Attachment 3
Section 01 57 19 Page 2
40 CFR 262.34 Standards Applicable to Generators of Hazardous Waste-Accumulation Time
40 CFR 263 Standards Applicable to Transporters of Hazardous
Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of
Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Standards for the Management of Specific Hazardous
Wastes and Specific Types of Hazardous Waste Management Facilities
40 CFR 268 Land Disposal Restrictions
40 CFR 273 Standards For Universal Waste Management
40 CFR 273.2 Standards for Universal Waste Management - Batteries
40 CFR 273.4 Standards for Universal Waste Management - Mercury
Containing Equipment
40 CFR 273.5 Standards for Universal Waste Management - Lamps
40 CFR 279 Standards for the Management of Used Oil
40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan
40 CFR 403 General Pretreatment Regulations for Existing and New
Sources of Pollution
40 CFR 50 National Primary and Secondary Ambient Air Quality Standards
40 CFR 60 Standards of Performance for New Stationary Sources
40 CFR 61 National Emission Standards for Hazardous Air
Pollutants
40 CFR 63 National Emission Standards for Hazardous Air Pollutants for Source Categories
Section 01 57 19 Page 3
40 CFR 64 Compliance Assurance Monitoring
40 CFR 745 Lead-Based Paint Poisoning Prevention in Certain
Residential Structures
40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 172.101 Hazardous Material Regulation-Purpose and Use of
Hazardous Material Table
49 CFR 173 Shippers - General Requirements for Shipments and Packagings
49 CFR 178 Specifications for Packagings
1.2 DEFINITIONS
1.2.1 Class I and II Ozone Depleting Substance (ODS)
Class I ODS is defined in Section 602(a) of The Clean Air Act. A list of Class I ODS can be found on the EPA website at the following weblink.
http://www.epa.gov/ozone/science/ods/classone.html.
Class II ODS is defined in Section 602(s) of The Clean Air Act. A list of Class II ODS can be found on the EPA website at the following weblink.
http://www.epa.gov/ozone/science/ods/classtwo.html.
1.2.2 Contractor Generated Hazardous Waste
Contractor generated hazardous waste is materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e.
methyl ethyl ketone, toluene), waste thinners, excess paints, excess solvents, waste solvents, excess pesticides, and contaminated pesticide equipment rinse water.
http://www.epa.gov/ozone/science/ods/classone.html http://www.epa.gov/ozone/science/ods/classtwo.html
Section 01 57 19 Page 4
1.2.3 Electronics Waste
Electronics waste is discarded electronic devices intended for salvage, recycling, or disposal.
1.2.4 Environmental Pollution and Damage
Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally or historically.
1.2.5 Environmental Protection
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste;
radiant energy and radioactive material as well as other pollutants.
1.2.6 Hazardous Debris
As defined in paragraph SOLID WASTE, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) in accordance with 40 CFR
261. Hazardous debris also includes debris that exhibits a characteristic of hazardous waste in accordance with 40 CFR 261.
1.2.7 Hazardous Materials
Hazardous materials as defined in 49 CFR 171 and listed in 49 CFR 172.
Hazardous material is any material that: Is regulated as a hazardous material in accordance with 49 CFR 173; or requires a Safety Data Sheet (SDS) in accordance with 29 CFR 1910.120; or during end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, C, or D. Designation of a material by this definition, when separately regulated or controlled by other sections or directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this section for "control" purposes. Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).
1.2.8 Hazardous Waste
Section 01 57 19 Page 5
Hazardous Waste is any material that meets the definition of a solid waste and exhibit a hazardous characteristic (ignitability, corrosivity, reactivity, or toxicity) as specified in 40 CFR 261, Subpart C, or contains a listed hazardous waste as identified in 40 CFR 261, Subpart D.
1.2.9 Land Application
Land Application means spreading or spraying discharge water at a rate that allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur. Comply with federal, state, and local laws and regulations.
1.2.10 National Pollutant Discharge Elimination System (NPDES)
The NPDES permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.
1.2.11 Oily Waste
Oily waste are those materials that are, or were, mixed with Petroleum, Oils, and Lubricants (POLs) and have become separated from that POLs. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, POLs and may be appropriately tested and discarded in a manner which is in compliance with other state and local requirements.
This definition includes materials such as oily rags, "kitty litter" sorbent clay and organic sorbent material. These materials may be land filled provided that: It is not prohibited in other state regulations or local ordinances; the amount generated is "de minimus" (a small amount); it is the result of minor leaks or spills resulting from normal process operations; and free-flowing oil has been removed to the practicable extent possible. Large quantities of this material, generated as a result of a major spill or in lieu of proper maintenance of the processing equipment, are a solid waste. As a solid waste, perform a hazardous waste determination prior to disposal. As this can be an expensive process, it is recommended that this type of waste be minimized through good housekeeping practices and employee education.
1.2.12 Regulated Waste
Regulated waste are solid wastes that have specific additional federal, state, or local controls for handling, storage, or disposal.
1.2.13 Sediment
Sediment is soil and other debris that have eroded and have been transported by runoff water or wind.
Section 01 57 19 Page 6
1.2.14 Solid Waste
Solid waste is a solid, liquid, semi-solid or contained gaseous waste. A solid waste can be a hazardous waste, non-hazardous waste, or non-Resource Conservation and Recovery Act (RCRA) regulated waste. Types of solid waste typically generated at construction sites may include:
1.2.14.1 Debris
Debris is non-hazardous solid material generated during the construction, demolition, or renovation of a structure that exceeds 2.5-inch particle size that is: a manufactured object;
plant or animal matter; or natural geologic material (for example, cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials [may][may not] be reinforced with or contain ferrous wire, rods, accessories and weldments. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.
1.2.14.2 Green Waste
Green waste is the vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots.
Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.
1.2.14.3 Material not regulated as solid waste
Material not regulated as solid waste is nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended; suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges;
regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.
1.2.14.4 Non-Hazardous Waste
Non-hazardous waste is waste that is excluded from, or does not meet, hazardous waste criteria in accordance with 40 CFR 263.
1.2.14.5 Recyclables
Recyclables are materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable,[ wiring,][ insulated/non-insulated copper wire cable,][ wire rope,] and structural components. It also includes commercial-grade refrigeration equipment with Freon removed, household appliances where the basic material content is metal, clean polyethylene
Section 01 57 19 Page 7 terephthalate bottles, cooking oil, used fuel oil, textiles, high-grade paper products and corrugated cardboard, stackable pallets in good condition, clean crating material, and clean rubber/vehicle tires. Metal meeting the definition of lead contaminated or lead based paint contaminated [may][may not] be included as recyclable if sold to a scrap metal company.
Paint cans that meet the definition of empty containers in accordance with 40 CFR 261.7 may be included as recyclable if sold to a scrap metal company.
1.2.14.6 Surplus Soil
Surplus soil is existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars, and paving.
Contaminated soil meeting the definition of hazardous material or hazardous waste is not included and must be managed in accordance with paragraph HAZARDOUS MATERIAL
MANAGEMENT.
1.2.14.7 Scrap Metal
This includes scrap and excess ferrous and non-ferrous metals such as reinforcing steel, structural shapes, pipe, and wire that are recovered or collected and disposed of as scrap.
Scrap metal meeting the definition of hazardous material or hazardous waste is not included.
1.2.14.8 Wood
Wood is dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included. Treated wood includes, but is not limited to, lumber, utility poles, crossties, and other wood products with chemical treatment.
1.2.15 Surface Discharge
Surface discharge means discharge of water into drainage ditches, storm sewers, creeks or "waters of the United States". Surface discharges are discrete, identifiable sources and require a permit from the governing agency. Comply with federal, state, and local laws and regulations.
1.2.16 Wastewater
Wastewater is the used water and solids from a community that flow to a treatment plant.
1.2.16.1 Stormwater
Stormwater is any precipitation in an urban or suburban area that does not evaporate or soak into the ground, but instead collects and flows into storm drains, rivers, and streams.
1.2.17 Waters of the United States
Section 01 57 19 Page 8
Waters of the United States means Federally jurisdictional waters, including wetlands, that are subject to regulation under Section 404 of the Clean Water Act or navigable waters, as defined under the Rivers and Harbors Act.
1.2.18 Wetlands
Wetlands are those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.
1.2.19 Universal Waste
The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (for example, thermostats), and lamps (for example, fluorescent bulbs). The rule is designed to reduce hazardous waste in the municipal solid waste (MSW) stream by making it easier for universal waste handlers to collect these items and send them for recycling or proper disposal.
These regulations can be found at 40 CFR 273.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, during the life of the contract, environmental protection as defined.
Plan for and provide environmental protective measures to control pollution that develops during construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by law, the laboratories must be certified.
1.4.1 Conformance with the Environmental Management System
Section 01 57 19 Page 9
Perform work under this contract consistent with the policy and objectives identified in the installation's Environmental Management System (EMS). Perform work in a manner that conforms to objectives and targets of the environmental programs and operational controls identified by the EMS. Support Government personnel when environmental compliance and EMS audits are conducted by escorting auditors at the Project site, answering questions, and providing proof of records being maintained. Provide monitoring and measurement information as necessary to address environmental performance relative to environmental, energy, and transportation management goals. In the event an EMS nonconformance or environmental noncompliance associated with the contracted services, tasks, or actions occurs, take corrective and preventative actions. In addition, employees must be aware of their roles and responsibilities under the installation EMS and of how these EMS roles and responsibilities affect work performed under the contract.
Coordinate with the installation's EMS coordinator, (208)828-6351, to identify training needs associated with environmental aspects and the EMS, and arrange training or take other action to meet these needs. Provide training documentation to the Contracting Officer. Mountain Home Air Force Base Environmental Management Office (A7IE) will retain associated environmental compliance records. Make EMS Awareness training completion certificates available to Government auditors during EMS audits and include the certificates in the Employee Training Records. See paragraph EMPLOYEE TRAINING RECORDS.
1.5 QUALITY ASSURANCE
1.5.1 Reserved.
1.5.2 Regulatory Notifications
Provide regulatory notification requirements in accordance with federal, state and local regulations. Submit copies of regulatory notifications to the Contracting Officer at least 14 days prior to commencement of work activities. Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).
1.5.3 Reserved.
1.5.4 Reserved.
1.5.5 Employee Training Records
1.5.6 Non-Compliance Notifications
The Contracting Officer will notify the Contractor in writing of any observed noncompliance with federal, state or local environmental laws or regulations, permits, and other elements of the Contractor's EPP. After receipt of such notice, inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer.
Section 01 57 19 Page 10
The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.
1.6 RESERVED.
1.6.2 General Site Information
1.6.2.1 Reserved
1.6.2.2 Reserved.
1.6.2.3 Reserved.
1.6.3 Reserved
1.6.4 Reserved.
1.6.5 Reserved.
1.6.6 Reserved.
1.6.7 Prevention of Releases to the Environment
Procedures to prevent releases to the environment include development of a MHAFB Contractor Site Specific Contingency Plan to provide procedures, instructions, and reports to be used in the event of an unforeseen spill/release of a substance (40 CFR 68, 40 CFR 302, and 40 CFR 355).
Notifications in the event of a release to the environment
1.6.8 Regulatory Notification and Permits
List what notifications and permit applications must be made. Some permits require up to 180 days to obtain. Demonstrate that those permits have been obtained or applied for by including copies of applicable environmental permits. The EPP will not be approved until the permits have been obtained.
1.6.9 Clean Air Act Compliance
Section 01 57 19 Page 11
1.6.9.1 Haul Route
Submit truck and material haul routes along with a Dirt and Dust Control Plan for controlling dirt, debris, and dust on Installation roadways. As a minimum, identify in the plan the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadways.
1.6.9.2 Pollution Generating Equipment
Identify air pollution generating equipment or processes that may require federal, state, or local permits under the Clean Air Act. Determine requirements based on any current installation permits and the impacts of the project. Provide a list of all fixed or mobile equipment, machinery or operations that could generate air emissions during the project to the Contracting Officer.
1.6.9.3 Stationary Internal Combustion Engines
Identify portable and stationary internal combustion engines that will be supplied, used or serviced. Comply with 40 CFR 60 Subpart IIII, 40 CFR 60 Subpart JJJJ, 40 CFR 63 Subpart ZZZZ, and local regulations as applicable. At minimum, include the make, model, serial number, manufacture date, size (engine brake horsepower), and EPA emission certification status of each engine. Maintain applicable records and log hours of operation and fuel use.
Logs must include reasons for operation and delineate between emergency and non-emergency operation.
1.6.9.4 Reserved.
1.6.9.5 Air Pollution-engineering Processes
Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions). Log hours of operations and track quantities of materials used.
1.6.9.6 Compliant Materials
Provide the Government a list of and SDSs for all hazardous materials proposed for use on site. Materials must be compliant with all Clean Air Act regulations for emissions including solvent and volatile organic compound contents, and applicable National Emission Standards for Hazardous Air Pollutants requirements. The Government may alter or limit use of specific materials as needed to meet installation permit requirements for emissions.
1.7 LICENSES AND PERMITS
Section 01 57 19 Page 12
Obtain licenses and permits required for the construction of the project and in accordance with FAR 52.236-7 Permits and Responsibilities. Notify the Government of all general use permitted equipment the Contractor plans to use on site. This paragraph supplements the Contractor's responsibility under FAR 52.236-7 Permits and Responsibilities.
1.8 RESERVED.
1.9 RESERVED.
1.9.1 Reserved.
1.10 FACILITY HAZARDOUS WASTE GENERATOR STATUS
MHAFB is designated as a Large Quantity Generator. Meet the regulatory requirements of this generator designation for any work conducted within the boundaries of this Installation.
Comply with provisions of federal, state, and local regulatory requirements applicable to this generator status regarding training and storage, handling, and disposal of construction derived wastes.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 PROTECTION OF NATURAL RESOURCES
Minimize interference with, disturbance to, and damage to fish, wildlife, and plants including their habitat to protect threatened, endangered, species of concern, migratory birds, or otherwise protected animal and plant species, including their habitat in accordance with the MHAFB Integrated Natural Resources Management Plan (INRMP), federal, state, regional, and local laws and regulations. Protection of migratory birds, particularly burrowing owls, is of concern on MHAFB. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility.
Confine activities, equipment staging, and material staging within pre-approved site boundaries. Any unapproved or unnecessary destruction of land resources shall be corrected at the Contractor's expense to the satisfaction of the Contracting Officer.
Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work that is consistent with the requirements of the MHAFB Environmental Management Office or as otherwise specified.
Section 01 57 19 Page 13
Do not destroy any occupied bird nests. Burrowing owls may be present from March through July and occupy abandoned badger holes. Coordinate with the Contracting Officer in February or March to perform site surveys for burrows or nests in order to prevent conflicts during construction.
Do not disturb, drive through, or fill areas designated as wetlands, for example playas.
3.1.1 Vegetation
Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer and Installation Environmental Management Office. Where such use of attached ropes, cables, or guys is authorized, the Contractor is responsible for any resultant damage.
Protect existing trees that are to remain to ensure they are not injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas.
Coordinate with the Contracting Officer and Installation Environmental Office to determine appropriate action for trees and other landscape features scarred or damaged by equipment operations.
Do not kill, drive on, burn, or otherwise destroy sagebrush.
Coordinate with the Contracting Officer and Installation Environmental Management Office regarding suitable herbicide pretreatment, seed mixes, seeding method, and timing for post construction soil stabilization.
3.2 RESERVED.
3.2.1 Reserved.
3.2.1.1 Reserved.
3.2.1.2 Reserved.
3.2.1.3 Reserved.
3.2.1.4 Reserved.
3.2.1.5 Reserved.
Section 01 57 19 Page 14
3.2.2 Reserved.
3.2.2.1 Reserved.
3.2.2.2 Reserved.
3.2.3 Reserved.
3.2.4 Reserved.
3.3 RESERVED.
3.3.1 Reserved.
3.3.2 Waters of the United States
Do not enter, disturb, destroy, or allow discharge of contaminants into waters of the United States.
3.4 RESERVED.
3.4.1 Reserved.
3.4.2 Reserved.
3.5 AIR RESOURCES
Equipment operation, activities, or processes will be in accordance with 40 CFR 64 and
IDAPA 58.01.01.
3.5.1 Reserved.
3.5.2 Reserved.
3.5.3 Burning
Burning is prohibited on MHAFB.
Section 01 57 19 Page 15
3.5.4 Class I and II ODS Prohibition
Class I and II ODS are Government property and must be returned to the Government for appropriate management. Coordinate with the Installation Environmental Office to determine the appropriate location for turn in of all reclaimed refrigerant.
3.5.5 Accidental Venting of Refrigerant
Accidental venting of a refrigerant is a release and must be reported immediately to the Contracting Officer.
3.5.6 Reserved.
3.5.7 Reserved.
3.5.7.1 Reserved.
3.5.7.2 Reserved.
3.5.8 Reserved.
3.6 WASTE MINIMIZATION
Minimize the use of hazardous materials and the generation of waste. Include procedures for pollution prevention/ hazardous waste minimization in the Hazardous Waste Management Section of the EPP.
3.6.1 Salvage, Reuse and Recycle
Identify anticipated materials and waste for salvage, reuse, and recycling. Describe actions to promote material reuse, resale or recycling. To the extent practicable, all scrap metal must be sent for reuse or recycling and will not be disposed of in a landfill.
Include the name, physical address, and telephone number of the hauler, if transported by a franchised solid waste hauler. Include the destination and, unless exempted, provide a copy of the state or local permit (cover) or license for recycling.
3.6.2 Reserved.
3.7 RESERVED.
3.7.1 Reserved.
3.7.1.1 Reserved.
Section 01 57 19 Page 16
3.7.1.1.1 Reserved.
3.7.1.1.2 Reserved.
3.7.1.1.3 Reserved.
3.7.2 Reserved.
3.7.2.1 Reserved.
3.7.2.2 Control and Management of Solid Wastes
Pick up solid wastes, and place in covered containers that are regularly emptied. Do not prepare or cook food on the project site. Prevent contamination of the site or other areas when handling and disposing of wastes. At project completion, leave the areas clean. Employ segregation measures so that no hazardous or toxic waste will become co-mingled with non-hazardous solid waste. Transport solid waste off Government property and dispose of it in compliance with 40 CFR 260, state, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill is the minimum acceptable offsite solid waste disposal option. Verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. Solid waste disposal offsite must comply with most stringent local, state, and federal requirements, including 40 CFR 241, 40 CFR 243, and 40 CFR 258.
Manage hazardous material used in construction, including but not limited to, aerosol cans, waste paint, cleaning solvents, contaminated brushes, and used rags, in accordance with 49
CFR 173.
3.7.3 Control and Management of Hazardous Waste
Do not dispose of hazardous waste on Government property. Do not discharge any waste to a sanitary sewer, storm drain, or to surface waters or conduct waste treatment or disposal on Government property without written approval of the Contracting Officer.
3.7.3.1 Reserved.
3.7.3.2 Waste Storage/Satellite Accumulation/90 Day Storage Areas
Accumulate hazardous waste at satellite accumulation points and in compliance with 40 CFR
262.34 and applicable state or local regulations. Individual waste streams will be limited to 55 gallons of accumulation (or 1 quart for acutely hazardous wastes). If the Contractor expects to generate hazardous waste at a rate and quantity that makes satellite accumulation impractical, the Contractor may request a temporary 90 day accumulation point be established. Submit a request in writing to the Contracting Officer and provide the following information (Attach Site Plan to the Request):
Section 01 57 19 Page 17
Contract Number [_____]
Contractor [_____]
Haz/Waste or Regulated Waste POC [_____]
Phone Number [_____]
Type of Waste [_____]
Source of Waste [_____]
Emergency POC [_____]
Phone Number [_____]
Location of the Site [_____]
Attach a Waste Determination form for the expected waste streams. Allow 10 working days for processing this request. Additional compliance requirements (e.g. training and contingency planning) that may be required are the responsibility of the Contractor. Barricade the designated area where waste is being stored and post a sign identifying as follows:
"DANGER - UNAUTHORIZED PERSONNEL KEEP OUT"
3.7.3.3 Hazardous Waste Disposal
3.7.3.3.1 Responsibilities for Contractor's Disposal
Provide hazardous waste manifest to the Installations Environmental Management Office for review, approval, and signature prior to shipping waste off Government property.
3.7.3.3.1.1 Services
Provide service necessary for the final treatment or disposal of the hazardous material or waste in accordance with 40 CFR 260, local, and state, laws and regulations, and the terms and conditions of the Contract within 60 days after the materials have been generated. These services include necessary personnel, labor, transportation, packaging, detailed analysis (if required for disposal or transportation, include manifesting or complete waste profile sheets, equipment, and compile documentation).
3.7.3.3.1.2 Samples
Obtain a representative sample of the material generated for each job done to provide waste stream determination.
Section 01 57 19 Page 18
3.7.3.3.1.3 Analysis
Analyze each sample taken and provide analytical results to the Contracting Officer. See paragraph WASTE DETERMINATION DOCUMENTATION.
3.7.3.3.1.4 Labeling
Determine the Department of Transportation's (DOT's) proper shipping names for waste (each container requiring disposal) and demonstrate to the Contracting Officer how this determination is developed and supported by the sampling and analysis requirements contained herein. Label all containers of hazardous waste with the words "Hazardous Waste" or other words to describe the contents of the container in accordance with 40 CFR 262.31 and applicable state or local regulations.
3.7.3.3.2 Contractor Disposal Turn-In Requirements
Hazardous waste generated must be disposed of in accordance with the following conditions to meet installation requirements:
a. Drums must be compatible with waste contents and drums must meet DOT requirements for 49 CFR 173 for transportation of materials.
b. Band drums to wooden pallets.
c. No more than three 55 gallon drums or two 85 gallon over packs are to be banded to a pallet.
d. Band using 1-1/4 inch minimum band on upper third of drum.
e. Provide label in accordance with 49 CFR 172.101.
f. Leave 3 to 5 inches of empty space above volume of material.
3.7.3.4 Universal Waste Management
Manage the following categories of universal waste in accordance with federal, state, and local requirements and installation instructions:
a. Batteries as described in 40 CFR 273.2
b. Lamps as described in 40 CFR 273.5
c. Mercury-containing equipment as described in 40 CFR 273.4
Section 01 57 19 Page 19
Mercury is prohibited in the construction of this facility, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed.
3.7.3.5 Electronics End-of-Life Management
Recycle or dispose of electronics waste, including, but not limited to, used electronic devices such computers, monitors, hard-copy devices, televisions, mobile devices, in accordance with 40 CFR 260-262, state, and local requirements, and installation instructions.
3.7.3.6 Disposal Documentation for Hazardous and Regulated Waste
Contact the Contracting Officer for the facility RCRA identification number that is to be used on each manifest.
Submit a copy of the applicable EPA and or state permit(s), manifest(s), or license(s) for transportation, treatment, storage, and disposal of hazardous and regulated waste by permitted facilities. Hazardous or toxic waste manifests must be reviewed, signed, and approved by the Contracting Officer before the Contractor may ship waste. To obtain specific disposal instructions, coordinate with the Installation Environmental Office.
3.7.4 Releases/Spills of Oil and Hazardous Substances
3.7.4.1 Response and Notifications
Exercise due diligence to prevent, contain, and respond to spills of hazardous material, hazardous substances, hazardous waste, sewage, regulated gas, petroleum, lubrication oil, and other substances regulated in accordance with 40 CFR 300. Maintain spill cleanup equipment and materials at the work site. In the event of a spill, take prompt, effective action to stop, contain, curtail, or otherwise limit the amount, duration, and severity of the spill/release. In the event of any releases of oil and hazardous substances, chemicals, or gases; immediately (within 15 minutes) notify the Installation Fire Department, the Installation Environmental Office, the Contracting Officer.
Submit written notification to the Contracting Officer of all spills regardless of substance or quantity using the MHAFB Environmental Hazardous Material Release Report. Contain and clean up these spills without cost to the Government.
3.7.4.2 Clean Up
Clean up hazardous and non-hazardous waste spills. Reimburse the Government for costs incurred including sample analysis materials, clothing, equipment, and labor if the Government will initiate its own spill cleanup procedures, for Contractor- responsible spills, Section 01 57 19 Page 20 when: Spill cleanup procedures have not begun within one hour of spill discovery/occurrence;
or, in the Government's judgment, spill cleanup is inadequate and the spill remains a threat to human health or the environment.
3.7.5 Mercury Materials
Immediately report to the Contracting Officer instances of breakage or mercury spillage.
Clean mercury spill area to the satisfaction of the Contracting Officer.
Do not recycle a mercury spill cleanup; manage it as a hazardous waste for disposal.
3.7.6 Reserved.
3.7.6.1 Reserved.
3.7.6.1.1 Reserved.
3.7.6.1.2 Reserved.
3.8 RESERVED.
3.8.1 Reserved.
3.9 RESERVED.
3.10 RESERVED.
3.11 RESERVED.
3.12 RESERVED.
3.13 RESERVED.
3.14 MILITARY MUNITIONS
In the event military munitions, as defined in 40 CFR 260, are discovered or uncovered, immediately stop work in that area and immediately inform the Contracting Officer.
3.15 PETROLEUM, OIL, LUBRICANT (POL) STORAGE AND FUELING
POL products include flammable or combustible liquids, such as gasoline, diesel, lubricating oil, used engine oil, hydraulic oil, mineral oil, and cooking oil. Store POL products and fuel equipment and motor vehicles in a manner that affords the maximum protection against spills into the environment. Manage and store POL products in accordance with EPA 40 CFR 112, and other federal, state, regional, and local laws and regulations. Use secondary containments, Section 01 57 19 Page 21 dikes, curbs, and other barriers, to prevent POL products from spilling and entering the ground, storm or sewer drains, stormwater ditches or canals, or navigable waters of the United States. Describe in the EPP (see paragraph ENVIRONMENTAL PROTECTION PLAN) how POL tanks and containers must be stored, managed, and inspected and what protections must be provided.Storage of fuel on the project site must be in accordance with EPA, state, and local laws and regulations and paragraph OIL STORAGE INCLUDING FUEL TANKS.
3.15.1 Used Oil Management
Manage used oil generated on site in accordance with 40 CFR 279. Determine if any used oil generated while onsite exhibits a characteristic of hazardous waste. Used oil containing 1,000 parts per million of solvents is considered a hazardous waste and disposed of at the Contractor's expense. Used oil mixed with a hazardous waste is also considered a hazardous waste. Dispose in accordance with paragraph HAZARDOUS WASTE DISPOSAL.
3.15.2 Oil Storage Including Fuel Tanks
Provide secondary containment and overfill protection for oil storage tanks. A berm used to provide secondary containment must be of sufficient size and strength to contain the contents of the tanks plus 5 inches freeboard for precipitation. Construct the berm to be impervious to oil for 72 hours that no discharge will permeate, drain, infiltrate, or otherwise escape before cleanup occurs. Use drip pans during oil transfer operations; adequate absorbent material must be onsite to clean up any spills and prevent releases to the environment. Cover tanks and drip pans during inclement weather. Provide procedures and equipment to prevent overfilling of tanks. If tanks and containers with an aggregate aboveground capacity greater than 1320 gallons will be used onsite (only containers with a capacity of 55 gallons or greater are counted), provide and implement a SPCC plan meeting the requirements of 40 CFR 112. Do not bring underground storage tanks to the installation for Contractor use during a project.
Submit the SPCC plan to the Contracting Officer for approval.
Monitor and remove any rainwater that accumulates in open containment dikes or berms.
Inspect the accumulated rainwater prior to draining from a containment dike to the environment, to determine there is no oil sheen present.
3.16 RESERVED.
3.17 PEST MANAGEMENT
In order to minimize impacts to existing fauna and flora, coordinate with the Installation Pest Management Coordinator (IPMC), through the Contracting Officer, at the earliest possible time prior to pesticide application. Discuss integrated pest management strategies with the IPMC and receive concurrence from the IPMC through the Contracting Officer prior to the application of any pesticide associated with these specifications. Provide Installation Project Office Pest Management personnel the opportunity to be present at meetings concerning treatment measures for pest or disease control and during application of the pesticide. The use and management of pesticides are regulated under 40 CFR 152 - 186.
Section 01 57 19 Page 22
3.17.1 Application
Apply pesticides using a state-certified pesticide applicator in accordance with EPA label restrictions and recommendation. The certified applicator must wear clothing and personal protective equipment as specified on the pesticide label. The Contracting Officer will designate locations for water used in formulating. Do not allow the equipment to overflow.
Inspect equipment for leaks, clogging, wear, or damage and repair prior to application of pesticide.
3.17.2 Pesticide Treatment Plan
Include and update a pesticide treatment plan, as information becomes available. Include in the plan the sequence of treatment, dates, times, locations, pesticide trade name, EPA registration numbers, authorized uses, chemical composition, formulation, original and applied concentration, application rates of active ingredient (that is, pounds of active ingredient applied), equipment used for application and calibration of equipment. Comply with 40 CFR 152-189, state, regional, and local pest management record-keeping and reporting requirements as well as any additional Installation Project Office specific requirements for data required to be reported to the Installation.
Spray tank filling may only be conducted at MHAFB Entomology building (#1337) from Monday to Friday, 0700hrs to 1530hrs. To coordinate, contact Mr. David Ash, IPMC, at (208)828-6300.
3.18 RESERVED.
3.19 RESERVED.
3.20 RESERVED.
-- End of Section --
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Class I and II Ozone Depleting Substance (ODS) |
| 1.2.2 Contractor Generated Hazardous Waste |
| 1.2.3 Electronics Waste |
| 1.2.4 Environmental Pollution and Damage |
| 1.2.5 Environmental Protection |
| 1.2.6 Hazardous Debris |
| 1.2.7 Hazardous Materials |
| 1.2.8 Hazardous Waste |
| 1.2.9 Land Application |
| 1.2.10 National Pollutant Discharge Elimination System (NPDES) |
| 1.2.11 Oily Waste |
| 1.2.12 Regulated Waste |
| 1.2.13 Sediment |
| 1.2.14 Solid Waste |
| 1.2.14.1 Debris |
| 1.2.14.2 Green Waste |
| 1.2.14.3 Material not regulated as solid waste |
| 1.2.14.4 Non-Hazardous Waste |
| 1.2.14.5 Recyclables |
| 1.2.14.6 Surplus Soil |
| 1.2.14.7 Scrap Metal |
| 1.2.14.8 Wood |
| 1.2.15 Surface Discharge |
| 1.2.16 Wastewater |
| 1.2.16.1 Stormwater |
| 1.2.17 Waters of the United States |
| 1.2.18 Wetlands |
| 1.2.19 Universal Waste |
| 1.3 SUBMITTALS |
| 1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS |
| 1.4.1 Conformance with the Environmental Management System |
| 1.5 QUALITY ASSURANCE |
| 1.5.1 Reserved. |
| 1.5.2 Regulatory Notifications |
| 1.5.3 Reserved. |
| 1.5.4 Reserved. |
| 1.5.5 Employee Training Records |
| 1.5.6 Non-Compliance Notifications |
| 1.6 Reserved. |
| 1.6.2 General Site Information |
| 1.6.2.1 Reserved |
| 1.6.2.2 Reserved. |
| 1.6.2.3 Reserved. |
| 1.6.3 Reserved |
| 1.6.4 Reserved. |
| 1.6.5 Reserved. |
| 1.6.6 Reserved. |
| 1.6.7 Prevention of Releases to the Environment |
| 1.6.8 Regulatory Notification and Permits |
| 1.6.9 Clean Air Act Compliance |
| 1.6.9.1 Haul Route |
| 1.6.9.2 Pollution Generating Equipment |
| 1.6.9.3 Stationary Internal Combustion Engines |
| 1.6.9.4 Reserved. |
| 1.6.9.5 Air Pollution-engineering Processes |
| 1.6.9.6 Compliant Materials |
| 1.7 LICENSES AND PERMITS |
| 1.8 Reserved. |
| 1.9 Reserved. |
| 1.9.1 Reserved. |
1.10 FACILITY HAZARDOUS WASTE GENERATOR STATUS
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 PROTECTION OF NATURAL RESOURCES |
| 3.1.1 Vegetation |
| 3.2 Reserved. |
| 3.2.1 Reserved. |
| 3.2.1.1 Reserved. |
| 3.2.1.2 Reserved. |
| 3.2.1.3 Reserved. |
| 3.2.1.4 Reserved. |
| 3.2.1.5 Reserved. |
| 3.2.2 Reserved. |
| 3.2.2.1 Reserved. |
| 3.2.2.2 Reserved. |
| 3.2.3 Reserved. |
| 3.2.4 Reserved. |
| 3.3 Reserved. |
| 3.3.1 Reserved. |
| 3.3.2 Waters of the United States |
| 3.4 Reserved. |
| 3.4.1 Reserved. |
| 3.4.2 Reserved. |
| 3.5 AIR RESOURCES |
| 3.5.1 Reserved. |
| 3.5.2 Reserved. |
| 3.5.3 Burning |
| 3.5.4 Class I and II ODS Prohibition |
| 3.5.5 Accidental Venting of Refrigerant |
| 3.5.6 Reserved. |
| 3.5.7 Reserved. |
| 3.5.7.1 Reserved. |
| 3.5.7.2 Reserved. |
3.5.8 Reserved.
| 3.6 WASTE MINIMIZATION |
| 3.6.1 Salvage, Reuse and Recycle |
| 3.6.2 Reserved. |
| 3.7 Reserved. |
| 3.7.1 Reserved. |
| 3.7.1.1 Reserved. |
| 3.7.1.1.1 Reserved. |
| 3.7.1.1.2 Reserved. |
| 3.7.1.1.3 Reserved. |
| 3.7.2 Reserved. |
| 3.7.2.1 Reserved. |
| 3.7.2.2 Control and Management of Solid Wastes |
| 3.7.3 Control and Management of Hazardous Waste |
| 3.7.3.1 Reserved. |
| 3.7.3.2 Waste Storage/Satellite Accumulation/90 Day Storage Areas |
| 3.7.3.3 Hazardous Waste Disposal |
| 3.7.3.3.1 Responsibilities for Contractor's Disposal |
| 3.7.3.3.1.1 Services |
| 3.7.3.3.1.2 Samples |
| 3.7.3.3.1.3 Analysis |
| 3.7.3.3.1.4 Labeling |
3.7.3.3.2 Contractor Disposal Turn-In Requirements
| 3.7.3.4 Universal Waste Management |
| 3.7.3.5 Electronics End-of-Life Management |
| 3.7.3.6 Disposal Documentation for Hazardous and Regulated Waste |
| 3.7.4 Releases/Spills of Oil and Hazardous Substances |
| 3.7.4.1 Response and Notifications |
| 3.7.4.2 Clean Up |
| 3.7.5 Mercury Materials |
| 3.7.6 Reserved. |
| 3.7.6.1 Reserved. |
| 3.7.6.1.1 Reserved. |
| 3.7.6.1.2 Reserved. |
| 3.8 Reserved. |
| 3.8.1 Reserved. |
| 3.9 Reserved. |
| 3.10 Reserved. |
| 3.11 Reserved. |
| 3.12 Reserved. |
| 3.13 Reserved. |
| 3.14 MILITARY MUNITIONS |
| 3.15 PETROLEUM, OIL, LUBRICANT (POL) STORAGE AND FUELING |
| 3.15.1 Used Oil Management |
| 3.15.2 Oil Storage Including Fuel Tanks |
| 3.16 Reserved. |
| 3.17 PEST MANAGEMENT |
| 3.17.1 Application |
| 3.17.2 Pesticide Treatment Plan |
| 3.18 Reserved. |
| 3.19 Reserved. |
| 3.20 RESERVED. |