This is a Standard Form 30 (SF 30) amendment to solicitation FA488726Q0008, issued by the U.S. Air Force 56th Contracting Squadron at Luke Air Force Base, Arizona. The amendment is effective January 21, 2026, and was issued to modify the evaluation criteria for the solicitation. The amendment does not extend the offer receipt deadline.
The primary purpose of this amendment is to remove past performance from the evaluation criteria under Federal Acquisition Regulation (FAR) clause 52.212-2, Evaluation-Commercial Products and Commercial Services. The revised evaluation methodology establishes two evaluation factors: (1) Technical Acceptability, scored on a 1-10 scale based on the proposal's conformance to performance work statement specifications and the proposed layout meeting the 2026 air show needs; and (2) Price, with contract award to be made to the technically acceptable contractor (minimum score of 5) with a Green or better Supplier Performance Risk System (SPRS) rating and the lowest Total Evaluated Price (TEP). The evaluation process consists of two steps: proposals are submitted for technical evaluation, followed by award to the lowest TEP among technically acceptable offers. The government reserves the right to evaluate option pricing and conduct tradeoff analysis among technically acceptable proposals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Evaluation Factors for Award
Additional Regulation or Supplemental Clauses Incorporated by Full Text
The following Clause modifications were made:
52.212-2 Evaluation-Commercial Products and Commercial Services. Nov 2021 hereby reads as follows:
Evaluation-Commercial Products and Commercial Services (Nov 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
The Government will award a contract resulting from this solicitation to the responsible offeror whose proposal conforming to the solicitation will be most advantageous to the Government, price and other factors considered. Contract award will be made to the contractor found technically acceptable with a Green or better Supplier Performance Risk System(SPRS) rating with the lowest price. Technical rating will not be an evaluation factor but rather it will first be determined whether or not the contractor meets technical acceptability and then the proposal will be evaluated based on the evaluation factor; price. The government will conduct a tradeoff analysis of the price factors of technically acceptable proposals.
The following factors shall be used to evaluate offers:
1) Technical Acceptability
2) Price
1) Technical acceptance is based on the proposal conforming to the overall specifications set forth in the performance work statement. The contractor should indicate that their proposal meets all specifications. The requiring activity will determine technical acceptability based on the proposed layout meeting the needs of the 2026 air show. The proposals will receive a technical acceptability score between 1-10.
2) Price - Contract award will be made to the contractor found technically acceptable with a score of 5 or better for technical acceptability, with a Green or better SPRS rating, with the lowest Total Evaluated Price (TEP). An offeror's Total Evaluated Price (TEP) will be determined by the sum of all separately priced CLINS as presented in Supplies/services section. If a separate CLIN and a TEP (as applicable) are not included, or are not clearly stated, miscalculated and/or understandable, the offer will be rejected as non-responsive.
Evaluation Process:
Step 1: Proposals received and sent for technical evaluation.
Step 2: Award to lowest TEP.
(b) . The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Options Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
FA488726Q00080001
| SUMMARY OF CHANGES |
| Evaluation Factors for Award |
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0001 |
| EffDate: 21 Jan 2026 |
| ReqNo: |
| ProjNo: |
| IssCode: FA4887 |
| AdmCode: |
| IssuedBy: FA4887 56 CONS CC |
14100 W EAGLE ST, ADMINISTRATIVE ONLY NO REQUISITIONS
LUKE AFB, AZ 85309-1217
UNITED STATES
Jalen Johnson, Email: jalen.johnson.17@us.af.mil Telephone: 896-2748 Jacqueline Aranda, Email: jacqueline.aranda.1@us.af.mil Telephone: 6238562733 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA488726Q0008 |
| SolDate: 20 Jan 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is to remove past performance from the Evaluation Criteria, listen within clause 52.212-2, Evaluation-Commercial Products and Commercial Services. |
| ContNameTitle: |
| CoNameTitle: Jacqueline C. Aranda |
| ContDate: |
| CODate: 21 Jan 2026 |