Solicitation Amendment FA487725R00020002 SF 30.pdf

PDF 1 MB Posted

Attached to
Davis-Monthan AFB: Base-Wide Painting and CRU Flooring IDIQ
Solicitation number
FA487725R0002
Issued by

About this file

This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a base-wide painting and CRU flooring Indefinite Delivery, Indefinite Quantity (IDIQ) contract at Davis-Monthan Air Force Base. The amendment extends the solicitation proposal due date from 09 May 2025 to 23 May 2025 at 4:30 PM PST and removes the offer guarantee requirement. The solicitation is an 8(a) Small Business Set-Aside under NAICS code 238320, with a size standard of $19 million and a project magnitude between $5-10 million.

The contract requires a contractor to provide all necessary labor, materials, equipment, and supervision to complete task orders for base-wide painting and CRU flooring. A site visit is scheduled for 23 April 2025 at 10:00 AM Arizona Local Time, with strict limitations on photography and attendance (only 2 individuals per company). The project will follow a Statement of Work dated 12 March 2025, with individual task order performance periods to be negotiated at the time of each order. Interested vendors must submit documentation through the PIEE Module and follow specific vendor access instructions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is to: Block 14 (Description of Amendment/Modification):

A) Extend the solicitation by 14 calendar days from 9 May 2025 to 23 May 2025 B) Incorporating the new Solicitation Proposal due date to 23 May 2025 4:30PM PST C) Removal of Offer Guarantee as it is not required

No other changes have been made to the solicitation

Section A - Solicitation/Contract Form

The following modifications were made:

INFORMATION FROM TO

Contract Description

Project Title: DMAFB Base-Wide Painting and CRU Flooring

IDIQ

Project Location: Davis-Monthan AFB

Indefinite Delivery, Indefinite Quantity contract for a Base- Wide Painting and CRU Flooring contract at Davis-Monthan AFB, AZ. Contractor shall provide all plant, labor, material, supervision, equipment, tools and all other required elements necessary to complete Task Orders. The ordering periods for this contract shall be TBD. All ordering period dates under the CLINS are just examples. All work shall be performed in accordance with the attached Statement of Work dated 12 March 2025 and is incorporated into this contract within Section J. Individual Task Orders will be accompanied by supplement supplemental project documents at the time of the order. The performance period for each Task Order will be negotiated at the time of the order.

SBA Requirement Number: LU1743546978C This acquisition is an 8(a) Small Business Set-Aside under NAICS 238320, Size Standard - $19 million.

The project magnitude is between $5,000,000 and $10,000,000

We are scheduling a site visit for 10 AM on 23 April 2025.

All forms of photography will be strictly prohibited at the site visit unless otherwise stated. Please limit site visit attendance to the minimum necessary attendees. Only 2 individuals allowed per company. If you plan on attending, please submit the attached EAL to the POCs listed at the end of this announcement via e-mail NLT 14 April 2025 at 12:00 PM Arizona Local Time.

Site Visit: 23 April 2025 at 10:00AM on Arizona Local Time RFI Due Date: 23 April 2025 at 5:00PM Arizona Local Time Proposal Due Date: 09 May 2025 at 2:00 pm Arizona Local Time

Project Title: DMAFB Base-Wide Painting and CRU Flooring

IDIQ

Project Location: Davis-Monthan AFB

Indefinite Delivery, Indefinite Quantity contract for a Base- Wide Painting and CRU Flooring contract at Davis-Monthan AFB, AZ. Contractor shall provide all plant, labor, material, supervision, equipment, tools and all other required elements necessary to complete Task Orders. The ordering periods for this contract shall be TBD. All ordering period dates under the CLINS are just examples. All work shall be performed in accordance with the attached Statement of Work dated 12 March 2025 and is incorporated into this contract within Section J. Individual Task Orders will be accompanied by supplement supplemental project documents at the time of the order. The performance period for each Task Order will be negotiated at the time of the order.

SBA Requirement Number: LU1743546978C This acquisition is an 8(a) Small Business Set-Aside under NAICS 238320, Size Standard - $19 million.

The project magnitude is between $5,000,000 and $10,000,000

We are scheduling a site visit for 10 AM on 23 April 2025.

All forms of photography will be strictly prohibited at the site visit unless otherwise stated. Please limit site visit attendance to the minimum necessary attendees. Only 2 individuals allowed per company. If you plan on attending, please submit the attached EAL to the POCs listed at the end of this announcement via e-mail NLT 14 April 2025 at 12:00 PM Arizona Local Time.

Site Visit: 23 April 2025 at 10:00AM on Arizona Local Time RFI Due Date: 23 April 2025 at 5:00PM Arizona Local Time Proposal Due Date: 23 May 2025 at 4:30 pm Arizona Local Time

Offer Guarantee Required true Response Due Time 02:00 PM 04:30 PM Response Due Time Zone Mountain Standard Time (UTC -7) Pacific Standard Time (UTC -8) Response Due Date 09 May 2025 23 May 2025

FA487725R00020002

SUMMARY OF CHANGES
Solicitation/Contract Form
IDCode: J
Page: 1
Pages: 2
AmendNo: 0002
EffDate: 08 May 2025
ReqNo:
ProjNo: FA487725QA169
IssCode: FA4877
AdmCode:
IssuedBy: FA4877 355 CONS PK

3180 S CRAYCROFT RD BLDG 2525, CP 520 228 3131

DAVIS MONTHAN AFB, AZ 85707-3522

UNITED STATES

HANS YURI GABRIEL, Email: hans_yuri.gabriel@us.af.mil Telephone: 520 228-4185 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA487725R0002
SolDate: 04 Apr 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: Karl A. Knott
ContDate:
CODate: 08 May 2025

File details come from the government source that posted it. Updated .