This document contains responses to questions from contractors regarding a federal solicitation for repair work at a base communications headquarters facility. Key details include: the solicitation is for repair work at the Base Communications Headquarters, Facility 1540 at Davis Monthan Air Force Base; the contractor will furnish all labor, equipment, materials, and perform all operations necessary for the repairs in accordance with specifications; the site visit was on December 8, 2020 and RFIs were due by December 10, 2020 with responses posted by December 22, 2020; the bid due date is January 5, 2021 and the estimated project value is between $1,000,000 to $5,000,000; the acquisition is 100% set aside for small businesses.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Special Notice - DM Access.pdf | ||
| Attachment 11 RFI LOG_Gov Response.xlsx | XLSX spreadsheet | |
| Attachment 12 Site Visit Sign in Sheet.pdf | ||
| Solicitation Amendment FA487721B00010001 SF 30.pdf | ||
| Solicitation - FA487721B0001.pdf | ||
| 4 Bid Schedule.pdf | ||
| 5 Specifications.pdf | ||
| 7 Plans_Bldg 1540.pdf | ||
| 1 Template of Contractor EAL.xls | XLS spreadsheet | |
| 3 AF Form 3052.pdf | ||
| 9 Contractor Environmental Guide_2019.pdf | ||
| 2 WD - AZ20190032 Sep 2020.pdf | ||
| 8 Asbestos Lead Paint Survey Report.pdf | ||
| 6 DMAFB Design Guide.pdf | ||
| 10 Submittal Register.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFI LOG | |
| Solicitation FA487721B00001 |
Title Repair Base Comm HQ Fac 1540
| RFI # | Question | Contractor | Government Response |
| 1 | Can you please provide the name of the manufacture for the existing system controls in building 1540? | Pilkington Contstruction Co. | Existing components at this facility are controlled with Staefa direct digital controls (DDC). A new and complete DDC will be installed under this project. Controls shall be IAW Davis Monthan Design Compatibility Guidelines. |
| 2 | Are the system controls monitored off site or by a 3rd party vendor? | Pilkington Construction Co. | Building is tied into the base wide EMCS . |
| 3 | Please provide information related to the existing system controls. | Pilkington Construction Co. | See Response to 1 |
| 4 | Will the site Superintent also be allowed to fill the role of SSHO and CQM? | Pilkington Contstruction Co. | Superintendent can fulfill SSHO or CQM roles of if qualified |
| 5 | Can you please provide “As-Builts” for the existing facility so we can determine the locations for existing Fire Alarm Devices? | Pilkington Contstruction Co. | Fire alarm devices indicated in plan are existing. Duct Detectors are required AHU-5. See Note Fire Alarm/Detection Note 2 on FP101 for additional information. |
| 6 | There are five 5HP applications located on the Variable Frequency Drive Schedule on sheet M0.3. There are 3 different VFD part numbers. Please confirm this is correct. Our electrician believes they should all be ACH550-VCR-08A8-4. | Guardian Construction Inc. | VFDs specified are the basis of design. Substitutions of equipment will be considered. |
| 7 | VFD #9 & 10 on the Variable Frequency Drive Schedule sheet M0.3 both call for NEMA 4 enclosures but also have note #2 which calls for NEMA 1 enclosures. Please confirm the correct enclosure. | Guardian Construction Inc. | Provide NEMA 4 enclosure. |
| 8 | The ABB ACH550 VFD’s are being phased out and replaced with ACH580 VFD’s is it acceptable to use the newer model? | Guardian Construction Inc. | VFDs specified are the basis of design. Substitutions of equipment will be considered. |
| 9 | On sheet M0.3 in the Variable Frequency Drive Schedule the Manufacturer/Model numbers show a -1 at the very end of the number, this in not a normal ABB model number, after the -4 which indicates 480V, there would be a +K466 after the -4 indicating the Ethernet Adapter. The part number would look like this: ACH550-VCR-08A8-4+k466 for a 5HP, 480V, NEMA 1 with Bypass and Ethernet Adapter. Please explain and confirm the -1 at the end of the model number. | Guardian Construction Inc. | VFDs specified are the basis of design. Ethernet adaptor is required per VFD schedule note 1. Contractor will ensure model provided meets project requirements. |
| 10 | Is enhanced commissioning required for this project? | Herman Construction Group | Enhanced Commissioning not required |
| 11 | Verify that the Owner will be responsible for removing ALL equipment, unbolted furniture, personal effects, etc. from the affected areas prior to construction. | Herman Construction Group | Dust covers and protective enclosures will be required to protect government property/equipment. Computers and other personnel belongings will be removed by government. Furniture and other equipment will be protected in place. |
| 12 | Is it the responsibility of the contractor to provide temporary facilities to the government while we are working in the facility? | Herman Construction Group | The facility will remain occupied throughout construction. Contractor will provide a sequence of operations which limits the affects of construction and maintains facility operations. Relocating occupants to temporary facilities is not anticipated. |
| 13 | Specification section 01 45 00.00 10, 3.4.3 states: |
In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: electrical, mechanical, structural, environmental, architectural, materials technician, Cx Agent/LEED Specialist. These individuals or specialized technical companies are employees of the prime or subcontractor; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized personnel's areas of responsibility; have the necessary education or experience in accordance with the experience matrix listed herein.
Is it the intent of the Government for us to budget these personnel to be on-site during the entire duration of work in each specialty area in addition to the full time QC manager? Consequently, adding $millions to the cost of general conditions over the duration of this project.
| Herman Construction Group | Individual can fulfil multiple roles (if qualified); but means and methods is subject to the contractor's discretion. |
| 14 | Specification section 01 45 00.00 10, 3.4.2 states: |
The CQC System Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years construction experience on construction similar to this Contract.
Does this statement require simply a bachelors degree or a graduate degree such as a master's or a PhD.
| Herman Construction Group | "Graduate" is referring to a bachelor's degree | |||
| 15 | Can the KTR reuse salvaged building components in the new buildout if they are in compliance with the RFP? | Herman Construction Group | All components are new unless otherwise specified. | |
| 16 | Provide sign-in sheets for the pre-bid site walk/meeting | Herman Construction Group | See attached sign in sheet to amendment 0001 | |
| 17 | Confirm standard / permissible work hours during construction. | Herman Construction Group | Assume 0730-1600 working hours. Hours may be adjusted to accommodate all parties. | |
| 18 | Please confirm that the Government will allow proposers a minimum of seven (7) days to respond to the RFP starting from the date that the Government responds to 100% of the RFIs received | Herman Construction Group | Confirmed. In accordance with Amendment 0001, the new closing date is Jan 12, 2021 | |
| 19 | Please provide existing DDC system details (make, model, version, BACnet Compatibility etc) | Herman Construction Group | See Response to 1 | |
| 20 | Sheet M5.1, detail 9 illustrates the installation of a supply air plenum box on the existing CRAC unit located in server room 141. During the site visit it was noticed that there is a set of stairs that are not indicated on the plans. The stairs will impede on the installation of the plenum and ducting. Please advise. | Orcom Construction Group | Duct work shown is schematic. Duct work will be adjusted to fit existing conditions. | |
| 21 | Can the work be accomplished by giving the contractor full access to HVAC zone? | |||
| a. Example: HVAC Zone 1 (zones TBD based on existing HVAC layout and new install) move occupants out, perform work, final acceptance of government for that zone, occupants move in, repeat next zone. | MAC GC-Electric Inc. | This approach is not acceptable. | ||
| 22 | Will a laydown area for storage, construction office, dumpsters, ect.. be provided on site or remote? | MAC GC-Electric Inc. | Areas for laydown, construction office, dumpsters, etc., will be available on site. | |
| 23 | Does the government want the old HVAC units that are to be demoed or will the contractor dispose of off base? | MAC GC-Electric Inc. | Government reserves the right to salvage. Contractor will dispose all other materials not claimed by the government. | |
| 24 | The attachment 8 asbestos lead paint survey report is corrupted. Can you upload a new file to website? | MAC GC-Electric Inc. | The attachment appears to be opening properly, however, you may request a drop via DoD SAFE. Please email 2d Lt Durlauf to request drop-off. | |
| 25 | Note #13 on sheet A-111 calls for new vinyl faced batts at open storage 175. Please confirm this also applies to room 176. | Guardian Construction Inc. | Provide insulation as noted. | |
| 26 | The DMAFB Design Compatibility Guidelines are included in the bid package but not referenced on the plans. The existing equipment in the building is connected to the base-wide EMCS - will the new equipment be required to meet the industrial security standards called out in the ‘Authority to Operate’ protocol necessary to integrate into the base-wide EMCS at Davis Monthan? | The Carlson Company | The new equipment shall be required to meet the industrial security standards called out in the ‘Authority to Operate’ protocol necessary to integrate into the base-wide EMCS at Davis Monthan. | |
| 27 | Where there are discrepancies between the Project specs and the 2017 DM Design guide (EMCS Controls & Press copper fittings) which one takes precedence? | The Carlson Company | Construction shall be IAW Davis Monthan Design Compatibility Guidelines. Please inform CO of all discrepancies. | |
| 28 | Are press fitting acceptable on this project? | The Carlson Company | Press fitting are not acceptable. |