PreBid Site Visit Q_A B190 10 Jan 22 V3.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
B190, Repair Doors, Sprinklers, Tile Briefing Rm
Solicitation number
FA485522B0001
Issued by

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

FA485522B0001, B190, Repair Doors, Sprinklers, Tile Briefing Rm COR Nomination
ItemDateQuestionGov't Response
120-Dec-21Per the General Requirement section 1.4.1 Designs, is the contractor required to provide any design drawings in addition to the 35% provided in the bid documents?No, the contractor is not required to build drawings. We just ask for as-builts, and the contractor may use the Govt. provided drawings to red-line and/or guide to submit as-built.
220-Dec-21Per the Description of the Project section 2.2.5 New Construction, is there a specific prefabricated wall or similar type of partition to be used to match existing?Government is working on this and will provide an update at later date
320-Dec-21Per the Description of the Project section 2.3.3 Fire Suppression, please confirm there are a total of (6) existing fire sprinkler heads in Room S128 that will be required to be lowered to existing ceiling height.Correct
420-Dec-21Per the Description of the Project section 2.3.3 Fire Detection, what is the type of existing fire alarm panel for B190 so the new smoke detectors and fire doors can be tied in?The fire alarm panel in B190 is Moncaco M-2 Conventional
520-Dec-21Is there a specific contractor who is responsible for monitoring the existing fire alarm system for B190?We do not have specific contractor that monitors the existing fire alarm system it is maintained by the Civil Engineering unit
620-Dec-21Is there a specific contractor who is responsible for handling the Blue Light devices and monitoring for B190?We do not know of a specific contractor for Blue light devices
720-Dec-21What type of new acoustical ceiling tiles are being requested in order to match existing?Ceiling tiles are to meet the 09 51 00 Specifications
820-Dec-21What type of new carpet tiles are being requested in order to match existing?Rolled carpet to match existing carpet
920-Dec-21Is there an existing asbestos survey for building 190 available or does Cannon know if any hazardous material is present within the building?Yes, the environmental form is attached.
103-Jan-22Please confirm that drywall can not be used in lieu of prefabricated panels. Is the customer open to building soundproof walls instead of using the panels?Government is working on this and will provide at later date
113-Jan-22Please provide VCT specsthey're provided in section 09 65 00 resilient flooring
123-Jan-22During the site visit, pictures of the sprinkler heads were discussed. Please provide pictures of sprinkler heads.Government is working on this and will provide at later date
133-Jan-22What fire alarm system is being used in B190?The fire alarm panel in B190 is Moncaco M-2 Conventional
143-Jan-22Can the site superintendent dual hat to cover the SSO and QCM for this project?yes
153-Jan-22Has there been or is there any testing results available for lead paint or asbestos?Yes, the environmental form is attached.
1610-Jan-22We are unable to find manufacturer for pre-manufactured partitions. There is no specification on this, is there any information available?Government is working on this and will provide at later date

File details come from the government source that posted it. Updated .