Questions_and_Government_Responses.pdf

PDF 142 KB Posted

Attached to
551 SOS Open Storage Bldg 724
Solicitation number
FA485519QA037
Issued by

About this file

Questions and Government Responses

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Government Responses

FA4855-19-Q-A037

1. Will you provide a floor plan of building 724 and block D (area to be secured), along with the communication demarcation location and the mechanical room?

Government Response: Request for Quote Amendment 02 added Attachment 7, Floor

Plans.

2. Is there currently an alarm system in this location (block D)?

Government Response: Block D does not currently have an alarm system as it is an addition to 724A, 724B, and 724C which are open storage areas and are alarmed.

3. In the Statement of Work / General Information / 1.3 Installation of Equipment:

"The contractor shall install all necessary parts in order for Open Storage to be approved by Security Forces for Building 724 Block D. This includes additional sensors for the mechanical room. 724D Intrusion Detection System shall be integrated with the rest of building 724"

a. We read this to indicate that block D will report to an existing alarm panel, shouldn't block D have a dedicated alarm panel?

Government Response: Block D will report to an existing alarm panel as all of the other areas in the building are already alarmed.

b. If the answer to question 3a is no, please list available inputs and the location of existing alarm panel.

Government Response: Please see answer to 3a.

File details come from the government source that posted it.