Bldg_1254_Replace_HVAC_Q A.docx

DOCX document 17 KB Posted

Attached to
Repair HVAC Bldg 1254
Solicitation number
FA4855-14-B-0006
Issued by

About this file

Attached are the questions that were received and the answers that go with them. Please review these items since they might affect your solicitation/quote. Thank you.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS FOR BLDG 1254 REPLACE HVAC

1. I am having a hard time locating any product schedules. Are we to just go by the Trane and Aerco catalogues for this information? I am specifically looking for the schedules for pumps 1-6.

· Equipment schedule is M-601, sheet 7 of 11, it lists all: Pumps, fans, chiller, boiler, FCUs, air separator, MAU outdoor air unit, air devices.

2. Please clarify if the existing pipe insulation contains asbestos.

· Attached is the asbestos survey report at Bldg. 1254, it does not indicate ACM in pipe insulation.

3. Please clarify how access is to be obtained to the roof.

· Access is only from outside the building

4. Is the Government responsible for the relocation of any existing furniture/equipment prior to construction activities?

· Furniture relocation is by the building occupants (the Gov.), related HVAC equipment is by the contractor

5. Structural steel is required to reinforce the roof structure. Is a structural engineer required to design such support?

· Would the contractor point out where he/she found such a requirement?

6. Please clarify how the Offeror is to maintain interior air temperature for occupied personnel during the removal and installation of chillers and condensers?

· There is no proposed condensers, Contractor shall coordinate with the building occupants (the Gov.)

7. Please clarify existing type of roofing materials?

· Standing seem roof over the original concrete deck

8. Are pictures available for the roof since access was not available during the site visit?

· Attached is geo-base snapshot

9. How many existing units are on the roof?

· Refer to the design drawings and geo-base snapshot.

10. Please clarify what is required to be tested and balanced and to what degree.

· Refer to the spec section 23 05 93

11. Are as-builts available for the roof?

· There is some as-built available; however they do not describe the existing conditions. Contractor shall go by the provide design package.

12. What new panels are required?

13. Where are new panels to be located?

14. What size of panels is needed?

· Electric drawings show proposed work to be completed, there is no new electric panels, see E-001 to E-004. Which panels does the contractor refer to?

*PLEASE REVIEW AND ANSWER THESE BY 16 MAY SO WE CAN POST THE ANSWERS*