1._Statement_of_Work.docx
DOCX document 16 KB Posted
- Attached to
- Repair HVAC Bldg 1254
- Solicitation number
- FA4855-14-B-0006
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bldg_1254_Replace_HVAC_Q A.docx | DOCX document | |
| Drawings.pdf | ||
| New_Drawings_(Mod_M-601).pdf | ||
| M-101-Plot.pdf | ||
| 6._CAFB_DDC_Requirements_Guide_-_25_Sep_2013.pdf | ||
| 3._Schedule_of_Material_Submittals_-_Bldg_1254_HVAC.pdf | ||
| 4._HVAC_Wage_Determination.docx | DOCX document | |
| Solicitation_-_Replace_HVAC_Bldg_1254.pdf | ||
| 5._Drawings_-_Replace_HVAC_Bldg_1254.pdf | ||
| 2._Bldg_1254_IFC_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
CANNON AIR FORCE BASE
REPAIR HVAC SYSTEM BUILDING 1254
11 April 2014
1. GENERAL:
1.1. The Contractor shall provide all labor, equipment, materials and supervision to replace the HVAC system at Building 1254 at Cannon Air Force Base, New Mexico.
1.2. The construction performance period shall not exceed 5 months. The building will remain occupied during construction. Construction will be phased to accommodate building occupants.
1.3. The following work shall be accomplished in accordance with the requirements contained in the original Contract, this Statement of Work, the applicable Specifications, and the project drawings:
2. SCOPE OF WORK:
2.1. Structural Requirements:
2.1.1. Reinforce existing roof structure as required to support new rooftop equipment and equipment hung from the existing roof structure per contract documents.
2.1.2. Patch existing roof deck where required per contract documents.
2.2. Mechanical Requirements:
2.2.1. Remove HVAC equipment and temperature controls per the contract documents.
2.2.2. Provide new fan coil units, CRAC unit, exhaust fans, unit heaters, associated ductwork, air devices, piping and temperature controls per contract documents.
2.2.3. Provide new chillers, boilers, pumps, glycol feeders, air separators, expansion tanks, accessories and temperature controls per contract documents.
2.2.4. Provide new louvers, diffusers grills, and control dampers per contract drawings.
2.2.5. Insulation ductwork and piping per contract documents.
2.2.6. Provide control programming and graphics in accordance with the attached DDC General Requirements Guide for Cannon Air Force Base.
2.2.7. Label equipment locations in ceiling on dropped ceiling grid. Label T-stats with the same name as the equipment they control.
2.3. Plumbing Requirements:
2.3.1. Reconfigure gas piping system per contract documents.
2.3.2. Reconfigure mechanical room floor drains and floor sinks per contract documents to accommodate new HVAC equipment.
2.4. Electrical Requirements:
2.4.1. Provide new distribution panels and feeders per contract documents.
2.4.2. Provide branch circuits and final connections for all new HVAC and plumbing equipment per contract documents.
3. SUBMITTALS. The Contractor shall submit for approval all technical data and material samples for all proposed building materials and equipment in accordance with Section 01 33 00: Submittal Procedures as per attached Schedule of Material Submittals.
4. AS – Built.