B135 Replace HVAC System

CZQZ 13‐1080

Drawings Change Log:

The following reflect changes made to the original contract drawings.

M‐101 ‐ Removed requirement to change the exhaust fan speed. (Keynote 3)

M‐101 ‐ Changed Keynote 3 to: Repair hole in the mechanical room wall above ceiling level.

M‐101 ‐ Keynote 9 is new.

M‐101 ‐ Keynote 2: Added the option to use galvanized steel as listed in the questions.

M‐101 ‐ Keynote 8: Added the requirement for a 7’ X 7’ double door entrance gate.

M‐101 ‐ Keynote 6: Move the location of the “Emergency HVAC System Shut‐Off Switch” to the corridor.

M‐201 ‐ change the route of the HVAC piping to show a more accurate route based on the site visit 23 August 2013.

M‐201 ‐ Added another location where an interior concrete wall will have to be drilled to allow the HVAC piping through.

M‐201 ‐ Keynote 6 is new.

M‐201 ‐ Keynote 7 is new.

M‐202 ‐ Keynote 4: Change pump head insulation requirement to only chilled water pumps.

M‐202 ‐ Keynote 6 is new.

M‐502 ‐ Added a freeze stat down‐stream of the cooling coil.