This Statement of Work (SOW) dated 10 April 2026 requires the Contractor to provide all plant, labor, material, design, and supervision for delivering approximately 8,001 tons of hot-mix asphalt (HMA) and 8,072 gallons of bituminous tack and prime coats to Taxiway Hotel at Avon Park Air Force Range, Avon Park, Florida. The taxiway is classified as a Type A traffic area required to support C-17 operations. The Contractor must also perform field and laboratory quality control testing as required by the Government. HMA mixtures shall conform to Uniform Guide Specification (UFGS) 32.12.15.13, and bituminous coats shall conform to UFGS 32.12.13, with design precedence given to the most stringent standard when requirements conflict between UFC and Avon Park Air Force Range Design Standards.
Prior to work commencement, the Contractor must submit a Design & Materials Data package (HMA Mix Design, Asphalt Cement Binder, and aggregate data), Quality Control Plan, comprehensive Safety Plan, and material test reports with compliance certificates. Deliveries are scheduled between June 1 and September 30, 2026, using a two-step coordination process: 10-day advance notification of potential delivery dates and day-before confirmation of final orders. The HMA requirement specifies 8,001 tons of Intermediate Course, Type B with PG 67-22 binder, delivered at a minimum of 290 degrees Fahrenheit, with possible night and weekend deliveries. The Contractor must provide approximately 1,960 gallons of bituminous tack coat and 6,200 gallons of prime coat for transportation and application. Performance requirements mandate production of a minimum 500-ton sublot during one 8-hour workday with no more than 30 minutes between delivery trucks. The Contractor bears all costs for rejected non-conforming material removal within 24 hours and must comply with federal, state, and local safety regulations, Avon Park Air Force Range requirements, and site cleanliness standards. Failure to comply may result in stop-work orders.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) FOR
Providing Hot-Mix Asphalt, Tack and Prime
DATE: 10 APRIL 2026
The Contractor shall provide all plant, labor, material, design, and supervision to provide and deliver approximately 8,001 tons of hot mix asphalt (HMA) and 8,072 gallons of Bituminous Tack and Prime Coats. The Contractor shall also provide field and laboratory quality control testing, as required by the Government. The asphalt will be for taxiway Hotel at Avon Park Air Force Range, Avon Park, Florida.
The taxiway is a Type A traffic area and will be required to support C-17 Operations. The Contractor shall not commence work without prior coordination with the Contracting Officer, Project Inspector, and Using Agency.
ONE (1) DESIGN
HMA mixtures shall conform to the Uniform Guide Specification (UFGS)
32.12.15.13 and all applicable references. Bituminous Tack and Prime Coats shall conform to the requirements of UFGS 32.12.13.
• Design Precedence: Design shall be in strict accordance with Unified Facilities Criteria (UFC) and the Avon Park Air Force Range Design Standards. Where requirements conflict, the most stringent standard shall be used.
• Acceptance: If any submittal fails to meet the requirements of this SOW or any referenced guidance, it shall be considered unacceptable and returned for correction.
TWO (2) SUBMITTALS
Prior to the commencement of work, the Contractor shall submit the following key documents to the Contracting Officer (CO) for approval:
Submittal Package Includes
Design & Materials Data
HMA Mix Design, Asphalt Cement Binder, Aggregate data, and all other product data.
Quality & Safety Plans The Contractor's Quality Control (QC) Plan and a comprehensive Safety Plan.
Testing & Certification Material test reports and compliance certificates.
Waybills and delivery tickets shall be provided with each delivery.
THREE (3) DETAILED SCOPE OF WORK
The Contractor shall provide all plant, labor, material, and supervision for the work described below. The Government reserves the right to coordinate and schedule all deliveries between June 1st and September 30th, 2026.
Scheduling and Coordination Protocol:
The delivery schedule will be managed through a two-step process:
1. 10-Day Advance Notification: The Government will notify the Contractor of potential delivery dates and times at least ten (10) days in advance. This serves as a forecast to ensure the Contractor can allocate resources for the upcoming work window.
2. Day-Before Order Confirmation: The day before any scheduled work, the Government Project Team Lead will contact the Contractor to confirm the final order. This confirmation will specify:
• Which materials are required (e.g., HMA, Tack Coat, or Prime Coat).
• The specific quantity needed for the following day's operation.
This final confirmation allows the Government lead to make an authoritative weather call and align the material order with the paving team's daily work capacity.
Hot-Mix Asphalt (HMA):
• Provide and deliver 8,001 tons of HMA Intermediate Course, Type B with PG 67-22 binder.
• Product must be a minimum of 290 degrees Fahrenheit at delivery.
Deliveries may be required during nights and weekends.
• Non-Conforming Deliveries: Rejected material shall be removed from the site by the Contractor at the Contractor's expense within 24 hours. The Government will not be liable for any costs associated with the rejected material.
• Testing: The Contractor shall perform sampling and testing of cores from each 1,000-ton lot for JMF deviations in Laboratory Air Voids and Stability.
Bituminous Tack and Prime Coats:
• Provide for the transportation and application of approximately 1,960 gallons of Bituminous Tack Coat.
• Provide for the transportation and application of approximately 6,200 gallons of Bituminous Prime Coat.
FOUR (4) PERFORMANCE
The contractor must be able to produce a minimum sub-lot of 500 tons of HMA during one 8-hour workday and ensure the maximum time between delivery trucks does not exceed 30 minutes. The Contractor shall adjust mixing temperatures to ensure the product is no less than 290 degrees Fahrenheit upon arrival at the Hotel Taxiway on Avon Park Air Force Range, FL.
FIVE (5) SAFETY, PERSONNEL, AND SITE REQUIREMENTS
• Safety Plan: Contractors are responsible for the safety and wellbeing of their employees. The submitted Safety Plan must comply with all applicable federal, state, and local regulations, as well as any specific requirements of the Avon Park Air Force Range.
• Personnel & Access: Drivers must be properly licensed, able to communicate in English, and be legally allowed to enter a military installation with proper identification. Drivers must be reachable by cell phone during all hours of operation.
• Site Cleanliness: The Contractor shall clean any mud, debris, or spills caused by their operations on any access street or staging area the same day.
• Compliance: Failure to comply with the requirements of this SOW may result in actions including, but not limited to, stop-work orders until deficiencies are corrected.
| STATEMENT OF WORK (SOW) FOR |
| Providing Hot-Mix Asphalt, Tack and Prime |
| ONE (1) DESIGN |
| TWO (2) SUBMITTALS |
| THREE (3) DETAILED SCOPE OF WORK |
| FOUR (4) PERFORMANCE |
| FIVE (5) SAFETY, PERSONNEL, AND SITE REQUIREMENTS |