This is a pricing worksheet (Independent Government Estimate) for a multi-building carpet and luxury vinyl plank (LVP) flooring removal and replacement project at Shaw Air Force Base. The project encompasses four separate contract line items (CLINs) covering buildings 106, 615, 710, and 825, with work to be performed under the direction of Project Engineer Mr. Thomas Harris and the 20 CES/CEOES Department.
CLIN 0001 (Building 106) requires removal and replacement of 750 square yards of carpet with modular carpet squares, including 1,800 linear feet of cove base installation. CLIN 0002 (Building 615) involves removal of existing carpet and replacement with 5,010 square feet of LVP flooring plus 1,163 linear feet of cove base. CLIN 0003 (Building 710) requires removal and replacement of 1,450 square yards of carpet with modular carpet squares and 2,830 linear feet of cove base. CLIN 0004 (Building 825) is a mixed project requiring 1,200 square yards of carpet installation and 600 square feet of LVP flooring replacement, with 2,300 linear feet of cove base. All CLINs include material costs (flooring, adhesives, and cove base) and labor costs (demolition, floor preparation, and installation). The pricing worksheet contains all line items with zero dollar values, indicating this is a template requiring contractor pricing. A note on each CLIN specifies that quantities are government estimates only and must be verified by the contractor.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
IGE Price Sheet - Multi-Bldg
| Project: | Multi-Building Carpet & LVP | Project Engineer: | Mr. Thomas Harris | ||||||
| Location: | B106 | Department: | 20 CES/CEOES | ||||||
| Contractor: | TBD | Date Created: | 20-Jul-26 | ||||||
| CONTROLLED UNCLASSIFIED INFORMATION (CUI) | |||||||||
| Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | ||
| Unit Cost (Means) | Total | Avg. Rate ($/hr) | Total | ||||||
| CLIN 0001: B106 Remove and Replace Carpet | |||||||||
| Material Costs: | |||||||||
| 1 | Carpet | SY | 750 | $0.00 | |||||
| 2 | Carpet Adhesive | EA | 21 | $0.00 | |||||
| 3 | Cove Base | LF | 1800 | $0.00 | |||||
| 4 | Cove Base Adhesive | EA | 32 | $0.00 | |||||
| Labor Costs: | |||||||||
| 5 | Remove (Demo) Carpet | SY | 750 | $0.00 | |||||
| 6 | Remove Cove Base and Transitions | LF | 1800 | $0.00 | |||||
| 7 | Floor Prep | SF | 5787 | $0.00 | |||||
| 8 | Install Modular Carpet Squares | SY | 750 | $0.00 | |||||
| 9 | Install Cove Base | LF | 1800 | $0.00 | |||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| NOTE: Quantities are Government estimates only and are provided for information purposes - they must be verified by the Contractor. |
| Project: | Multi-Building Carpet & LVP | Project Engineer: | Mr. Thomas Harris | ||||||
| Location: | B615 | Department: | 20 CES/CEOES | ||||||
| Contractor: | TBD | Date Created: | 20-Jul-26 | ||||||
| CONTROLLED UNCLASSIFIED INFORMATION (CUI) | |||||||||
| Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | ||
| Unit Cost (Means) | Total | Avg. Rate ($/hr) | Total | ||||||
| CLIN 0002: B615 Remove Existing Carpet and Replaced With LVP | |||||||||
| Material Costs | |||||||||
| 1 | LVP Flooring | SF | 5010 | $0.00 | |||||
| 2 | LVP Adhesive | EA | 6 | $0.00 | |||||
| 3 | Cove Base for LVP Flooring | LF | 1163 | $0.00 | |||||
| 4 | Cove Base Adhesive | EA | 15 | $0.00 | |||||
| Labor Costs: | |||||||||
| 5 | Remove (Demo) Carpet | SY | 550 | $0.00 | |||||
| 6 | Remove Cove Base and Transitions | LF | 1163 | $0.00 | |||||
| 7 | Floor Prep | SF | 5010 | $0.00 | |||||
| 8 | Install LVP Flooring | SF | 5010 | $0.00 | |||||
| 9 | Install Cove Base | LF | 1163 | $0.00 | |||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| NOTE: Quantities are Government estimates only and are provided for information purposes - they must be verified by the Contractor. |
| Project: | Multi-Building Carpet & LVP | Project Engineer: | Mr. Thomas Harris | ||||||
| Location: | B710 | Department: | 20 CES/CEOES | ||||||
| Contractor: | TBD | Date Created: | 20-Jul-26 | ||||||
| CONTROLLED UNCLASSIFIED INFORMATION (CUI) | |||||||||
| Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | ||
| Unit Cost (Means) | Total | Avg. Rate ($/hr) | Total | ||||||
| CLIN 0003: B710 Remove and Replace Carpet | |||||||||
| Material Costs: | |||||||||
| 1 | Carpet | SY | 1450 | $0.00 | |||||
| 2 | Carpet Adhesive | EA | 28 | $0.00 | |||||
| 3 | Cove Base | LF | 3240 | $0.00 | |||||
| 4 | Cove Base Adhesive | EA | 65 | $0.00 | |||||
| Labor Costs: | |||||||||
| 5 | Remove (Demo) Carpet | SY | 1400 | $0.00 | |||||
| 6 | Remove Cove Base and Transitions | LF | 3240 | $0.00 | |||||
| 7 | Floor Prep | SF | 12197 | $0.00 | |||||
| 8 | Install Modular Carpet Squares | SY | 1450 | $0.00 | |||||
| 9 | Install Cove Base | LF | 2830 | $0.00 | |||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| NOTE: Quantities are Government estimates only and are provided for information purposes - they must be verified by the Contractor. |
| Project: | Multi-Building Carpet & LVP | Project Engineer: | Mr. Thomas Harris | ||||||
| Location: | B825 | Department: | 20 CES/CEOES | ||||||
| Contractor: | TBD | Date Created: | 20-Jul-26 | ||||||
| CONTROLLED UNCLASSIFIED INFORMATION (CUI) | |||||||||
| Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | ||
| Unit Cost (Means) | Total | Avg. Rate ($/hr) | Total | ||||||
| CLIN 0004: B825 Remove Carpet and Replace with Carpet and LVP | |||||||||
| Material Costs: | |||||||||
| 1 | Carpet | SY | 1200 | $0.00 | |||||
| 2 | Carpet Adhesive | EA | 25 | $0.00 | |||||
| 3 | LVP Flooring | SF | 600 | $0.00 | |||||
| 4 | LVP Adhesive | EA | 2 | $0.00 | |||||
| 5 | Cove Base for Carpet and LVP Flooring | LF | 2300 | $0.00 | |||||
| 6 | Cove Base Adhesive | EA | 65 | $0.00 | |||||
| Labor Costs: | |||||||||
| 7 | Remove (Demo) Carpet | SY | 1200 | $0.00 | |||||
| 8 | Remove Cove Base & and Transitions | LF | 2300 | $0.00 | |||||
| 9 | Floor Prep | SF | 16800 | $0.00 | |||||
| 10 | Install LVP Flooring | SF | 600 | $0.00 | |||||
| 11 | Install Cove Base | LF | 2300 | $0.00 | |||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| NOTE: Quantities are Government estimates only and are provided for information purposes - they must be verified by the Contractor. | |||||||||
| Total Price | $0.00 |