Attachment 7-Questions with Answers.pdf

PDF 108 KB Posted

Attached to
Vindicator Intrusion Detection System Installation Federal contract opportunity
Solicitation number
FA480321QB085
Issued by
Department of the Air Force Air Combat Command

View the file

Other files for this federal contract opportunity

Other files attached to Vindicator Intrusion Detection System Installation, newest first.
File Type Posted
Attachment 8_Vindicator Brand Name JA_Redacted.pdf PDF
FA480321QB085 Amendment 0001.pdf PDF
Attachment 5-Building Sections.pdf PDF
Attachment 6-Wall Sections.pdf PDF
Attachment 4-Floor Plan.pdf PDF
Attachment 3-Base Pass Request.docx DOCX document
COMBOSOL-21QB085-Vindicator IDS Installation B1130 Annex.pdf PDF
Attachment 2-SOW Vindicator IDS Install B1130 Annex.pdf PDF
Attachment 1-Facility Drawing Bldg 1130 Annex redo.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0001 26 August 2021

Questions with Answers

1. Regarding SOW Para 1.1 General Requirements IDS statement, “Contractor shall procure and install required IDS equipment for 9th Air Force office areas of Building 1130 Annex (specified on the attachment).

Can the Government identify the dimensions of the highlighted green open storage area to better understand the size of the spaces?

The space is approximately 7,350.

2. Can the Government identify what room number within the area of work that the system will be connected back to? It appears there are multiple telecom rooms and other rooms that may appear to be comm rooms.

The alarm panels will need to be in the General’s office and it will run back to the network switch inside room 123 and all that will need to be programmed to the BDOC headend.

3. Is it acceptable for the Vendor to utilize flush cable hiders installed closest to the ceiling and the highest part of the wall to minimize the visual of the wires? Would the Government prefer the Vendor run any cabling and wires up in the ceiling (above the drop down ceiling)?

The wire needs to be run above the drop ceiling. Wires need to be concealed within walls.

4. If mounting above the drop down ceiling, can the Vendor utilize the existing raceways or conduit?

No, the vendor will need to provide their own conduit.

5. What is the height of the ceiling in the Building 1130 Annex (to the drop ceiling, and then how much space is between the drop ceiling and the actual ceiling for work space)?

See the following attached documents posted with Amendment 0001:

Attachment 4-Floor Plan

Attachment 5-Building Sections

Attachment 6-Wall Sections

6. Is the ceiling made of drop tiles if so, can the Government provide the size and material of the drop ceiling?

The ceilings are 2x2 acoustical tiles