Reqs Doc Building 1178 Transformer AMENDED.pdf
PDF 97 KB Posted
- Attached to
- Transformers
- Solicitation number
- FA480126Q0027
About this file
This is a Requirements Document for the purchase and installation of electrical transformers for Building 1178 at Holloman Air Force Base, supporting the 704th Test Group/846th Test Squadron's rocket sled manufacturing operations.
The 846th Test Squadron requires delivery of three (3) pole-mounted, liquid-filled, compartmental-type transformers with the following specifications: 165 KVA capacity per unit, three-phase configuration, step-down operation only, primary voltage of 13200Y at 15 kV class with 95 KV BIL, secondary voltage of 208Y/120 with 60 Hz frequency and 2.5% TAPS A/B adjustment, DYN1 vector group, loop feed configuration, Class OE insulation rated at 120°C, KNAN cooling class (self-cooled with no forced air fans), 5-position tap changer at 2.5% increments, and standard warranty. The transformers will replace three existing temporary, undersized units that currently lack sufficient capacity to simultaneously support the facility's HVAC system and high-draw industrial machinery. Delivery must occur no later than 20 weeks after receipt of order (ARO). Prior to delivery, the contractor must contact Keith Bullard at 575-572-5239 to schedule delivery to 550 Tabosa Ave., Holloman AFB 88330. The document was issued on 17 June 2025 and contains no specified pricing terms, response deadlines, or contract vehicle information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - FA480126Q0027 - AMENDED.pdf | ||
| PWS (Reqs Doc).pdf | ||
| Solicitation - FA480126Q0027.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING 1178 TRANSFORMER
Requirements Document for
704th Test Group/846th Test Squadron
17 Jun 2025
1.0 PURPOSE
The 846th Test Squadron requires the purchase and installation of permanent, appropriately sized electrical transformers for Building 1178, a critical industrial manufacturing facility. This facility is solely responsible for producing custom-built rocket sleds supporting the 704 TG test and evaluation missions.
Currently, the facility operates on three temporary, undersized transformers provided as an emergency interim measure by the 49th Civil Engineer Squadron (49 CES). These interim units lack the capacity to simultaneously sustain the facility's robust HVAC system and high-draw industrial machinery. Upgrading to permanent, correctly sized transformers is critical to prevent power failures, avoid mission delays, and ensure uninterrupted manufacturing operations.
2.0 SCOPE
The Contractor shall deliver three (3) pole mounted transformers to meet the following requirements:
2.1 Transformer Type: Pole Mounted, Compartmental-Type Transformer Configuration:
Liquid Filled
2.2 Mounted Transformer Feed Type: Loop Feed
2.3 Operation: Step-Down Operation (Not Approved for Step-Up)
2.4 Phase: Three Phase Capacity: 165 KVA x3 Vector Group: DYN1
2.5 Primary Voltage: 13200Y
2.6 Primary Voltage Switch: N/A Primary Voltage Class: 15 kV Class Primary Phasor: Delta
2.7 Primary BIL: 95 KV
2.8 Secondary Voltage: 208Y/120 Secondary Voltage Class: TAPS 2.5% A/B
2.9 Secondary BIL: 60 Hz Temperature Rise: 65°C
2.10 Insulation Rating: Class OE Insulation - 120°C, 248°F
2.11 Cooling Class: KNAN; Self-Cooled
2.12 Forced Air (Fans): None
2.13 Tap Changer: 5-position Tap Changer
2.14 Tap %: 2.5%
2.15 Standard warranty
3.0 MILESTONES
The contractor shall deliver three (3) pole mounted transformers no later than 20 Weeks ARO.
4.0 DELIVERABLES
Before delivery, the contractor shall contact Keith Bullard at 575-572-5239 to schedule a delivery date and time. Delivery address: 550 Tabosa Ave. Holloman AFB 88330.
File details come from the government source that posted it. Updated .