Q and A for Heavy Equipment Rental.docx
DOCX document 14 KB Posted
- Attached to
- Heavy Equipment Rental Federal contract opportunity
- Solicitation number
- FA480121Q0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A for Heavy Equipment Rental.docx | DOCX document | |
| Holloman BEAR Pad Equipment Renta SOW Updated (003).pdf | ||
| Holloman BEAR Pad Equipment Rental SOW_Updated (002).pdf | ||
| Solicitation - FA480121Q0007.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please see responses below to all questions submitted for this requirement:
1. I noticed that the delivery date is March 29. Including the time it is going to take for contracting to award the contract that provides a very small turnaround time to deliver all of the equipment. Is there any flexibility on the delivery date.
0. Answer: No due to projected material delivery on same date. If we could prioritize receiving the Front End Loader, Grader, Sheep’s Foot Roller, Compact Track Loader, and Water Truck as close to the that date as possible, that would be ideal.
1. The RFQ pricing sheet and SOW show different hours of use on the equipment. Can you verify the time in hrs. per unit?
1. Answer: correct usage rates are on the SOW (160 hrs/80 hrs). The RFQ were the old rates that were updated.
1. 1-Are you sure you are looking for a 6000kw Generator? I don’t even think they make something that big.
2. Answer: The primary requirement is for a lighttower with power generation capability as a secondary option. A standalone generator is not required.
2. Power generating lighttower (would only need one) https://www.sunbeltrentals.com/equipment/detail/1178/0120420/4000w-20kw-wide-vertical-mast-lighttower/
1. Here is a link for a 1000Kw that would be delivered as a semi-truck trailer.
3. Answer: A standalone generator is not required.
https://www.sunbeltrentals.com/equipment/detail/1615/0090350/1000kw-diesel-generator/
1. I just wanted to clarify equipment and materials would be for Holloman AFB.
1. The close out day for this solicitation is reset for 19 March 19 March 2021 @ 1 pm.