This is a Questions and Answers document for a paintball concessionaire contract opportunity issued by the Air Force (Solicitation No FA480026Q0064) under the Non-Appropriated Funds (NAF) program. The document does not contain specific contract award dates, pricing terms, or response deadlines, as it serves solely to clarify key operational and administrative requirements for prospective contractors.

The contractor is responsible for providing all equipment and supplies required for paintball operations and must maintain a minimum staffing level of two field officials during operating hours. All required permits, safety certifications, and installation-specific recreational regulations are detailed in the Statement of Work Paragraph 2.1 and Appendix A. Operating hours are outlined in SOW paragraph 4.1, with peak usage occurring during weekends. This is not a brand-new contract; the previous contract number was FA480021H0002, indicating there is an incumbent contractor whose services are being rebid.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions – Paintball Concessionaire (NAF)

Solicitation No FA480026Q0064

1. Is existing paintball equipment owned by the Government, or is the contractor required to provide all equipment and supplies?

The contractor is responsible for providing all equipment and supplies.

2. What are the minimum staffing requirements during operating hours?

The contractor shall maintain a minimum staffing level of two (2) field officials.

3. Are there existing permits, safety certifications, or base-specific recreational requirements that must be maintained by the contractor?

All required permits, safety certifications, and installation-specific recreational regulations that the contractor must maintain are outlined in the Statement of Work (SOW) Paragraph 2.1 and Appendix A.

4. What are the expected seasonal operating hours or peak usage periods?

The hours of operations are outlined in the SOW para 4.1. The peak usage is during the weekends.

5. Is this a brand-new contract OR is (was) there an incumbent performing these services? If not a brand new, could you please provide the current/previous contract number?

FA480021H0002