412 Pool SOW (revised).pdf
PDF 120 KB Posted
- Attached to
- Pool Repairs
- Solicitation number
- FA4800-24-Q-A016
About this file
This document is a Statement of Work (SOW) for the repairs to the aluminum liner of the pool at Langley. The contractor is required to provide all labor, tools, equipment, transportation, materials, and supervision necessary to perform the work.
The key tasks include cutting twelve 24-inch by 24-inch holes in the pool liner, then welding aluminum patches into each hole to restore the pool's water-tightness and functionality. The contractor must be ready to begin work within 1-2 weeks of contract award and complete the project, including both cutting and welecting phases, within the agreed lead time. All work must comply with relevant safety standards and regulations, and the contractor is liable for any damages to government property. The related federal contract opportunity is for the Pool Repairs requirement, solicitation number FA4800-24-Q-A016, issued by the Department of the Air Force Air Combat Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR
RIVERVIEW EVENT CENTER (B.412) POOL REPAIRS
Scope of Work: The contractor, shall provide non-personal services to furnish all labor, tools, equipment, transportation, materials, and supervision necessary to perform repairs to the aluminum liner of the pool at Langley. This includes precision cutting and welding activities to ensure the integrity and functionality (retains water) of the pool’s aluminum liner.
Cutting Holes in Aluminum Pool Liner:
• The contractor is to cut twelve (12) holes, each measuring 24 inches by 24 inches, in the specified locations on the aluminum pool liner. These locations will be clearly marked and provided by the overseeing authority at Langley.
Welding Patches for Holes:
• Following the cutting phase and an intervening period as directed by the government, the contractor shall weld aluminum patches into each of the twelve (12) holes to restore the pool liner's integrity. This welding must ensure a water-tight seal capable of withstanding the operational pressures of the pool.
Inspection:
• Upon completion of the work, the contractor shall inform the Langley representative to schedule an inspection. All work will be inspected by Langley's designated authority prior to acceptance. The contractor must ensure that the repair work meets all specified requirements and standards for safety and quality.
Timeline:
• Lead Time: The contractor must be ready to begin work within 1-2 weeks of contract award.
• The contractor will leave holes open unit requested by the government to close after testing is completed (estimated 1-2 days).
• Completion: The project, including both cutting and subsequent welding phases, is expected to be completed within the agreed lead time, allowing for the pool’s timely return to service.
The specific timing for welding and patching will be determined based on government direction.
Contractor Requirements:
• The contractor is responsible for providing all necessary materials, equipment, and labor to complete the project as described.
• All work must comply with relevant safety standards and regulations.
• The contractor will perform a final walkthrough with the Langley representative to ensure the quality and durability of the repairs.
SAFETY AND HEALTH REQUIREMENTS:
• The contractor shall provide safety controls and protection to the life and health of employees and other persons for prevention of damage to property, materials, supplies and equipment.
The contractor shall comply with all U.S. Department of Labor Occupational Safety & Health Administration (OSHA) standards in the performance of this contract.
DAMAGES TO GOVERNMENT BUILDINGS, EQUIPMENT, OR VEGETATION
• Damages to Government buildings, equipment, or vegetation are addressed in clause 52.237-
2 – “Protection of Government Buildings, Equipment, and Vegetation.” The contractor shall be liable for damages to government and personal property caused by contractor operations.
File details come from the government source that posted it. Updated .