Attachment_24_Revised_SOW_MUHJ_03-4247.docx

DOCX document 1 MB Posted

Attached to
Repair East Apron Federal contract opportunity
Solicitation number
FA4800-17-B-0001
Issued by
Department of the Air Force Air Combat Command

About this file

Revised SOW

View the file

Other files for this federal contract opportunity

Other files attached to Repair East Apron, newest first.
File Type Posted
FA4800-17-B-0001-0003.pdf PDF
Amendment_27_Q&A_16_May_2017.docx DOCX document
Amendment_22__Bid_Schedule_Revision_2_-_10May17.docx DOCX document
FA4800-17-B-0001-0002.pdf PDF
Attachment_18_Phasing_schedule_timeline_Revision_1.docx DOCX document
Attachment_22_Bid_Schedule_Revision_1.docx DOCX document
Attachment_25_Q&A.docx DOCX document
Attachment_26_Storm_Pipe_and_Manhole_Drawing.pdf PDF
Attachment_22_MUHJ_03-4247_Final_Bid_Schedule_Corrected..docx DOCX document
FA4800-17-B-0001_East_Apron_Site_Visit_Meeting_Roster.pdf PDF
FA4800-17-B-0001-P0001_Amendment_Signed.pdf PDF
Attachment_22_MUHJ_03-4247_Final_Bid_Schedule.docx DOCX document
attachment_23_Pavement_Markings_20Arp17.pptx PPTX presentation
Attachment_19_Langley_AFB_QA_10_Apr_2017.docx DOCX document
Attachment_21_Langley_East_Apron_MUHJ_03-4247_Airfield_Slabs_Phasing.pdf PDF
Attachment_18_Phasing_Schedule.docx DOCX document
FA4800-17-B-0001-P00001_Amendment_to_Solicitation.pdf PDF
Attachment_20_Langley_East_Apron_MUHJ_03-4247_90_Haul_Route_and_Plant_Site.pdf PDF
Attach_8__Work_Areas.pdf PDF
Attach_1_MUHJ_03-4247_Final_Specs.pdf PDF
Attach_16_MUHJ_03-4247_Final_Warranty_Schedule.pdf PDF
Attach_2_Airfield_Slabs_Total.pdf PDF
Attach_9_MUHJ_03-4247_Final_Basis_of_Design.pdf PDF
Attach_14_MUHJ_03-4247_Final_Submittal_Form_AF_Form_66.pdf PDF
Attach_6_Airfield_Slabs4.pdf PDF
Attach_4_Airfield_Slabs2.pdf PDF
Attach_15_MUHJ_03-4247_Final_Survey.pdf PDF
Attach_5_Airfield_Slabs3.pdf PDF
Attach_11_MUHJ_03-4247_Final_Drawings_-_13Mar17.pdf PDF
Attach_13_MUHJ_03-4247_Final_Geotech_Report.pdf PDF
Attach_10_MUHJ_03-4247_Final_Buy_American.pdf PDF
Attach_7_Airfield_Slabs5.pdf PDF
Attach_12_MUHJ_03-4247_Final_Envir_Report.pdf PDF
FA4800-17-B-0001.pdf PDF
Attach_3_Airfield_Slabs1.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PROJECT MUHJ 03-4247

REPAIR EAST APRON, F. 6020

AT

JBLE-LANGLEY

10 Apr 2017

1.DESCRIPTION OF WORK:
1.1General Scope: Furnish all plant, labor, equipment, materials, tools, and perform all operations necessary to perform work to repair by replacement, the transient aircraft parking area (Brownie Pad), the Flight Line road, and the T-38 East Apron transient parking area. Repairs include the removal of existing pavement including the aggregate base and sub-base, unclassified excavation, subgrade stabilization, placement of a new sub-base and base section, concrete pavement, replacement of existing box drain, 24” reinforce concrete pipe replacement, manhole modifications, aircraft tie down, pavement markings, and curb and gutter replacement. Environmnetal testing is required to determine if the existing subgrage material contains any contaiminants prior to disposal off base.
All work shall be in accordance with the design and current UFCs included in the specifications.

The design package provided by the government is for full depth replacement of the T-38 East Apron area. However, the Contractor shall use this design to perform full depth replacement of the Brownie Pad only. Selective slab replacement is required for the T-38 parking area and Flight Line road. Contractor will submit a Geometric Plan Layout, and Joint Layout for the Brownie Pad for approval using the design provided (C-300) as guide.

Please see attached slide for clarification:

-Phase I (Fligh Line road): Selective slab replacement (red boxes only) -Phase II (Brownie pad): Full depth replacement -Phase III (T-38 Parking area): Selective slab replacement (red boxes only).

2. PROGRAM MANAGEMENT: The contractor shall sequence his work to ensure progress efficient for airfield operations.

2.1 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK:

No variance.

2.2 SUBCONTRACTORS:

No variance.

2.3 QUALITY CONTROL PLAN:

No variance.

3. RESPONSE REQUIREMENT:

No variance.

4. DESIGN DOCUMENTS, GENERAL:

Disregard the following:

-Entire Specification 00 22 13.00 22 -Paragraph 1.3 in Specification 01 11 00.00 10. See Bidding Schedule.

4.1 DRAWINGS:

No variance.

4.2 RENDERED PERSPECTIVE:

No variance.

4.3 SPECIFICATIONS:

No variance.

4.4 CONSTRUCTION COST ESTIMATE BREAKDOWN:

No variance.

4.5 PREPARATION OF AF FORM 66, Schedule of Material Submittals:

No variance.

4.6 BID SCHEDULE:

No variance.

4.7 DESIGN ANALYSIS:

No variance.

4.8 COMMUNICATIONS:

NA

4.9 ENERGY MONITORING AND CONTROL SYSTEM (EMCS):

NA

4.10 LOCKSETS:

NA

4.11 GEODETIC CONTROL SURVEYS:

No variance.

5. CONTRACT OPERATIONS:

No variance.

5.1 WORK HOURS:

According to approved schedule request.

5.2 ORDER OF WORK:

No variance.

5.3 APPLICABLE CODES AND REGULATIONS:

No variance.

6. GOVERNMENT POINT OF CONTACTS

633 CES Project Manager – Anhthu Nguyen, 764-1446.

633 CES Inspector – Kevin Armstrong, 764-0172.

STATEMENT OF WORK

MUHJ 03-4247

image1.png