Attachment_18_Phasing_schedule_timeline_Revision_1.docx
DOCX document 18 KB Posted
- Attached to
- Repair East Apron Federal contract opportunity
- Solicitation number
- FA4800-17-B-0001
About this file
Attachment 18 - Phasing Schedule Time Revision 1
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Time Breakout for Project MUHJ 03-4247 Repair East Apron, F. 6020 – 8 May 2017
The following are estimated requirements for this project from the Notice to Proceed:
| Actual Construction of three phases | 300 | calendar days |
| Phase I – Repair Flight Line road (selective slabs) | 30 | days |
NOTE: Phase I shall start 60 days after NTP Phase II – Full depth replacement of Transient Aircraft parking ramp 210 days NOTE: Phase II shall start February 2018 Phase III – Repair T-38 ramp (selective slabs) 60 days NOTE: This phase shall start no earlier than 30 days after the last concrete placement and turnover of Phase II.
Additional calendar days required for:
| 1. Initial Submittal Approval | 5 | days | |
| 2. Mobilization/Demobilization | 5 | days | |
| 3. Erection of Barriers/Safety Equip | 5 | days | |
| 4. Surveying/Site Layout | 2 | days | |
| 5. Long Delivery Impacts | 10 | days | |
| (List/source company names, POC and phone number) |
| 6. | Material Availability | 10 | days |
| (list/source company names, POC and phone number) |
| 7. | Weather Impacts | 5 | days | |||
| 8. | Phasing Impacts | 5 | days | |||
| 9. | Security Delays (Secure area access) | 1 | days | |||
| 10. | Cleanup/Turf Establishment | 1 | days | |||
| 11. | Final Inspection | 1 | days | |||
| Subtotal | 50 | days | ||||
| Total | 350 | days |
File details come from the government source that posted it. Updated .