Attachment_18_Phasing_Schedule.docx

DOCX document 18 KB Posted

Attached to
Repair East Apron Federal contract opportunity
Solicitation number
FA4800-17-B-0001
Issued by
Department of the Air Force Air Combat Command

About this file

Phasing Schedule Timeline

View the file

Other files for this federal contract opportunity

Other files attached to Repair East Apron, newest first.
File Type Posted
Amendment_27_Q&A_16_May_2017.docx DOCX document
Amendment_22__Bid_Schedule_Revision_2_-_10May17.docx DOCX document
FA4800-17-B-0001-0003.pdf PDF
FA4800-17-B-0001-0002.pdf PDF
Attachment_25_Q&A.docx DOCX document
Attachment_26_Storm_Pipe_and_Manhole_Drawing.pdf PDF
Attachment_18_Phasing_schedule_timeline_Revision_1.docx DOCX document
Attachment_22_Bid_Schedule_Revision_1.docx DOCX document
Attachment_22_MUHJ_03-4247_Final_Bid_Schedule_Corrected..docx DOCX document
FA4800-17-B-0001_East_Apron_Site_Visit_Meeting_Roster.pdf PDF
FA4800-17-B-0001-P0001_Amendment_Signed.pdf PDF
Attachment_22_MUHJ_03-4247_Final_Bid_Schedule.docx DOCX document
attachment_23_Pavement_Markings_20Arp17.pptx PPTX presentation
Attachment_19_Langley_AFB_QA_10_Apr_2017.docx DOCX document
Attachment_21_Langley_East_Apron_MUHJ_03-4247_Airfield_Slabs_Phasing.pdf PDF
Attachment_24_Revised_SOW_MUHJ_03-4247.docx DOCX document
FA4800-17-B-0001-P00001_Amendment_to_Solicitation.pdf PDF
Attachment_20_Langley_East_Apron_MUHJ_03-4247_90_Haul_Route_and_Plant_Site.pdf PDF
Attach_8__Work_Areas.pdf PDF
Attach_13_MUHJ_03-4247_Final_Geotech_Report.pdf PDF
Attach_10_MUHJ_03-4247_Final_Buy_American.pdf PDF
Attach_7_Airfield_Slabs5.pdf PDF
Attach_12_MUHJ_03-4247_Final_Envir_Report.pdf PDF
FA4800-17-B-0001.pdf PDF
Attach_3_Airfield_Slabs1.pdf PDF
Attach_1_MUHJ_03-4247_Final_Specs.pdf PDF
Attach_16_MUHJ_03-4247_Final_Warranty_Schedule.pdf PDF
Attach_2_Airfield_Slabs_Total.pdf PDF
Attach_9_MUHJ_03-4247_Final_Basis_of_Design.pdf PDF
Attach_14_MUHJ_03-4247_Final_Submittal_Form_AF_Form_66.pdf PDF
Attach_6_Airfield_Slabs4.pdf PDF
Attach_4_Airfield_Slabs2.pdf PDF
Attach_15_MUHJ_03-4247_Final_Survey.pdf PDF
Attach_5_Airfield_Slabs3.pdf PDF
Attach_11_MUHJ_03-4247_Final_Drawings_-_13Mar17.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Time Breakout for Project MUHJ 03-4247 Repair East Apron, F. 6020

The following are estimated requirements for this project from the Notice to Proceed:

Actual Construction of three phases300calendar days
Phase I – Repair Flight Line road (selective slabs)30days

NOTE: Phase I shall start 60 days after NTP Phase II – Full depth replacement of Transient Aircraft parking ramp 210 days NOTE: Phase II shall start June 2018 Phase III – Repair T-38 ramp (selective slabs) 60 days NOTE: This phase shall start no earlier than 30 days after the last concrete placement and turnover of Phase II.

Additional calendar days required for:

1. Initial Submittal Approval5days
2. Mobilization/Demobilization5days
3. Erection of Barriers/Safety Equip5days
4. Surveying/Site Layout2days
5. Long Delivery Impacts10days
(List/source company names, POC and phone number)
6.Material Availability10days
(list/source company names, POC and phone number)
7.Weather Impacts5days
8.Phasing Impacts5days
9.Security Delays (Secure area access)1days
10.Cleanup/Turf Establishment1days
11.Final Inspection1days
Subtotal50days
Total350days