Questions and Answers.docx

DOCX document 12 KB Posted

Attached to
HVAC Duct Cleaning Services Federal contract opportunity
Solicitation number
FA4800-11-T-0013
Issued by
Department of the Air Force Air Combat Command

About this file

Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to HVAC Duct Cleaning Services, newest first.
File Type Posted
FA4800-11-T-0013-0001.doc DOC document
Site Visit Meeting Minutes.docx DOCX document
FA4800-11-T-0013 Site Visit.docx DOCX document
FA4800-11-T-0013.docx DOCX document
Attachment 2 - Performance Plan.docx DOCX document
Attachment 1 - PWS.docx DOCX document
Attachment 3 - Wage Determination.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Item 001 = What are the dimensions of the 60 each exhaust fans?

The exhaust fans range from small 12"x12" to 48"x48" there are no kitchen exhaust fans just general exhaust fans.

2. Item 002 = How many of each size of the AHU's from 0.5 to 30 tons are included?

(Example: 0.5 ton = 6 each, 30 ton = 10 each, etc.)

The number of air handlers is not relevant we just need the pricing of our description

3. Item 003 = How many of each size of the AH's from 30 to 100 tons are included?

(Example: 30 ton = 6 each, 100 ton = 10 each, etc.)

The number of air handlers is not relevant we just need the pricing of our description

4. Item 004 = What are the dimensions of the VAV's?

They are all different sizes.

5. Item 005 = What are the dimensions of the water source heat pumps and where are they located? Rooftop, Ground, inside the buildings?

The water source heat pumps range in size from 1.5 ton to 15 ton and about 80% are located in the ceilings and the rest are in mechanical rooms.

6. Item 006 = What are the dimensions of the Supply, Return and Exhaust Ducts?

The dimensions of the supply and return ducts vary.

7. Item 010 = What are the dimensions of the fan coil units and is there access points on either side for cleaning?

They vary in size also from 1/2 ton to 3 tons and some have access and some do not.

8. Item 012 = What are the dimensions of the insulated supply and return ducts and is the internal insulation exposed?

The dimensions vary and the insulation is exposed.

9. Paragraphs 1.1.2.3, 1.1.3.2, 1.1.3.6, 1.1.7.2, 1.1.8.1.1, 1.1.9.1, 1.1.9.2 and 1.1.12.2 indicates work to be accomplish in accordance with NADCA standards. Does this solicitation require the contractor to be a member of NADCA and have ASCS's (Air Systems Cleaning Specialist) on staff and or on-site?

No you do not need to be a member of NADCA, but will use their standards.

10. If mold contamination is found does this solicitation require the contractor to have VSMR (Ventilation System Mold Remediator) trained and approved by NADCA?

No special training for mold will be required.

File details come from the government source that posted it. Updated .