Q and A.pdf
PDF 54 KB Posted
- Attached to
- Security Cameras Federal contract opportunity
- Solicitation number
- FA469023Q0016
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA469023Q00160001 SF 30.pdf | ||
| Performance Work Statement.pdf | ||
| Solicitation - FA469023Q0016 - Draft.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q1: What is the approximate distance from the camera locations to the ECP?
A1: 300 ft.
Q2: What is the projected height of the camera installation?
A2: 30 ft.
Q3: Will a lift be required, or will they be accessible by ladder?
A3: A lift will be required.
Q4: Is there a preexisting conduit or will the contractor be required to excavate?
A4: A separate contractor is currently tasked with dropping conduit. Wire will be required to be pulled through the conduit, but will not be required to be excavated.