Questions & Answers from Site Visit – 30 Mar 23
a) Can there be another site visit set up? The reason for our request is to have the specific subcontractors to what this project will require look at the site. Also, in order to prepare an accurate bid, we will need to have access to the main power panels and the fire riser/suppression room that was not available at the 30 March 2023 site visit.
Yes, a second site visit will be scheduled.
b) Can the as-builts be provided for B7510?
Yes. They will be attached to the amended solicitation.
c) Is there any asbestos in the construction work areas of the above listed project?
Unknown. The Government does not have samples from that area of the building. The blocks in the wall could potentially contain vermiculite but it is not known for certain.
d) Has there any led based paint?
Unknown. The Government does not have samples from that area of the building.
e) Has there been any engineers involved in the planning of the new Dust Collector Project, if so, can we be provided with them?
No, this is just replacement of existing equipment.
f) What will be the construction period for the above listed project?
The contract will not be broken down into periods. The contract will have a delivery due date of 180 days after award.
f) What will be the construction period for the above listed project?
The contract will not be broken down into periods. The contract will have a delivery due date of 180 days after award.
g) Will this project require a full design service (investigation, 35%, 65%, 95%, and 100%)?
No, this is just replacement of existing equipment.
h) Will the project area be occupied, and work being performed during the construction period?
Yes, but it will be limited.
i) Who is responsible for the deactivation of the current fire suppression?
Contractor will be responsible.
j) What is the term of the service contract?
The contract will not be broken down into periods. The contract will have a delivery due date of 180 days after award.