Attch_1_PWS_hoods_ducts_Rev_1.docx
DOCX document 41 KB Posted
- Attached to
- Cooking Hood And Exhaust Vent Cleaning Services
- Solicitation number
- FA469019QA003
About this file
Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_-_FA469019QA003.pdf | ||
| Attch_5_Site_Visit_Minutes.pdf | ||
| FA469019QA0030001_SF_30.pdf | ||
| Attch_3_Addendum_Revision_1.pdf | ||
| Attch_1_PWS_hoods_Rev_1_9-Nov-18.pdf | ||
| Attch_6_Bldg_2106_Map.pdf | ||
| Minutes_for_Site_Visit.pdf | ||
| Attch_2,_WD_15-5367_(Rev._9).pdf | ||
| Attch_4_Emergency_Cleaning_Price_schedule.XLSX | XLSX spreadsheet | |
| Attch_3_52.212-1_and_-2_addendum.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FOR COOKING HOOD AND EXHAUST VENT CLEANING SERVICES
31 Oct 2018
1. DESCRIPTION OF SERVICES. The contractor shall provide all management, tools, supplies, equipment and labor necessary to ensure that cooking hood and exhaust vent cleaning services are performed at Ellsworth AFB in a satisfactory manner.
1.1 Summary of SERVICES. The contractor shall inspect and clean the vertical and horizontal cooking hoods, filters and exhaust vent systems (See Appendix A) in accordance with NFPA Standard 96 except 11.6.1.1.1 Hoods, grease removal devices, fans, ducts, and other appurtenances shall be cleaned to remove combustible contaminants to a minimum of 50 microns(0.002 in). Authority having jurisdiction, (NFPA 96 - 3.2.2), Ellsworth AFB Fire Chief requires contractor to exceed NFPA 96 11.6.1.1.1 as follows. (Appendix C) Contractor shall ensure all hoods, grease removal device (filters), fans ducts, and other appurtenances are clean and free of residual oil and grease. Contractor shall coordinate cleaning times with the facility manager.
1.1.1. Contractor shall inspect hood and exhaust vent system before and after servicing and document any and all findings on the inspection checklist (Appendix B) IAW NFPA Standard 96. Pre-existing damage prior to starting work must be identified and documented through digital pictures with time stamp on the photo. The HVAC personnel and/or COR will inspect exhaust system the following business day after cleaning. If the exhaust system doesn’t meet the requirements of this PWS the contractor will be required to re-perform the service as indicated in the service delivery summary (see PWS item 5). Notification will be through both phone and email. Re-performance work will be at no additional cost to the Government.
1.1.2. Exhaust vent system shall be clean and dry after the system is serviced. All kitchen equipment effected by the cleaning service shall be returned to original location and functional status. Re-connect all services that were dis-connected. Clean all kitchen equipment that was effected by contracted cleaning operations.
1.1.3. Perform operational tests on hood and exhaust vent systems prior to and after cleaning IAW NFPA Standard 96. Document system status on inspection report. The exhaust system shall be reassembled and returned to original functional status after cleaning service. Failure to return exhaust system to pre-inspection operational status of this PWS shall require the contractor to return exhaust system to pre-inspection operational status within 3 hours of notification (phone and email). Re-performance work will be at no additional cost to the Government.
1.1.4. Exhaust system shall be returned to original operational status per pre-inspection report (PWS 1.1.1) failure to return exhaust system to pre-inspection operational status of this PWS shall require the contractor to return exhaust system to pre-inspection operational status within 3 hours of notification (phone and email). Re-performance work will be at no additional cost to the Government.
1.1.5. Submit a report of hood and exhaust vent system inspections and operational tests accomplished. Reports shall include a record of conditions before and after cleaning and completed operational tests and inspection results performed on each system. Contractor shall submit pictures of all components of exhaust system and kitchen equipment placement with time stamp in each the photo. Photos will include before cleaning and after cleaning pictures. Pictures will be sorted into individual folders per facility, each facility folder will have sub folders for before and after cleaning pictures. Photos shall be stored on a CD and delivered to the COR within three business days of cleaning the system.
1.1.6. Perform all work in strict accordance with the highest safety standards and applicable codes in order to eliminate the possibility of damage to installed machinery, equipment, personnel and building structures. All cleaning residue to include grease, oils, trash, soap and cleaning detergents will be removed from work site both inside and outside the facility when work is completed. Re-performance within 3 business hours of notification of valid defect at no additional cost to the Government.
1.1.7. After cleaning or inspection is completed, the contractor shall notify the COR immediately (normal business hours) or next business of areas that were inaccessible or not cleaned. The contractor will provide a written report that also specifies reason for deviation of service.
1.1.8. All damage caused by the Contractor due to performance of cleaning operations shall be repaired or replaced by the contractor at no additional cost to the government within 15 calendar days after identification and/or notification. The HVAC personnel, CO and COR will inspect repairs to ensure system is returned to pre-inspection operational status.
1.1.9. Contractor shall provide and display on each hood system serviced a semi permeant label indicating the date the exhaust system was cleaned and the name of the company that provided the service.
1.1.10. Unscheduled cleaning is any cleaning other than the scheduled cleanings identified in Appendix A. Cleaning of hood exhaust system shall be started within 12 hours of notification of request. Contractor shall clean the exhaust system to the same standard and level of quality that is performed during routine cleaning.
2. GENERAL INFORMATION.
2.1 QUALITY CONTROL. Contractor shall develop and maintain a quality program to ensure cleaning services are performed in accordance with the NFPA Standard 96 and other commonly accepted commercial practices. The contractor shall develop and implement procedures to identify and prevent defective services from reoccurring. As a minimum, the contractor shall develop quality control procedures that address the areas identified in paragraph 5, Service Delivery Summary. The COR shall have a specific company point of contact to notify in case of customer complaints.
2.2 HOURS OF OPERATION. Normal working hours will be based on the cleaning schedule that has been coordinated with the facility managers for the building to be cleaned. Days of service will be Monday through Friday unless otherwise approved by the COR. Majority of the buildings maybe cleaned after normal work hours. Services after normal duty hours shall be coordinated through the government representative.
2.2.1. Bowling alley is closed on Monday afternoons and is available for service after 1330 on that day only.
2.3 COORDINATIONS. Only the Contracting Officer is authorized to request/change services under this contract. All coordination’s shall be made through the COR at 385-2633 or 385 2623. All schedules shall be submitted to the government representative two weeks prior to the proposed schedule.
2.4 INSPECTIONS. All Hood and Exhaust Vent inspections shall be made by the 28 CES HVAC shop the next business day after cleaning. HVAC shop personnel will sign the completed inspection checklist (Appendix B) provided by the contractor.
3. SECURITY REQUIREMENTS.
3.1 Base Access and Passes. Contractor personnel and vehicles must obtain appropriate Base passes. Contractor shall initiate the process at the Contracting Office and proceed to the Security Police Pass and ID located at the Visitors Center. The contractor shall enter and exit the base through the Commercial Gate located at the south side of the base.
3.2 Compliance with Laws and Regulations. The contractor is subject to all base fire, safety and security regulations. The contractor shall obey all base, local, state and federal laws and regulations.
4. GOVERNMENT FURNISHED PROPERTY AND SERVICES.
Utility Service. The government will furnish the electricity, water, and sewage required to support this agreement.
Base Maps. Base maps shall be provided to the contractor to determine locations as required. Contact the COR (Charles Anderson) at 385-2633.
Security Police and Fire Protection. The government will provide security police and fire protection to the extent necessary to ensure a secure and safe installation. The contractor shall adhere to the security and fire directives, instructions, and policies of Ellsworth Air Force.
Emergency Services. The contractor shall reimburse the government for emergency medical treatment and transportation if these services are required.
5. SERVICE DELIVERY SUMMARY.
6. APPENDICES.
A. Estimated Workload Data B. Inspection Checklist C. AHJ Ellsworth Fire Chief
APPENDIX A ESTIMATED WORKLOAD DATA
APPENDIX B INSPECTION CHECKLIST
image1.emf image2.emf image3.emf