Text version

BASE YEAR

CLIN DESCRIPTIONS - ROOF SYSTEMS MAINTENANCE AND REPAIR
CLINUNIT OF ISSUEDESCRIPTION
ASPHALT SHINGLES
AASFRemove and replace individual shingles; match existing type, texture and color, as available. Includes fasteners and roofing cement, as necessary. Measurement based upon exposed area of shingle(s).
ABSFRemove shingles, edge metal and underlayment for reroof; one or two layers, as required. Remove to deck and prep for reroof. Notify contracting officer of discrepancies NIC. Includes re-nailing loose sheathing. Does not include repair/replacement of sheathing.
ACLFInstall edge metal for reshingling. Includeds fasteners. Measurement based on actual dimensions of roof.
ADSFInstall laminated architectural shingles; Class A, minimum 215 lb/sq; Provide minimum 30-yr manufacturer's warranty. Includes fasteners, starter strip, ridge and hip shingles. Does not include underlayment, vents or flashing. Measurements based on actual dimensions of roof.
WOOD
AEBFRemove and replace deteriorated wood decking, isolated areas, 2" max nominal thickness. Cut out and replace deteriorated areas of wood decking as directed the CO. Replace with similar decking, or CDX plywood as directed by the CO. Includes removal, decking, fasteners and clips. Measurements based on actual areas replaced.
AFSFInstall 1/2" CDX plywood sheathing. Includes sheathing, fasteners and clips.
AGSFInstall 1/2" CDX backing for roof flashings and membranes. Install as directed over curbs, parapet walls, cants and crickets as a backer for adhered single-ply membranes and flashings. Includes fasteners and/or adhesives. Measurements based upon actual installed areas.
AHBFRemove existing wood framing, curbing, blocking, nailers, trim and fascia. Remove and prep substrate to receive new materials, as necessary. Measurements based on nominal sizes of materials removed.
AJBFInstall wood cants, curbing, blocking and nailers. Provide treatment per applicable roof spec section. Includes fasteners, cutting, tapering, as required. Measurements based on nominal size of installed materials.
AKBFInstall wood framing. Includes fasteners. Does not include hangars, straps, anchors, bolts, clips, etc. Measurements based on nominal sizes of materials installed.
ALBFInstall wood trim and fascia board. Includes wood, fasteners, and installation. Does not include surface prep, priming and painting. Measurements based upon actual area installed.
ROOF INSULATION
AMBFRemove existing insulation. Includes removal and disposal of additional thickness of roof insulation, fasteners, adhesive, asphalt, vapor barrier and base sheet not included in an applicable roof removal CLIN. Measurements based upon actual applicable area and thickness of roof assembly less thickness removed under the appropriate roof removal CLIN.
ANBFInstall tapered polyisocyanurate insulation. Taper and layout to be identified on the plans or provided by the Government. Includes tapered boards, adhesive, asphalt or fasteners as required. Measurements based upon average thickness of tapered boards x area of boards as installed per plan.
APSFInstall coverboard for PVC or EPDM reroof. Install manufacturer's recommended high density iso or gypsum coverboard, 1/2" thickness, including fasteners, adhesive or asphalt, for recover or over new insulation, as specified.
AQSFInstall 4" polyisocyanurate insulation in two layers with joints staggered. Includes asphalt, adhesive or fasteners, as applicable.
ARSFInstall 5" polyisocyanurate insulation in two layers with joints staggered. Includes asphalt, adhesive or fasteners, as applicable.
ASSFInstall R19 fiberglass batt insulation, unfaced, installed in attics or wall cavities. Includes fasteners as required.
ATSFInstall R38 fiberglass batt insulation, unfaced, installed in attics or wall cavities. Includes fasteners as required.
AUSFInstall 6 mil polyethelene vapor barrier, including taped joints and repair before covering.
METAL ROOFING SYSTEMS
AVSFRemove existing metal roof or wall panels and flashings. Includes removal and disposal of metal, fasteners and any underlayment. Measurement based on area of coverage.
AWSFReattach existing loose metal roof or wall panels and flashings. Includes new fasteners or clips, as required. Measurement based on area of coverage.
AXSFInstall corrugated steel roof or wall panels, field painted. Includes 24 ga G90 finished panel to match existing, fasteners, prep, prime and paint. Measurement based on actual area of coverage.
AYSFInstall SSMR system: 20 yr warr. Includes panels, clips, fasteners, seam sealants and warranty. Does not include, deck, insulation, vapor barrier, flashings, gutters, closures, purlins, substrate, etc. Measurement shall be based on the actual area of the roof.
AZLBInstall light-gage steel supports for structural SSMR system incl. purlins, subpurlins, rafters, columns, braces, plates and fasteners. Does not include roof panels, flashings, closures, insulation, deck or sealants. Measurements based upon estimated calculations from manufacturer's data.
BALFInstall SSMR system flashing for rake, eave, sidewall or headwall incl. fasteners, closures, sealants, and counterflashing. Does not include gutters, vents, curbs or accessories. Measurement based on actual field length of flashing installation.
BBLFInstall SSMR system flashing for ridge, hip or valley including all fasteners, closures, sealants, and counterflashing. Does not include vents, gutters, curbs or accessories. Measurement based on actual field length of flashing installation.
BCLFInstall SSMR system snow retention system, S-5 Color Guard w/snow clips, or equal, clamped to SSMR system ribs. Includes clamps at all ribs, snow clips between all ribs, bar and color-matching metal. Measurement based on actual field length installation.
BUILT-UP ROOFING SYSTEM (BURS) BUR items referenced to NRCA published guidelines and details for BUR roofing, reroofing and repair.
BDSFSweep and spud gravel for repair, store on roof. Includes sweeping of loose gravel, spudding of embedded gravel, and surface prep to receive repair. Does not include new materials.
BESFRemove BUR for replace, incl. gravel, roof plies, insulation, flashing and cants. Includes removal of all materials to deck except for adhered, mopped base sheets and vapor barriers, which may remain. Includes removal of 3" maximum thickness of roof plies and insulation. Additional roof insulation thickness greater than 3" shall be included in item AM.
BFSFRepair blisters and splits in BUR membrane per NRCA repair guidelines
BGSFRepair wind scours per NRCA repair guidelines
BHSFInstall 2-ply mopped roof for vapor barrier or temp roof
SINGLE-PLY ROOFING SYSTEMS
BJSFInstall .060" fully-adhered EPDM membrane roof system; not incl. insulation, flashings and accessories; 20 yr mfr. warr. Includes membrane, adhesive and field seams.
BKLFInstall EPDM flashing system on .060" EPDM roof edges and penetrations; incl. attachment strips, fasteners, sealants, adhesives, term. bars, cover strips and accessories. (not incl. nailers, cants, cleats and metal flashings)
BLSFInstall EPDM roof membrane patch. Measurement based size of patch as recommended by roof membrane manufacturer.
BMSFInstall .072" fully-adhered PVC membrane roof system; not incl. insulation, flashings and accessories; 20 yr mfr. warr. Includes membrane, adhesive and field seams.
BNLFInstall PVC flashing system on .072" PVC roof edges and penetrations; incl. attachment strips, fasteners, sealants, adhesives, cover strips and accessories. (not incl. nailers, cants cleats and metal flashings)
BPSFInstall PVC roof membrane patch. Measurement based size of patch as recommended by roof membrane manufacturer.
BQSFInstall water-based, liquid acrylic roofing membrane. "TOPCOAT MEMBRANE" system, or approved equal, applied in two coats for a total dft of 22-25 mils. Includes pressure washing, and tightening/encapsulating of fasteners. Does not include roof repairs, patching, priming or treatment of joints and seams with reinforcing fabric and flashing grade membrane.
BRSFInstall synthetic rubber waterproofing elastomeric sealant, TOPCOAT FLASHING GRADE or approved equal. Apply along seams, joints and base flashings at approximately 1 gal/ 12 SF. Includes surface prep, tightening/replacement of fasteners. Does not include final membrane or reinforcing fabric.
BSSFInstall non-woven, spunbound polyester seam reinforcing fabric, TOPCOAT TOPESTER or approved equal. Instal 6" wide fabric embedded in FLASHING GRADE sealant along seams, joints and fastener lines as specified. Does not include surface prep, sealant or final membrane.
FLASHINGS AND METALS
BTLFRemove and replace BUR base flashing for repair, <5' per location. Includes cutting and removal of sections of loose or unsound BUR base flashing, and covering with new mineral-surfaced modified bitumen base flashing per NRCA repair guidelines.
BULFRemove, clean, straighten and reinstall sheet metal flashing. Includes removal to prevent damage and allow for re-use, cleaning of excess sealant and coating, straightening to improve function and appearance and reinstallation with new fasteners as necessary. Does not include new flashing, paint, sealant, cleat, underlayment, reglet or related repairs.
BVLFSawcut for reglet in masonry or concrete. Includes sawcutting for new or modified reglet installation, up to 1" depth.
BWLFInstall Kynar-finished steel counter flashing. Includes two-piece, removable counter flashing system with fasteners and sealant for surface mount or reglet installation. Does not include cutting for reglet or removal of old flashing and sealant.
BXSFRemove existing sheet metal fascia, coping and flashing
BYSFInstall 24 ga. Kynar-finished fascia, coping and flashing. Includes misc. flashings of various shapes, lengths and widths not covered under any other CLIN. Measurement based upon actual "stretch-out" area of metal used.
BZSFInstall 24 ga. Kynar-finished soffit panel, plain or vented
CALFIncreased cost for vented ridge flashing vs non-vented. Includes increased ridge flashing width, 1" thick venting media, sheet metal baffles, spacers and fasteners.
CBLFInstall 24 ga. galvanized steel continous cleat
CCEAInstall pipe penetration flashing: 0 to 6" dia.
CDEAInstall pipe penetration flashing: 6"+ to 12" dia.
GUTTERS AND DOWNSPOUTS
CELFClean out gutters and downspouts
CFLFRemove existing gutters and downspouts
CGLFInstall Kynar pre-finished sheet metal gutters. Furnish and install 24 ga. Kynar-finished steel gutters up to 4"x6", as specified.
CHLFInstall Kynar pre-finished sheet metal downspouts. Furnish and install 24 ga. Kynar-finished steel downspouts up to 4"x6", as specified.
CJEAInstall Kynar pre-finished 24 ga. steel roof scupper box
CKEAInstall precast concrete splash blocks
SEALANTS
CLLFRemove existing backer rod and sealant, clean joint for reseal
CMLFInstall backer rod and polyurethane sealant: 0 to 5/8" wide
CNLFInstall backer rod and polyurethane sealant: >5/8" wide
CPLBInstall polyurethane sealant, misc. joints and seams: no backer rod
CQLBInstall butyl sealant, misc. joints and seams: no backer rod
ROOF DRAINS
CREAClean in and around roof drains. Remove debris from drain, drain basket and drain sump area. Inspect drain and reinstall basket. Remove debris from roof
CSEAInstall new clamp ring and bolts. Provide and install new ring and bolts. Drill and tap broken bolts or stripped holes.
CTEAInstall new strainer basket. Includes replacement drain basket to replace damage or missing basket.
CUEARe-flash existing drain in single ply roof. Includes a maximum of nine square feet of replacement or patched membrane, seaming, flashing and sealing.
MISCELLANEOUS TASKS
CVSFInstall new EPDM or PVC walkway pad. Includes pads and adhesive, measurement based on actual size.
CWSFInstall new concrete paver walkway. Includes 2-1/2" concrete pavers and slipsheet membrane, measurement based on actual size of pavers.
CXLFFabricate & install plumbers vent extension 2-6" diam. Includes pipe and coupling as necessary to extend vent
CYEARemove and re-install existing ventilator as necessary to replace or repair roof.
CZLBRemove and re-install rooftop mounted equipment as necessary to replace or repair roof.
DAEAFill pitch pans
DBSFInstall water & ice shield
DCSFInstall #15 felt underlayment, no mopping. Includes fasteners. Quantity based on actual area of roof.
DDSFRemove existing, deteriorated steel roof decking
DESFInstall new steel roof decking to match existing
DFSFField paint wood or metal surface. Includes surface preparation, priming and painting of new or existing surfaces, to match existing adjacent finished surface, or as directed by Contracting Officer.
DG5 GalSiloxane Masonry Water Repellant. Includes material, surface prep as necessary, and installation.
MOBILIZATION AND SERVICE CALLS
DHEALeak service call (Two-man crew, three hours on-site, first $200 in materials). Includes mobilization and three hours on site for a repair crew consisting of a minimum of an experienced roofer and laborer. Perform repair and maintenance as prescribed by Contracting Officer or authorized representative. Log and submit report of time expended, materials used, work completed and additional work recommended. Leak service call Delivery Orders will be placed as either Urgent or Routine. The Contractor shall respond to Urgent service calls within 72 hours, not including Sat, Sun and Federal Holidays; and Routine service calls within 14 calendar days.
DJEAEmergency leak service call. Includes Leak Service Call requirements requested by Contracting Officer to be performed within 24 hours, including weekends and Federal Holidays. The Contractor shall provide telephone contact number(s) for "after hours" Emergency leak service calls. Service calls placed by telephone shall be confirmed to the Contractor in writing the next business day.
DKHRExtended time on site for service call crew, when authorized. Includes additional on site hours for two-man Leak Service Call crew to increase time authorized on a Leak Service Call.
DLEAMobilization of roofing crew, once each per facility, per delivery order. Includes minimum initial mobilization costs for initial crew, to be paid once per each facility, per each Delivery Order, except not to be included on Leak Service Calls.
DMEAMobilization and prep. of asphalt kettle, once each per facility, per delivery order when needed. Includes mobilization, setup, startup, shutdown and demobilization of asphalt kettle to be paid once per each facility where required, per each Delivery Order where required.

&C&"Arial,Bold"ROOFING SYSTEMS MAINTENANCE AND REPAIR, ELLSWORTH AFB

&C&P OF &N