This is a Questions and Answers document for a federal contract opportunity for restroom/shower trailer services. The contract is a standalone purchase order (not a BPA) with no previous contractor, requiring a mobile restroom and shower trailer for a 12-month lease period at a Munitions Storage Area. The contract structure includes four CLINs: setup (CLIN 0001), monthly lease (CLIN 0002), weekly waste tank servicing (CLIN 0003), and demobilization (CLIN 0004).
Key contract terms include Net 30 payment terms, WAWF invoicing platform using the 2-in-1 format, and monthly invoicing for the lease and service CLINs while setup and demobilization are billed separately upon completion. The site will provide electricity and water via spigot/hose connection, with the trailer requiring external water pumping capability and offsite waste disposal. Subcontractors are permitted, with general liability insurance not required under the firm fixed price structure. The government will provide a point of contact after award for delivery coordination, with inspection and acceptance occurring at destination. Repair response time for non-functional components is within one month of notification, and the only required servicing is weekly waste tank emptying with no additional housekeeping requirements. The contract is not expected to extend beyond the 12-month performance period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Are subcontractors allowed under this contract?
a. ANSWER: Yes, Subcontractors are allowed. The Governments contractual relationship is with the Prime Contractor.
2. What are the payment terms (e.g., Net 30)?
a. ANSWER: Yes, payment terms are Net 30. Please reference FAR Clause 52.232.25
3. Is WAWF the correct invoicing platform for this order? If so, should we use the 2-in-1 format for combined invoice and receiving report?
a. ANSWER: Yes, please reference FAR Clause 252.232-7006 .
4. Can we invoice monthly, or is there a different schedule?
a. ANSWER Yes, CLIN 0002 & 0003 can be invoiced monthly as the unit of measure is “MO” . See CLIN Structure in SF 1449. CLIN 0001 and 0004 are one time invoice.
5. Will electricity and water be provided at the site, or should the trailer be fully self-contained?
a. ANSWER: Electricity and water will be provided on site. The trailer should have a way to pump water into the fresh water tank externally.
6. Will a point of contact for coordinating delivery, weekly service, and pickup be provided after award?
a. ANSWER: Yes, please reference SF 1449, Inspection and Acceptance for POC information.
7. How will inspection and acceptance be handled?
a. ANSWER: Please reference 52.212-4(a)Acceptance will occur at destination upon delivery & the Government has the right to inspect all services in accordance with the contract requirements as called for by the order.
8. With the deadline being August 14th, what is the expected award and start date?
a. ANSWER: Expected award will ideally be within a week. We have to allow time to review quotes and draft documentation. Reference SF 1449 for estimated start date.
9. Is this part of a BPA or a standalone contract?
a. ANSWER: This is not a BPA, this is a stand-alone purchase order.
10. Is there a current or previous contractor for this requirement?
a. ANSWER: No, there is not a previous contractor for this requirement.
11. Can CLINs 0002 and 0003 be invoiced monthly throughout the 12-month lease
a. ANSWER: Yes, CLIN 0002 & 0003 can be invoiced monthly as the unit of measure is “MO” . See CLIN Structure in SF 1449.
12. Should CLINs 0001 (setup) and 0004 (demobilization) be invoiced separately upon completion?
a. ANSWER: Yes, they should be billed separately as they are separate line items.
13. If a trailer component (example, sink, toilet, or shower) becomes non-functional during the lease, is there a required response or repair timeframe?
a. ANSWER: Response should be addressed within a month of official notification.
14. If government personnel cause damage to the trailers, will the government accept responsibility for the cost of repair or replacement? If so, what is the process?
a. ANSWER: Please reference 52.212-4(j). If an item becomes non-functional, the Government will notify the Contractor and request a quote for the repairs and then an REA would be executed.
15. Will the government require the prime contractor to carry general liability or other insurance coverage for this contract?
a. ANSWER: not required under a firm fixed price
16. Will the subcontractor performing the work also be required to provide proof of insurance to the government?
a. ANSWER: The government usually does not directly require subcontractors to provide proof of insurance to the government . However, the prime contractor is responsible for ensuring that its subcontractors comply with insurance requirements that they pass down in the subcontract.
17. Are there any additional compliance requirements (e.g., OSHA, environmental, state licenses) that apply to the trailer servicing or waste disposal?
a. ANSWER: No known requirements as this is a closed loop system without any generator(air quality)
18. Will the government require proof of licenses or certifications from subcontractors (e.g., for waste handling)?
a. No, not required
19. Is there a designated or proposed disposal area?
a. ANSWER: Offsite disposal required, the Munitions Storage Area does not have any capabilities.
20. Will there be any water connection spigot for the restroom? I have access to trailer units that have a 200 gallon freshwater tank, However, since it’s a shower trailer, we strongly recommend connecting it directly to a water spigot for consistent water flow and optimal use.
a. ANSWER: There is a spigot/hose that can reach the designated area for the trailer mount point.
21. Is there a likely hood that this contract will extend beyond the POP?
a. ANSWER: No, there is no reason at this time to believe it will extend beyond 12
Months
22. Please advise on housekeeping schedule for interiors of restroom/shower mounted trailer: Shower environments require more regular housekeeping that restrooms typically Our suggestion is 3x pr week minimum.
a. ANSWER: The only servicing requirements expected from the vendor is to empty the waste tank weekly. No other servicing requirement are needed.