Attachment 01 Statement of Need Revision 01 .pdf

PDF 226 KB Posted

Attached to
FA468624R0033 B4793 Capehart Vendor Hood Install
Solicitation number
FA468624R0033
Issued by

About this file

This document is a Statement of Need (SON) for the B4793 Capehart Vendor Hood Install project at Beale Air Force Base. The contractor shall furnish all supervision, labor, tools, equipment, materials, operations, and incidentals required to install one (1) Type 1 Commercial Kitchen Grease Hood to support three (3) vat fryers and one 4ft flat grill, including fire suppression equipment/system. The contractor shall also replace the current duct system with a Class 1 air duct that supports the Type 1 hood, install a new exhaust fan, and provide a metal roof catwalk system for cleaning access. The work must comply with all applicable NFPA, AFI, UFC, and ETL fire safety standards. The project has an estimated cost between $100,000 and $250,000, and is 100% set aside for small businesses. The site visit is scheduled for August 27, 2024, and proposals are due by September 11, 2024.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 9TH RECONNAISSANCE WING (ACC)

BEALE AIR FORCE BASE, CALIFORNIA

21 Aug 2024

MEMORANDUM FOR 9 CONS

FROM: 9 CES/CEOER

SUBJECT: B4793 Capehart Vendor Hood Install - Statement of Need (SON)

A. General Scope. The contractor shall furnish all supervision, labor, tools, equipment, materials, operations, and incidentals as required to do the following:

COMMERCIAL KITCHEN HOOD:

• In preparation of supporting a new food vendor at the Capehart gas station, Beale AFB is seeking a qualified commercial kitchen contractor to install one (1) Type 1 Commercial

Kitchen Grease Hood that will support three (3) vat fryers and one 4ft flat grill.

• Kitchen hood should meet all fire code requirements for a commercial kitchen hood, including fire suppression equipment/system.

• Install breaker, wiring, conduit, and associated electrical components as needed to support the new equipment.

DUCT SYSTEM:

• Replace current duct system with a Class 1 air duct that supports a Type 1 hood, with cleanouts at required intervals, and single vertical venting configuration.

• Remove exterior exhaust fan, patch wall, and install exhaust fan to new duct system

• Install metal roof catwalk system for cleaning access

B. Other Requirements. Drawings/As-Builts require stamp of approval from a licensed Fire

Protection Engineer. Contractor shall comply with IAW, all NFPA (including NFPA 96), AFI, UFC (including UFC 3-600-01), and ETL standards for fire safety.

C. Authorized Work. Work shall be accomplished in accordance with all contractually incorporated documents. Any work that is accomplished outside of the contractual documents, unless authorized by a contracting officer, is accomplished at the contractor’s own risk.

D. All work shall be accomplished between 0700-1700 Mon-Fri.

E. All contractor vehicles must enter the base via the Wheatland Gate and shall be subject to inspection. All contractor personnel must obtain base passes or be listed on the Entry Access

List (EAL) throughout duration of work performance. Any persons in the EAL are required to bring two (2) forms of identification or REAL ID to access the base.

F. The Government/AAFES will remove any items/equipment in i ts vicinity in preparation for this project and will return any items/equipment after work is complete.

G. Work Items. The contractor shall comply with all applicable Federal, State, and local

NEC construction standards. Current Air Force Occupational Safety and Health

(AFOSH) standards and COVID-19 safety regulations also apply.

All metal and equipment recycling will be disposed of on base to the 9 CES Recycle yard. All other waste material is to be removed off base by the Contractor, POC: Shane Morris at 530-634-

0744 or shane.morris.5@us.af.mil. Contractor will practice good housekeeping during the project.

WARREN R. CINCO, CIV, USAF

Planner/Manager mailto:shane.morris.5@us.af.mil

2024-08-27T11:32:37-0700
CINCO.WARREN.RIONDA.1254153113