RFIs1-10-9PSPTSLargeCompressor.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
Large Air Compressor System
Solicitation number
FA468624Q0523
Issued by

About this file

This document is a Request for Information (RFI) related to a federal contract opportunity for a Large Air Compressor System. The RFI contains questions and answers regarding the specifications of the existing compressors, such as breaker size, electrical ratings, hours of operation, and the duration the compressors have been down. The key details gathered from the RFI include:

The contract opportunity is for the Department of the Air Force Air Combat Command, with a solicitation number of FA468624Q0523. The government is seeking a contractor to replace the existing large air compressor system. The new compressors must meet or exceed the capacity and specifications of the current units, including being oil-less, providing the required PSIG and CFM capacity, and having the ability to cool and dry the air before entering the building plumbing. The government will provide a forklift and operator to assist with loading and unloading the equipment. The expected project completion date is one month from the date of award, though the contractor's proposed period of performance is requested. A site visit is scheduled for August 29th, 2024, and interested parties must submit an Escort Approval Letter by August 27th, 2024.

View the file

Other files

File Type Posted
RFQ - PSPTS Large Compressor Amendment 1.pdf PDF
PXL_20240819_153031833.jpg JPG image
PXL_20240819_153017038.jpg JPG image
PXL_20240819_153114051.jpg JPG image
PXL_20240819_152915666.jpg JPG image
PXL_20240819_152855634.jpg JPG image
PXL_20240819_152841514.jpg JPG image
PXL_20240819_152819081.jpg JPG image
EAL-Template.xlsx XLSX spreadsheet
Large Compressor SON FINAL_Redacted.pdf PDF
RFQ - PSPTS Large Compressor FINAL.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionsAnswers
What is the breaker size for the compressor? We are asking for the listed volts and amps for the two electrical circuits for the two compressors mounted on the horizontal tank.40AMPS (2 each)
Where are these breakers located? We will need access to them during the removal and installation process.Loctaed DOWNSTAIRS mechanical room
Will base staff be provided during the removal and installation process to assist with any unforeseen occurrences for us to ask questions of or specific site directs for these occurrences? Usually one representative is available minimum by telephone, not necessarily on site, for this interaction.Yes, a base staff member will be available by phone call during working hours.
What is the electrical rating for the two disconnects on the front control panel of the compressor? Is there a separate breaker in these disconnects or are they only mechanical disconnects?They are only mechanical disconnects
What are your hours of operation?M-F, approximately 16 hours per day with a potential for 24 hours per day. Sa-Sun, zero, with potential for seven day a week operations.
How long has the compressor been down?18 months
What is the USAF expected project completion?One month from date of award. (This is the customer's expected project completion date. The contractor will not be required to complete the project within this time frame. Please provide your proposed period of performance on the RFQ Combo.)
Do you have an approved MFR for this compressor , or any will do if it meets the minimum specifications?As long as the new units meet or exeed the current units specifications and or capacity, that is what we are needing. Some key specs: Oil-less Compressors, equal or greater PSIG and CFM capacity of air, and the Cooling/ Drying of the air before entering the building plumbing, and the auto moisture drain tank feature.
Do site personnel have access to a forklift and operator for us to use for the day for loading the old unit for disposal and unloading the new unit from our truck?A forklift and operator can be provided by the government upon request. We can coordinate it for the planned day.