Questions and Answers for CVIA Office Trailer.docx
DOCX document 16 KB Posted
- Attached to
- CVIA Office Trailer
- Solicitation number
- FA468624Q0016
About this file
This document is a Questions and Answers (Q&A) for a solicitation related to a CVIA Office Trailer requirement. The key details are:
The solicitation is for the purchase of an 8x40 or 10x40 office trailer for use at Beale AFB, CA. The trailer does not require restrooms, HVAC, or electrical hookups, as those will be provided by the government. The trailer should be delivered by May 31st and can be either new or used. The government is open to a 10x36 or 12x46 trailer if the 8x40 or 10x40 size is not available. The trailer must be placed on a flat, dirt surface and accessible by truck. No ADA compliance is required. This is for the purchase of an office trailer, not a container office.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ - CVIA Trailer.pdf | ||
| Questions and Answers for CVIA Office Trailer.docx | DOCX document | |
| RFQ - CVIA Trailer.pdf | ||
| CVIA Trailer SON.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers for CVIA Office Trailer
· What size do I need? (Single, Double, or Triple Wide) Must be 8x40 or 10x40.
· How many people do I need to accommodate? This is not a factor, must be size requested.
· How much space do I have? There is enough space to fit up to 10x40
· Is the site where I'm placing the office truck accessible? (Is the site clear of obstacles that may impede a truck from reaching the set location?) Yes
· Is the site flat and level? ( What type of terrain am I setting the building? Does it need to be prepped?) Yes, on dirt.
· Do I need restrooms? If so, I am responsible for calling a plumber to set up my septic system. No
· Do I need electricity in my office? If so, I am responsible for calling an electrician to hook up my electricity. No
· Do you plan on leasing or purchasing? If purchased, is it used or new? If leased, how many months or year? Purchase
· Where exactly does the trailer need to be delivered to? South Beale, Beale AFB, CA 95903
· Will it be placed on a flat surface? The area will be dirt, but flat.
· Will the area be "prepared" for the delivery and placement of the trailer? If you mean will the area, be clean of debris, yes the area will be prepared
· Is there a clear path to the trailer site? Yes
· would a standard mobile office on wheels be ok? Not a must, but I’m concerned with safety and liability. We rather not have stairs to prevent mishaps with our airmen and customers.
· Are you looking for a container office? (it would not have a restroom) Yes
· You indicated a need for an 8x40, would a 10x36 work for you? Or an 12x46? Like to stay at 8X40 or a 10X40.
· Do you have spatial parameters, or boundaries you are trying to remain within? The area can handle up to a 10X40.
· Do you need ADA compliancy for entry with a wheelchair ramp, or only steps? No
· If you are looking for a unit with a restroom, is there access to utilities (water, sewer, electricity)? No restroom, power and communication will be available for the trailer.
· SOW states Heating, Ventilation and A/C required however there are no specs for any system nor any specs on a electrical package to power the appliances. How does the customer plan on running the equipment? HVAC should be sufficient for the area. The government will be installing its own electrical package.
· Is the office container to be insulated? Not required.
· Will customer have lift service at destination? No
· Confirmation on whether this is for an office trailer or for a container office? This is for a office trailer, we were unaware there was a difference.