Answers_to_RFsI_on_FA4664-15-T-0002_Solicitation.pdf

PDF 168 KB Posted

Attached to
Clean Room, Blast Room and Curring Oven Purchase & Installation
Solicitation number
FA4664-16-T-0004
Issued by

About this file

Questions and answers to RFIs submitted for FA4664-16-T-0004 Solicitation

View the file

Other files

File Type Posted
RFIs_ _answers_on_FA4664_16_T_0004.docx DOCX document
Statement_of_Work_all_3_items.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs on FA4664-16-T-0004 Solicitat ion:

Question 1: Please provide the contact information for the base South Coast Air Quality Management representative Response 1: Melissa Sanchez (909)396-2355

Question 2: The clean room is required to have over head sprinklers, will the contractor be required to install notification signaling from the clean room back to the hangar fire alarm panel?

Response 2: Yes

Question 3: Clean room specification is calling out for “walls 3” thick” the industry standard for modular rooms is 2” walls insulated with 800 degree rock wool. Can the contractor provide 2” insulated walls?

Response 3: Yes

Question 4: In the clean room can we substitute the ceiling tiles with 18-gauge powder coated white steel panels for the ceiling? This will allow for easier cleaning and help with the truss structure necessary to support the A/C system and assist with overhead fire suppression and installation of the overhed lighting Response 4: Yes

Question 5: What is the maximum weight load in the oven?

Response 5: No more than 500 lbs.

Question 6: Please define cure oven “wheel guides” Response 6: Recessed tracks in the floor to facilitate our racks to be moved in and out.

Question 7: Can the breathing air purifier be moved (by contractor) to the back wall to allow more clearance for the blast room?

Response 7: Yes