Test Requirements

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEST/REQUIREMENTS LIST

This report lists all the test requirements cited in the text.

SECTION: 01 14 00 SUBPART: 1.4.1

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project.

SECTION: 02 41 00 SUBPART: 1.3

Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

SECTION: 02 41 00 SUBPART: 1.8

If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris.

SECTION: 02 82 16.00 20 SUBPART: 3.2.5.2

Field test the encapsulation test patches in accordance with ASTM E1494, paragraph "Required Field Test," in the presence of the Contracting Officer.

SECTION: 02 82 16.00 20 SUBPART: 3.3.3.1

An area for interim storage of asbestos waste-containing drums or skids will be assigned by the Contracting Officer or his authorized representative.

SECTION: 05 12 00 SUBPART: 3.7

Perform field tests, and provide labor, equipment, and incidentals required for testing. The Contracting Officer must be notified in writing of defective welds, bolts, nuts, and washers within 7 working days of the date of the inspection.

SECTION: 05 12 00 SUBPART: 3.7.3

ASTM A143/A143M for steel products hot-dip galvanized after fabrication.

SECTION: 08 33 23 SUBPART: 2.2.1

Provide test data showing compliance with ASTM E330

SECTION: 08 33 23 SUBPART: 2.3.2

The insulated slat assembly requires a flame spread rating of not more than 25 and a smoke development factor of not more than 50 when tested in accordance with ASTM E84.

6EPLACE STEEL COLUMN ANCHORS AND ROLL-UP DOORSAttachment 6 to
March 11, 2015BLDG1244 3:07 PMFA4664-15-R-0014

Test/Requirements List Page 1

SECTION: 08 33 23 SUBPART: 3.3

Test the door opening and closing operation when activated by controls or alarm-connected fire-release system. Adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. Reset door-closing mechanism after successful test.

SECTION: 08 33 23 SUBPART: 3.3.1

Not more than 90 calendar days after completion and acceptance of the project, examine, lubricate, test, and re-adjust doors as required for proper operation.

SECTION: 26 20 00 SUBPART: 3.3.1

Operate each device subject to manual operation at least five times, demonstrating satisfactory operation each time.

SECTION: 26 20 00 SUBPART: 3.3.2

Test wiring rated 600 volt and less to verify that no short circuits or accidental grounds exist. Perform insulation resistance tests on wiring No. 6 AWG and larger diameter using instrument which applies voltage of approximately 500 volts to provide direct reading of resistance.

SECTION: 26 20 00 SUBPART: 3.3.3

Test grounding system to ensure continuity, and that resistance to ground is not excessive.