FA4664-13-R-0006_-_Atch_5_01330_Submittal_Procedures.doc
DOC document 35 KB Posted
- Solicitation number
- FA4664-13-R-0006
About this file
Attachment 5 - Specification 01330
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Walk_Notes.pdf | ||
| FA4664-13-R-0006_-_Atch_3_Rule1147.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_1_Wage_Decision.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_01670_Recycled_Recovered_Materials.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_01780A_Closeout_Submittals.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_4_Schedule_of_Material_Submittals.pdf | ||
| FA4664-13-R-0006.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_01355_Environmental_Protection.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_15190_Gas_Piping_Systems.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_01010_General_Conditions.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_2_SOW_Low_NOx_Heating_System_9_May_2013.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_5_01351_Safety_Health_and_Emergency_Response.doc | DOC document | |
| FA4664-13-R-0006_-_Atch_6_Existing_Equipment_Data_Sheet.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5 to
FA4664-13-R-0006
SECTION 01330
SUBMITTAL PROCEDURES
03/01
PART 1 GENERAL
1.1 Government Approved
The Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Contractor shall be required to submit “shop drawings” as required in the individual specification sections herein or as requested by the government.
1.2 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the CQC requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.3 DISAPPROVED SUBMITTALS
The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.
1.4 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL
The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be shall be stamped, signed, and dated by the CQC representative indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
3.2 SCHEDULE OF MATERIAL SUBMITTALS (AF FORM 66)
At the end of this section is one set of AF Form 66 listing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The approved submittal will become the scheduling document and will be used to control submittals throughout the life of the contract. The submittal and the progress schedules shall be coordinated.
3.3 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 35 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
3.4 AS-BUILT DRAWINGS
The contractor shall furnish one full set of as-built black line prints for use in preparation of as-built drawings by the Government. The as-built prints shall be a record of the construction as installed and completed by the contractor. They shall include all the information shown on the contract set of drawings and a record of all deviations, modifications, or changes from those drawings, however minor, which were incorporated in the work, all additional work not appearing on the contract drawings, and all changes which are made after final inspection of the contract work. An electronic copy of the as-built drawing shall be submitted in AutoCAD 2008 format.
3.5 CONTROL OF SUBMITTALS
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Schedule of Submittals."
3.6 GOVERNMENT APPROVED SUBMITTALS
Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Three (3) copies of the submittal will be retained by the Contracting Officer and one (1) copy of the submittal will be returned to the Contractor.
-- End of Section –-