This is a Questions and Answers document for a washer/dryer lease procurement at Dyess Air Force Base. The Q&A clarifies that the requirement is for 12 barracks buildings, with no elevators, but with sidewalk access. The equipment requirements include 72 single washers, 72 single dryers, and 76 combo washer/dryers (which can be either stacked units or all-in-one combos). All dryers require 4-prong electrical connections.

The facility offers both short-term storage (2,000 sq ft climate-controlled and 2,000 sq ft warehouse with loading dock) and long-term storage (200 sq ft within dorms). Service calls have been revised from 500 to 75 per year, with payment only for actual calls completed. Semi-annual maintenance includes vent cleaning, with vent runs approximately 5-8 feet long. The contract is planned to start in January or February, with weekend work requiring special approval. Installation scheduling is at the contractor's discretion, though washrooms should not be out of service over weekends or holidays.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers 3 Washer Dryer Lease

• Q: Are there elevators in any of the dorms?

A: No.

• Q: Will there be sidewalk access to all buildings to load and unload directly into the buildings?

A: Yes.

• Q: How would you like to schedule install by building?

A: It is at the contractor’s discretion

• Q: Will there be extra space for parts storage?

A: Yes.

• Q: What kind of storage is available?

A: Short-term storage: Climate Controlled Storage (2,000 sq. ft.), Warehouse storage with loading dock (2,000 sq. ft). Long Term Storage: Within dorm buildings (200 sq. ft.)

• Q: Can vendors work on weekends/federal holidays?

A: Avoid weekends if possible- As needed to ensure that entire washrooms are not out of service over the weekends or holidays. Clearance must be obtained by customer AND Contracting Officer.

• Q: Is there a specific budget range you are trying to stay within that you feel comfortable with? We ask because we have the option to provide high-tech, energy-efficient, and fast washer and dryers. However, these options do come at a higher price point compared to some basic models, which would still get the job done but may not be as energy-efficient or as fast.

A: While the specific budget cannot be disclosed, vendors are required to submit a quote that aligns with the specifications outlined in the Performance Work Statement (PWS). Any additional features are optional and left to the vendor's discretion.

• Q: Regarding the 500 service calls—are these guaranteed to be paid for the entire year, or will they be paid out just on how much service calls are made in the given year.

A: These will be paid out on just how many service calls are made in a year.

• Q: Project Start Date: Could you confirm the anticipated start date for this project?

A: I would like to start this contract in the month of January or February.

• Q: Number of Barracks: How many barracks will require the installation of washers and dryers?

A: 12.

• Q: Delivery Dock: Does Dyess AFB have a delivery dock available for unloading equipment, or should alternative arrangements be made?

A: Yes, we have a dock with a couple thousand square feet of temporary storage, but it’s located a couple blocks away from the dormitories.

• Q: I believe you are requesting the lease of the following:

Your solicitation requests the following:

• 72 single washers

• 72 single dryers

• 76 combo washer dryers

My question is are the 76 combo units made up of one front load washer with dryer stacked on top or will you accept a unit that is all in one.

A: We will accept stacked or a combo unit.

• Q: Line item 0003 Maintenance (Semi-Annual) please explain what this involves A: Paragraphs 1.9 through 1.9.4 in the PWS provides details on what the Semi-Annual Maintenance entails.

• Q: Is this line item for vent cleaning? If so, please provide more information about the vents to be cleaned. Such as do the dryer vents from the dryers go directly out the back wall of each dryer or do the vents go thru the interior wall to an opening on the roof?

A: Paragraph 1.9.1. describes what needs to be cleaned for the vents. A site visit is needed to show where the vents exit the facility, but I believe the vents go through the exterior wall to an opening on the side of the facility.

• Q: Is the vent cleaning only from the back of each dryer to connection in wall?

A: Paragraph 1.9.1. describes what needs to be cleaned for the vents

• Q: How long is the vent hose behind each dyer?

A: Approximately 5-8 feet. A site visit will be helpful.

• Q: Please provide the type of dryer electric cord required for each dryer. three prong or four prong.

A: Paragraph 1.2.2. discusses dryer specifications. All are 4 prongs.

• Q: Will you provide a secure staging area for the incoming new washers and dryers for installation?

A: We have a warehouse, and we can temporarily store approximately 2K square feet during the install phase.

• Q: Do the buildings receiving new washers and dryers have elevators that can be used for installing the new units?

A: No.

• Q: 500 service calls-- if there are fewer service calls will contractor be paid for 500 service calls if there are more than 500 service calls will contractor be paid for the additional service calls?

A: Contractors will only be paid for the service calls executed. The new number of service calls are 75 for each year. Still, the vendor will only be paid for service calls executed.

• Q: Project Start Date: Could you confirm the anticipated start date for this project?

A: I would like to start this contract in the month of January or February.

• Q: Number of Barracks: How many barracks will require the installation of washers and dryers?

A: 12.

• Q: Delivery Dock: Does Dyess AFB have a delivery dock available for unloading equipment, or should alternative arrangements be made?

A: Yes, we have a dock with a couple thousand square feet of temporary storage, but it’s located a couple blocks away from the dormitories.

File details come from the government source that posted it. Updated .