6 Pricing Worksheet (SOW att G).xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- Dyess AFB MACC
- Solicitation number
- FA4661-20-R-0001
About this file
This document contains a pricing worksheet and related federal contract opportunity notice. The pricing worksheet is a template for contractors to provide labor, material, equipment, and subcontract pricing by construction division for renovating building 6030A and B at Dyess Air Force Base in Texas, including relocating and storing furniture during construction. The total proposed construction cost is $4. The related federal contract opportunity is a pre-solicitation notice for an upcoming multiple award construction contract at Dyess AFB with a ceiling of $150 million over a seven-year period including two one-year options. The initial task order is expected to be between $1-5 million for repairs to building 6030. The 100% small business set-aside solicitation will be issued on or around February 28, 2020 by the Department of the Air Force Global Strike Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12 Question Submission Form.doc | DOC document | |
| 11 Site Visit Registration Form.doc | DOC document | |
| 4 Seed Project SOW Bldg 6030 v3.pdf | ||
| 5 WD 18 Feb.pdf | ||
| 10 Subcontractor Consent Form.doc | DOC document | |
| 3 MACC Blanket Special Conditions.pdf | ||
| 1 MACC solicitation sections F-H.docx | DOCX document | |
| 7 FACTS Sheet.docx | DOCX document | |
| 8 PPQ.docx | DOCX document | |
| 0 Solicitation - FA466120R0001.pdf | ||
| 9 Financial Reference Sheet.docx | DOCX document | |
| 2 MACC solicitation sections L and M.docx | DOCX document | |
| MACC Synopsis memo.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ATTACHMENT 6 | DRAFT DOCUMENT | |||||||||||
| PRICE BREAKDOWN BY DIVISION | Contractor: | |||||||||||
| Date: | ||||||||||||
| Dyess AFB, TX | Note: Due no later than 2 hours after official bid time. | |||||||||||
| FNWZ 13-0068 | Color Legend: | Formula Areas | Gov't Numbers | |||||||||
| Division Line Items Include the Items Below: | ||||||||||||
| 0001 Base Pricing, Item 1 – Renovate 6030A & B | CONTRACTOR BID | GOVERNMENT ESTIMATE | Division 1: typically bonds, general liability, builders risk, O&P | |||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | % of Est | IGE | % of Bid | Difference | Notes: If DB, typically includes design fees, geotechnical, CAD as-builts, materials testing, etc. | |||
| Division 1 - General Conditions | $ 1.00 | $ - 0 | $ - 0 | $ - 0 | $ 1.00 | 100.00% | $ - 0 | ERROR:#DIV/0! | $ (1.00) | Notes: If Bid-Build, typically includes CAD as-builts, materials testing, superintendent, storage containers, vehicles, small tools, trash dumpsters, portable toilets, project signage, |
bulletin board, plan sets, temporary fencing, cleanup, etc.
| Division 2 - Existing Conditions | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 2: earthwork, asbestos abatement, selective building demolition, site grading, tree trimming & removal, termite treatment, seeding, etc. | |
| Division 3 - Concrete | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 3: basic concrete materials & methods, forms, accesssories, reinforcement, concrete placement & labor | |
| Division 4 - Masonry | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 4: masonry, grout, labor | |
| Division 5 - Metals | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 5: structural framing, metal deck & joists, cold-formed metal framing, ornamental metal, expansion control | |
| Division 6 - Woods & Plastic | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 6: rough & finish carpentry, casework | |
| Division 7 - Thermal/Moisture | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 7: dampproofing, waterproofing, thermal protection, roofing, flashing, roof specialties, fire & smoke protection, joint sealers | |
| Division 8 - Doors & Windows | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 8: doors, frames, windows, entrances & storefronts, skylights, hardware, glazing | |
| 9 | Division 9 - Finishes | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 9: metal support facilities, gypsum board, tile, ceilings, flooring, wall finishes, acoustical treatment, paints & coatings |
| Division 10 - Miscellaneous Specialties | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 10: visual display boards, grilles & screens, architectural louvers & vents, corner guards, access flooring, flagpoles, identification devices/signage | |
| Division 11 - Equipment | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 11: loading dock equipment, residential equipment | |
| Division 12 - Furnishings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 12: manufactured casework | |
| Division 13 - Special Construction | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 13: sound, vibration & seismic control, lightning protection, pre-engineered structures, swimming pools, hazardous material remediation, building automation & control, | |
| Division 15 - Plumbing & HVAC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 15: building services piping, fire protection piping, plumbing fixtures & equipment, HVAC equipment, air distribution, HVAC instrumentation & controls, HVAC testing & balancing | |
| Division 16 - Electrical, Communication, & Fire Alarm | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 | Division 16: fire detection & alarms, wiring methods, electrical power, transmission & distribution, lighting, communications | |
| 100.00% | ERROR:#DIV/0! | ||||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | |||||||
| 0001 Base Pricing, Item 1 – Renovate 6030A & B Totals: | 1.00 | 0.00 | 0.00 | 0.00 | $ 1.00 | $ - 0 | $ (1.00) |
| 0002 Base Pricing, Item 2 - Furniture Relocation, Storage during construction and reinstallation | |||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | % of Est | IGE | % of Bid | Difference | |
| Division 1 - General Conditions | $ 1.00 | $ - 0 | $ - 0 | $ - 0 | $ 1.00 | 100.00% | $ - 0 | ERROR:#DIV/0! | $ (1.00) |
| 100.00% | ERROR:#DIV/0! | ||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | |||||
| 0002 Base Pricing, Item 2 - Furniture Relocation, Storage during construction and reinstallation Totals: | 1.00 | 0.00 | 0.00 | 0.00 | $ 1.00 | $ - 0 | $ (1.00) |
| 0003 Pricing Option, Item 3 - Lightning Protect System | |||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | % of Est | IGE | % of Bid | Difference | |
| Division 1 - General Conditions | $ 1.00 | $ - 0 | $ - 0 | $ - 0 | $ 1.00 | 100.00% | $ - 0 | ERROR:#DIV/0! | $ (1.00) |
| Division 2 - Existing Conditions | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 |
| Division 13 - Special Construction | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 |
| 100.00% | ERROR:#DIV/0! | ||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | |||||
| 0003 Pricing Option, Item 3 - Lightning Protect System Totals: | 1.00 | 0.00 | 0.00 | 0.00 | $ 1.00 | $ - 0 | $ (1.00) |
| 0004 Pricing Option, Item 4 - Photo-Voltaic System | |||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | % of Est | IGE | % of Bid | Difference | |
| Division 1 - General Conditions | $ 1.00 | $ - 0 | $ - 0 | $ - 0 | $ 1.00 | 100.00% | $ - 0 | ERROR:#DIV/0! | $ (1.00) |
| Division 2 - Existing Conditions | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 |
| Division 16 - Electrical, Communication, & Fire Alarm | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | 0.00% | $ - 0 | ERROR:#DIV/0! | $ - 0 |
| 100.00% | ERROR:#DIV/0! | ||||||||
| LABOR | MATERIAL | EQUIPMENT | SUBCONTRACT | TOTAL | |||||
| 0004 Pricing Option, Item 4 - Photo-Voltaic System Totals: | 1.00 | 0.00 | 0.00 | 0.00 | $ 1.00 | $ - 0 | $ (1.00) |
Total Construction Cost: $ 4.00 $ - 0