Q_&_A's_Amnd1.pdf
PDF 196 KB Posted
- Solicitation number
- FA4659-17-Q-0029
About this file
Updated answers to contractor submitted questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q_&_A's.pdf | ||
| Combo_Combat_Arms_AMND3.pdf | ||
| Combo_Combat_Arms_AMND1.pdf | ||
| Wage_Determination.pdf | ||
| Combo_Combat_Arms.pdf | ||
| STATEMENT_OF_WORK_cleaning_27_April.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Submitted Questions and Government Answers
The below questions represent those proposed by contractors regarding the statement of work for Solicitation Number: FA4659-17-Q-0029. The government’s answers are shown below.
Scope of Work, Section 2:
1) 2.2 - "Clean the 21 point retrieval system. vertical supports."
- How do you define vertical supports? The immediate components required for the retrieval system? This is not to include the "buildings" vertical support.
A. It’s the components required for the target retrieval system
2) 2.3 - "The waste will be property of the contractor."
- Contractor recommends this language is changed, the Range Owner is the generator of the hazardous-waste. Contractor can facilitate the transport and disposal, but a range contact will be needed for signing profiles and manifests.
- Can contractor treat waste for disposal as non-hazardous or disposal?
A. The waste will become the property of the contractor once removed.
Attachment 2 of SOW
Under Basic Services
3) "Area of all Firing Lanes" - say to "HEPA Vacuum/Wipe Clean"
- Wipe clean is not mentioned in Basic SOW. Please specify what should be wiped clean.
A. what cannot be HEPA vacuumed will be wiped clean, example would be door frames/wall separating firing bay from firing lanes
4) - Does this job include the option for lead reclamation of granular rubber trap?
A. There will not be reclamation of lead rounds for this requirement.
General
5) - Is contractor required to stage a containment work/hot zone and associated zones for work?
A. There will not be lead reclamation, so this will not be required.
6) - In the event we win this bid is it possible if we send a HEPA vacuum and leave at the range? Or do we have to take it each visit?
A. Take it each visit, Combat Arms will not be responsible for equipment left behind.
7) Do we only submit price schedule form or do you guys also needs a company estimate/proposal with each line item?
A. A full price schedule must be submitted to include all CLINs and Option years.
*NEW QUESTIONS*
8. What was the previous contract value and number?
A. This is the first time this requirement has been solicited, so there is no prior contract number or value.
9. Do the rubber granules on the floor need to be disposed of or placed back into the rubber berm?
A. They may be placed back into the rubber berm.
10. Will the extra rubber used to fill the trap be moved from the storage area by the government or will that be the responsibility of the contractor?
A. It will be the responsibility of the contractor to move extra rubber from the storage area.