Repair, Add, and Locate Natural Gas Distribution Grand Forks AFB

33 05 23.13 - 1 JFSD200417

August 2016

SECTION 33 05 23.13

UTILITY HORIZONTAL DIRECTIONAL DRILLING

11/13

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION

OFFICIALS (AASHTO)

AASHTO T 180 (2010) Standard Method of Test for Moisture-Density

Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01000 TECHNICAL PROVISIONS:

SD-01 Preconstruction Submittals

Statement of Qualifications and Records; G

SD-02 Shop Drawings

Record Drawings; G

SD-03 Product Data

Polyethylene Pipe; G

Drilling Fluids; G

Additives; G

Mixtures; G

SD-05 Design Data

Material Safety Data Sheets; G

33 05 23.13 - 2 JFSD200417

SD-06 Test Reports

Soil Test Data; G

SD-07 Certificates

Drill Rod; G

SD-11 Closeout Submittals

Complete Work Logs of Guided Directional Drill Operations; G

1.3 COMMENCEMENT, DELIVERY, STORAGE, AND HANDLING OF MATERIALS

Prior to commencement of the work, submit the following to the Engineer of Record for review and approval:

a. Polyethylene Pipe

b. Material Safety Data Sheets

c. Statement of Qualifications and Records

d. Soil Test Data

Provide written documentation of conformance with AASHTO T 180. Submit a complete list of all drilling fluids, additives, and mixtures to be used along with Material Safety Data Sheets.

Inspect materials delivered to the site for damage. All materials found during inspection or during the progress of work to have cracks, flaws, surface abrasions, or other defects will be rejected. Remove defective materials from the job site.

1.4 QUALITY ASSURANCE

1.4.1 Qualifications

Ensure that Contractor and his field supervisor assigned to this project are experienced in work of this nature and have successfully completed similar projects of similar length, pipe type, pipe size, and soil type using directional drilling in the last three (3) years. As part of the bid submission, submit a description of such project(s) which include, at a minimum, a listing of the location(s), date of project(s), owner, pipe type, size installed, length of installation, type, and manufacturer of equipment used, and other information relevant to the successful completion of the project.

1.4.2 Safety

Include in directional drilling equipment machine safety requirements a common grounding system to prevent electrical shock in the event of underground electrical cable strike. Ensure the grounding system connects all pieces of interconnecting machinery; the drill, mud mixing system, drill power unit, drill rod trailer, operators booth, worker grounding mats, and any other interconnected equipment

33 05 23.13 - 3 JFSD200417

to a common ground. Equip the drill with an "electrical strike" audible and visual warning system that notifies the system operators of an electrical strike.

PART 2 PRODUCTS

2.1 EQUIPMENT

2.1.1 Drill Rod

Select the appropriate drill rod to be used. Submit certified statement that the drill rod has been inspected and is in satisfactory condition for its intended use.

2.1.2 Pipe

Install pipe of sizes and materials shown the drawings.

2.2 MATERIALS

2.2.1 Drilling Fluids

Disposal of fluids is the responsibility of the Contractor. Dispose of fluids in a manner that is in compliance with all permits and applicable Federal, State, and local regulations.

Use a high quality bentonite drilling fluid to ensure hole stability, cuttings transport, bit and electronics cooling, and hole lubrication to reduce drag on the drill pipe and the product pipe. Use only fluid with a composition which complies with all Federal, State, and local environmental regulations.

Mix the bentonite drilling fluid with potable water (of proper pH) to ensure no contamination is introduced into the soil during the drilling, reaming, or pipe installation process. The Contractor is responsible for any required pH adjustments.

Disposal of the drilling fluids is the responsibility of the Contractor. Conduct disposal in compliance with all relative environmental regulations, right-of-way and work space agreements, and permit requirements.

Collect drilling fluid returns in the entrance pit, exit pit, or spoils recovery pit. Immediately clean up any drilling fluid spills or overflows from these pits.

PART 3 EXECUTION

3.1 INSTALLATION

Ensure all utilities are located and clearly marked prior to start of excavation or drilling.

3.1.1 Drill Set-Up

Do not allow drilling mud to flow freely on the site. Remove spilled mud and restore ground to original condition.

33 05 23.13 - 4 JFSD200417

When drilling near wetlands or water courses, provide secondary containment to prevent drilling fluids from entering the wetlands, and secure written approval of secondary containment plan from the Contracting Officer.

3.1.2 Drill Entrance and Exit Angle

Ensure entrance and exit angles and elevation profile maintains adequate cover to reduce risk of drilling fluid breakouts and ground exit occurs as specified herein. Ensure that entrance and exit angles generate pullback forces that do not exceed 5 percent strain on the pipe.

3.1.3 Pilot Hole

The type and size of the pilot string cutting head and the diameter of the drill pipe is at the Contractor's discretion.

Drill the pilot hole along the path shown on the plan drawings. Pilot hole tolerances are as follows:

a. Horizontal Tolerance: Plus/minus - 60-inches from the centerline of the product pipe.

b. Curve Radius: No curve is acceptable with a radius less than 1,000-feet.

c. Entry Point Location: Make pilot hole entry point within plus/minus - 60-inches of the location shown on the drawings or as directed by the Contracting Officer in the field.

d. Exit Point Location: Make the exit point location within plus/minus - 60-inches of the location shown on the drawings or as directed by the Contracting Officer in the field.

e. Mandatory pipeline cover requirements are as shown on the drawings or as specified.

3.1.4 Guidance Systems

Walkover guidance systems are not acceptable for this project; use a magnetic survey tool locator installed behind the pilot string cutting head and an electric grid (tru-tracker) system for this project.

3.1.5 Reaming

Conduct reaming operations at the Contractor's discretion. Determine the type of back reamer to be utilized by the type of subsurface soil conditions that are encountered during the pilot hole drilling operation. The reamer type is at the Contractor's discretion.

3.1.6 Pull Back

Fully assemble the entire pipeline to be installed via direction drill prior to commencement of pull back operations.

Support the pipeline during pullback operations in a manner to enable it to move freely and prevent damage. Install the pipeline in one continuous pull.

Minimize torsion stress by using a swivel to connect the pull section to the reaming assembly.

33 05 23.13 - 5 JFSD200417

Maximum allowable tensile force imposed on the pull section is not to exceed 90 percent of the pipe manufacturer's safe pull (or tensile) strength. If the pull section is made up of multiple pipe size or materials, the lowest safe pull strength value governs and the maximum allowable tensile force is not to exceed 90 percent of this value.

Minimize external pressure during installation of the pullback section in the reamed hole. Replace damaged pipe resulting from external pressure at no cost to the Government. Buoyancy modification is at the discretion of the Contractor.

3.1.7 Connection of Product Pipe to Pipeline

After the product pipe has been successfully installed, allow the product pipe to recover for 24 hours prior to connection of the pipeline. Ensure that a sufficient length of the product pipe has been pulled through the hole so that the pull-nose is not pulled back into bore hole due to stretch recovery of the product pipe.

3.2 FIELD QUALITY CONTROL

Maintain drilling logs that accurately provide drill bit location (both horizontally and vertically) at least every 2-inches along the drill path. In addition, keep logs that record, as a minimum the following, every 15 minutes throughout each drill pass, back ream pass, or pipe installation pass:

a. Drilling Fluid Pressure

b. Drilling Fluid Flow Rate

c. Drill Thrust Pressure

d. Drill Pullback Pressure

e. Drill Head Torque

Make all instrumentation, readings, and logs available to the Contracting Officer at all times during operation.

3.3 CLOSEOUT ACTIVITIES

Immediately upon completion of work, remove all rubbish and debris from the job site. Remove all construction equipment and implements of service leaving the entire area involved in a neat condition acceptable of the Contracting Officer.

Immediately clean "blow holes" or "breakouts" of drilling fluid to the surface and return the surface area to its original condition. Dispose of all drilling fluids, soils, and separated materials in compliance with Federal, State, and local environmental regulations.

Submit an electronic copy and three hard copies of the record drawings to the Contracting Officer within five days after completing the pull back. Include in the record drawings a plan, profile, and all information recorded during the progress of the work. Clearly tie the record drawings to the project's survey control. Maintain and submit upon completion signed complete work logs of guided directional drill operations.

33 05 23.13 - 6 JFSD200417

-- End of Section --