Attch_2_Submittal_Schedule.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- Fire Suppression System Federal contract opportunity
- Solicitation number
- FA4626-15-R-0003
About this file
Attch 2 Material Submittal
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SKMBT_42315030317050.pdf | ||
| PreProposal_SiteVisit_Minutes.doc | DOC document | |
| Attch_4_Drawings.zip | ZIP file | |
| Solicitation.doc | DOC document | |
| Attch_6_Base_Entry_Policy_Letter.pdf | ||
| Attch_5_Wage_Determination.pdf | ||
| Attch_3_Schedule_of_Drawings.docx | DOCX document | |
| Attch_1_Specs.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIALS SUBMITTALS | Project Number | Project Title: | Solicitation/Contract No. | ||||||||||||||||||
| NZAS 10-1024 | Fire Protection Building 1082 | FA4626-xx-x-xxxx | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | NOTIFICATION | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| 1 | Section 01 00 00 - General Requirements | ||||||||||||||||||||
| 1 | 3.5 A. Red Lines | 4 | PTFI | ||||||||||||||||||
| 2 | 3.5 B. As Built Field Data | 4 | 3 PTFA | ||||||||||||||||||
| 3 | 3.7 Operating and Maintenance Instructions | 4 | 3 PTFA | ||||||||||||||||||
| 4 | 3.8 B. Contractor Furnished Equipment List | 4 | 3 PTFA | ||||||||||||||||||
| 5 | 3.8 C. Guarantees | 4 | 10 PTFA | ||||||||||||||||||
| 6 | 3.9 Shop Drawings as Required by Technical Specifications | 4 | 10 PTSA | ||||||||||||||||||
| 7 | 3.10 Start of Work Notification | 1 | PTSW | ||||||||||||||||||
| 8 | 3.11 Notice of Final Inspection | 1 | 14 PTFI | ||||||||||||||||||
| 9 | 3.12 Construction Near Utility Systems (AF Form 103) | 1 | PTSW | ||||||||||||||||||
| 10 | 3.13 Utility Outage Notices | 1 | 14 PTO | ||||||||||||||||||
| 11 | 3.17 B. Quality Control Plan | 4 | PTSW | ||||||||||||||||||
| 12 | 3.17 D.Quality Control Records | 1 | EWD | ||||||||||||||||||
| 13 | 13.18 1354 Checklist (Property Inventory Checklist) | 4 | PTFI | ||||||||||||||||||
| 15 | 3.20 Nuclear Densometers | 4 | PTSW | ||||||||||||||||||
| 16 | 3.21 Project Sign | 4 | PTSW | ||||||||||||||||||
| 17 | |||||||||||||||||||||
| 18 | Section 01 00 10 - Security | ||||||||||||||||||||
| 19 | 1.1 A. Entry Authorization List | 4 | PTSW | ||||||||||||||||||
| 20 | |||||||||||||||||||||
| 21 | Section 01 30 00 - Administrative Requirements | ||||||||||||||||||||
| 22 | 3.1 D. Preconstruction Meeting Minutes | PTSW | |||||||||||||||||||
| 23 | 3.2 E. Progress Meetings | PTSW | |||||||||||||||||||
| 24 | 3.3 A. Construction Progress Schedule (AF Form 3064) | PTSW | |||||||||||||||||||
| 25 | |||||||||||||||||||||
| 26 | Section 01 36 00 - Environmental Protection | ||||||||||||||||||||
| 27 | 1.5 B. Demolition Activities Notification | 4 | PTSW | ||||||||||||||||||
| 28 | 1.6 A. Environmental Protection and Waste Management Plan | 4 | PTSW | ||||||||||||||||||
| 28 | 1.6 B. Monthly Report of Solid Waste Generation and Disposal | 4 | Monthly | ||||||||||||||||||
| 29 | 1.6 C. Noise Level Report | 4 | Monthly | ||||||||||||||||||
| 30 | 3.3 A.1. Construction Storm Water Notice of Intent | 4 | PTSW | ||||||||||||||||||
| 31 | 3.3 A.2. Construction Storm Water Polution Prevention Plan | 4 | PTSW | ||||||||||||||||||
| 32 | 3.3 B.3.Construction Storm Water Notice of Termination | 4 | PTSW | ||||||||||||||||||
| 33 | 3.3 D. Construction Dewatering Permit | 4 | PTSW | ||||||||||||||||||
| 34 | 3.6 and 3.7 Hazardous Materials Report EESOH-MIS 3952 | 4 | PTSW | ||||||||||||||||||
| 35 | 3.10 C. Divert/Recycle Material Report | 4 | PTSW | ||||||||||||||||||
| 36 | 3.11 E. and F. Recovered Materials Written Determination Form - 01 36 00 - 12.4 | 4 | PTSW | ||||||||||||||||||
| 37 | 3.14 A.1 MDEQ Certification Letter for operation of a Public Water Supply or Wastewater System | 4 | SRO | ||||||||||||||||||
| 38 | 3.14 A.2 Certified As-Builts Accepted by MDEQ | 4 | PTSA | ||||||||||||||||||
| 39 | |||||||||||||||||||||
| 40 | Section 03 31 00 - Structural Concrete | ||||||||||||||||||||
| 41 | 1.6 A. Product Data | 4 | 15 ANP | ||||||||||||||||||
| 42 | 1.6 B. Samples | 4 | 3 PTP | ||||||||||||||||||
| 43 | 1.6 C. Concrete Mix Design | 1 | 21 PTFU | ||||||||||||||||||
| 44 | 1.6 D. Concrete Test Results | 4 | 36 HR ATT | ||||||||||||||||||
| 45 | |||||||||||||||||||||
| 46 | Section 21 13 13 - Wet Pipe Fire Sprinkler System | ||||||||||||||||||||
| 47 | 1.6 B. As-Built Plans | 1 | PTFA | ||||||||||||||||||
| 48 | 3.3 C. Test Certificates | 4 | PTFA | ||||||||||||||||||
| 49 | 1.7 A. Operation and Maintenance Manual | 4 | PTFA | ||||||||||||||||||
| 50 | As-Built Drawings | 4 | PTFA | ||||||||||||||||||
| 51 | As-Built Calculations | 4 | PTFA | ||||||||||||||||||
| 52 | NFPA #25 | 4 | PTFA | ||||||||||||||||||
| 53 | Materials | 4 | PTFA | ||||||||||||||||||
| 54 | Manufacturers Instructions | 4 | PTFA | ||||||||||||||||||
| 55 | Test Certificates | 4 | PTFA | ||||||||||||||||||
| 56 | As-Built CD | 4 | PTFA | ||||||||||||||||||
| 57 | 1.8 Training | 4 | AFI | ||||||||||||||||||
| 58 | 1.9 Warranty | 4 | AFI | ||||||||||||||||||
| 59 | |||||||||||||||||||||
| 60 | Section 21 13 17 - Dry Pipe Fire Sprinkler System | ||||||||||||||||||||
| 61 | 1.6 B. As-Built Plans | 1 | PTFA | ||||||||||||||||||
| 62 | 3.3 D. Test Certificates | 4 | PTFA | ||||||||||||||||||
| 63 | 1.7 A. Operation and Maintenance Manual | 4 | PTFA | ||||||||||||||||||
| 64 | As-Built Drawings | 4 | PTFA | ||||||||||||||||||
| 65 | As-Built Calculations | 4 | PTFA | ||||||||||||||||||
| 66 | NFPA #25 | 4 | PTFA | ||||||||||||||||||
| 67 | Materials | 4 | PTFA | ||||||||||||||||||
| 68 | Manufacturers Instructions | 4 | PTFA | ||||||||||||||||||
| 69 | Test Certificates | 4 | PTFA | ||||||||||||||||||
| 70 | As-Built CD | 4 | PTFA | ||||||||||||||||||
| 71 | 1.8 Training | 4 | AFI | ||||||||||||||||||
| 72 | 1.9 Warranty | 4 | AFI | ||||||||||||||||||
| 73 | |||||||||||||||||||||
| 74 | Section 26 42 00 - Cathodic Protection | ||||||||||||||||||||
| 75 | 4.4 Test Results and Drawing | 4 | PFI | ||||||||||||||||||
| 76 | |||||||||||||||||||||
| 77 | Section 28 31 74 - Interior Addressable Fire Alarm System | ||||||||||||||||||||
| 78 | 1.4.C., 1.4.I.a. Manufacturer's Authorization | 4 | PTSW | ||||||||||||||||||
| 79 | 1.4.G., 1.4.I.b. Contractor License | 4 | PTSW | ||||||||||||||||||
| 80 | 1.4.G., 1.4.I.c. Installers Licenses | 4 | PTSW | ||||||||||||||||||
| 81 | 1.4.F., 1.4.J.a., 1.6 Red Line Asbuilt Drawings | 1 | PTFA | ||||||||||||||||||
| 82 | 1.4.D., 1.4.J.b. Device List | 4 | PTFA | ||||||||||||||||||
| 83 | 1.4 J.c., 3.4 Preliminary Test Report | 4 | PTFA | ||||||||||||||||||
| 84 | 1.4.K.a., 1.8 Spare Parts | 4 | AFI | ||||||||||||||||||
| 85 | 3.4 Final Test Reports | 4 | AFI | ||||||||||||||||||
| 86 | 1.4.L.b., 1.7 Operation & Maintenance Manuals | 4 | AFI | ||||||||||||||||||
| 87 | 1.4.L.c., 1.9 Training Attandance Record | 4 | AFI | ||||||||||||||||||
| 88 | 1.4.L.d., 1.10 Letter of Warranty | 4 | |||||||||||||||||||
| 89 | |||||||||||||||||||||
| 90 | Section 28 31 76 - Interior Mass Notification System | ||||||||||||||||||||
| 91 | 1.4.C., 1.4.I.a. Manufacturer's Authorization | 4 | PTSW | ||||||||||||||||||
| 92 | 1.4.G., 1.4.I.b. Contractor License | 4 | PTSW | ||||||||||||||||||
| 93 | 1.4.G., 1.4.I.c. Installers Licenses | 4 | PTSW | ||||||||||||||||||
| 94 | 1.4.F., 1.4.J.a., 1.6 Red Line Asbuilt Drawings | 1 | PTFA | ||||||||||||||||||
| 95 | 1.4.D., 1.4.J.b. Device List | 4 | PTFA | ||||||||||||||||||
| 96 | 1.4 J.c., 3.4 Preliminary Test Report | 4 | PTFA | ||||||||||||||||||
| 97 | 1.4.K.a., 1.8 Spare Parts | 4 | AFI | ||||||||||||||||||
| 98 | 3.4 Final Test Reports | 4 | AFI | ||||||||||||||||||
| 99 | 1.4.L.b., 1.7 Operation & Maintenance Manuals | 4 | AFI | ||||||||||||||||||
| 100 | 1.4.L.c., 1.9 Training Attandance Record | 4 | AFI | ||||||||||||||||||
| 101 | 1.4.L.d., 1.10 Letter of Warranty | 4 | |||||||||||||||||||
| 102 | |||||||||||||||||||||
| 103 | Section 31 23 00 - Trench Excavation and backfill for Pipelines and Appurtenant structures | ||||||||||||||||||||
| 104 | 1.4 Bedding Gradation and Atterberg Limits Lab Tests | 4 | 7 BD | ||||||||||||||||||
| 105 | 1.4 Native Soil Moisture Density Lab Tests | 4 | 7 PTFU | ||||||||||||||||||
| 106 | 1.4 Import Soils Moisture Density Lab Tests | 4 | 7 BD | ||||||||||||||||||
| 107 | |||||||||||||||||||||
| 108 | Section 31 23 23 - Flowable Fill | ||||||||||||||||||||
| 109 | 1.6 A. Product Data | 4 | 15 ANP | ||||||||||||||||||
| 110 | 1.6 B. Material Sampling | 1 | 3 PTP | ||||||||||||||||||
| 111 | 1.6 C. Mix Design | 1 | 21 PTFU | ||||||||||||||||||
| 112 | |||||||||||||||||||||
| 113 | Section 31 23 25 - Excavation, Embankment, Fill, Backfill, and Compaction | ||||||||||||||||||||
| 114 | 1.4 Native Soil Moisture Density Lab Tests | 4 | PTFU | ||||||||||||||||||
| 115 | 1.4 Sub-Excavation Replacement Soil Gradation and Atterberg Limits Lab Tests | 4 | BD | ||||||||||||||||||
| 116 | |||||||||||||||||||||
| 117 | Section 32 12 14 - Gravel Base Course (Crushed) | ||||||||||||||||||||
| 118 | 1.4 Certified Gravel Gradation & Atterberg Limits | 4 | 15 PSW | ||||||||||||||||||
| 119 | 1.4 Gravel Moisture Density Lab Tests | 4 | 15 PSW | ||||||||||||||||||
| 120 | |||||||||||||||||||||
| 121 | Section 32 12 16 - Asphaltic Concrete Pavement | ||||||||||||||||||||
| 122 | 1.4 A. Job Mix Formula | 4 | 15 ANP | ||||||||||||||||||
| 123 | 1.4 B. Bitument Test Reports | 4 | 3 PTFU | ||||||||||||||||||
| 124 | 1.4 C. Field Sample and Core Test Reports | 4 | 2 ATT | ||||||||||||||||||
| 125 | |||||||||||||||||||||
| 126 | Section 32 92 23 - Sodding | ||||||||||||||||||||
| 127 | 3.2 Sod Certification | 4 | PSW | ||||||||||||||||||
| 128 | |||||||||||||||||||||
| 129 | Section 33 11 00 - Water Distribution | ||||||||||||||||||||
| 130 | 1.4 Catalog Data | 4 | 15 ANP | ||||||||||||||||||
| 131 | |||||||||||||||||||||
| Schedule of Abbreviations: | |||||||||||||||||||||
| D - Days | ATT - After Test is Taken | PBC - Prior to Beginning Construction | PT - Prior to Testing | ||||||||||||||||||
| AA - After Award | PSW - Prior to Start Work | PFI - Prior to Final Inspection | PTP - Prior to Placement | ||||||||||||||||||
| AFI - After Final Inspection | BBCW - Before Beginning Concrete Work | PNP - Prior to Notice to Proceed | PTFU - Prior to First Planned Use | ||||||||||||||||||
| ANP - After Notice to Proceed | BD - Before Delivery | PPC - Prior to Project Completion | PTE - Prior to Event | ||||||||||||||||||
| AR - After Receipt |
&"Times New Roman,Regular"&12Attachment 2 &"Times New Roman,Regular"&12Title: Fire Protection-Building 1082 &"Times New Roman,Regular"&12FA4626-15-R-0003
&"Times New Roman,Regular"&12This list is not all inclusive. If needed, additional items may be added.
AF Form 66 &D &"Times New Roman,Regular"&12
SS-&P
REQUIRED TECHNICAL SUBMITTALS