Attach 2 Submittal List
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Reponses_to_Questions.docx | DOCX document | |
| Site_Visit.pdf | ||
| Attch_5_Wage_Determination.pdf | ||
| Drawings.zip | ZIP file | |
| Attch_6_Base_Entry_Policy_Letter.pdf | ||
| Attch_3_Schedule_of_Drawings.docx | DOCX document | |
| Specifications.zip | ZIP file | |
| Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | Project Number | Project Title: | Soliciation/Contract No. | ||||||||||||||||||
| NZAS 15-0041 | Fitness Center Parking Lot | FA4626-14-R-0035 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONSTRCT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MAUFACTURER'S RECOMMENDTIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | NOTIFICATION | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITAL NUMBERS | DATE CONRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DISAPPROVED | ||||||||||||||||||||
| 1 | No Work Condition Notification 01000 3.3 | 1 | |||||||||||||||||||
| 2 | As-Built Field Drawings 01000 3.5.2 | 2 | |||||||||||||||||||
| 3 | Final As-Built Record Drawings 01000 3.5.6 | 2 | |||||||||||||||||||
| 4 | Shop Drawings 01000 3.9 | 4 | |||||||||||||||||||
| 5 | Start of Work Notification | 1 | |||||||||||||||||||
| 6 | Notice of Final Inspection 01000 3.11 | 1 | |||||||||||||||||||
| 7 | Utility Outage Notification 01000 3.13 | 1 | |||||||||||||||||||
| 8 | Quality Control Records 01000 3.17.4 | 1 | |||||||||||||||||||
| 9 | Quality Control Plan 10000 3.17.5 | 3 | |||||||||||||||||||
| 10 | Work Schedule Change Notificationn 01000 3.19 | 1 | |||||||||||||||||||
| 11 | Nuclear Densometer Documentation 01000 3.20 | 1 | |||||||||||||||||||
| 12 | Entry Authority List 01000 1.1.1 | 1 | |||||||||||||||||||
| 13 | Street Closure and Traffic Control Plan 01140 1.2 | 3 | |||||||||||||||||||
| 14 | Environmental Permit Deliverables 01360 2.3 & 4.3.1.1 | 1 | |||||||||||||||||||
| 15 | AF Form 3952 Haz Mat 01360 8.1.2 | 1 | |||||||||||||||||||
| 16 | Haz Mat Data 01360 8.1.4 | 1 | |||||||||||||||||||
| 17 | Disposal Documents and Weight Tickets 01360 11.3 | 1 | |||||||||||||||||||
| 18 | Non-Hazardous Solid Waste Division Report 01360 11.6 | 1 | |||||||||||||||||||
| 19 | Corrective Action Plan 01370 4.1 | 1 | |||||||||||||||||||
| 20 | Geo Textile Sample 0211 1.4 | 1 | |||||||||||||||||||
| 21 | Geo Grid Sample 0211 1.4 | 1 | |||||||||||||||||||
| 22 | Geo Grid, Geo Textile and Contaminiation Barrier Certificate of Compliance 0221 1.4 | 1 | |||||||||||||||||||
| 23 | Bedding Gradation and Atterberg Limits Lab Tests 02221 1.4 | 3 | |||||||||||||||||||
| 24 | Native Soil Moisture Density Lab Tests 02221 1.4 & 02230 1.4 | 3 | |||||||||||||||||||
| 25 | Sub-Excavation Replacement Sol Gradation & Atterberg Limits Lab Tests 02230 1.4 | 3 | |||||||||||||||||||
| 26 | Certified Gravel Gradation & Atterberg Limits 02235 1.4 | 3 | |||||||||||||||||||
| 27 | Gravel Moisture Density Lab Tests 02235 1.4 | 3 | |||||||||||||||||||
| 28 | Tack Oil Certification of Complaince 02502 1.3 | 1 | |||||||||||||||||||
| 29 | Asphalt Mix Formula 02510 1.4A | 3 | |||||||||||||||||||
| 30 | Bitumen Test Reports 02510 1.4B | 3 | |||||||||||||||||||
| 31 | Field Sample and Core Test Reports 02510 1.4C | 3 | |||||||||||||||||||
| 32 | Tactile Warning Surface Catalog Data 02529 1.4B | 3 | |||||||||||||||||||
| 33 | Pavement Marking Paint Certification 02760 1.3 | 3 | |||||||||||||||||||
| 34 | Concrete Product Data 03310 03310 1.6A | 3 | |||||||||||||||||||
| 35 | Concrete Mix Design 03310 1.6C | 3 |
| D - Days | BBCW - Before Beginning Concrete Work | PTP - Prior to Placement |
| AA - After Award | BD - Before Delivery | PTFU - Prior to First Planned Use |
| AFI - After Final Inspection | PBC - Prior to Beginning Construction | PTE - Prior to Event |
| ANP - After Notice to Proceed | PFI - Prior to Final Inspection | |
| AR - After Receipt | PNP - Prior to Notice to Proceed | |
| ATT - After Test is Taken | PPC - Prior to Project Completion | |
| PSW - Prior to Start Work | PT - Prior to Resting |
Attachment 2 FA4626-14-R-0035
&"Times New Roman,Regular"&12This list is not all inclisive. If needed, additional items may be added.
AF Form 66
&D SS-&P