Attachment 2 Submittal Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bldg_500_Questions_-_7-25-14.doc | DOC document | |
| C9.pdf | ||
| Bldg_500_Questions_-_7-22-14.doc | DOC document | |
| B1.pdf | ||
| Site_Visit_Minutes.pdf | ||
| Attch_6_Base_Entry_Policy_Letter.pdf | ||
| Attach_1_Specifications.zip | ZIP file | |
| FA4626-14-R-0027.doc | DOC document | |
| Attach_5_Wage_Determinations.pdf | ||
| Attach_3_SCHEDULE_OF_DRAWINGS.doc | DOC document | |
| Attach_4_Drawings.zip | ZIP file |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIALS SUBMITTALS | Project Number | Project Title: | Solicitation/Contract No. | ||||||||||||||||||
| NZAS 14-0020 | Repair Entrance Bldg 500, Wing HQ | FA4626-14-R-0027 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | NOTIFICATION | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| 1 | GENERAL REQUIREMENTS 01 00 00 - 3.5; As Built Field Data | 2 | 3d PTFI | ||||||||||||||||||
| 2 | GENERAL REQUIREMENTS 01 00 00 - 3.7; O & M Manuals | 3 | PTFA | ||||||||||||||||||
| 3 | GENERAL REQUIREMENTS 01 00 00 - 3.8.1; Contractor Furnished Equipment List | 2 | 10d PTFI | ||||||||||||||||||
| 4 | GENERAL REQUIREMENTS 01 00 00 - 3.8.2; Contractor Guarantees | 2 | 10d PTFI | ||||||||||||||||||
| 5 | GENERAL REQUIREMENTS 01 00 00 - 3.11; Start of Work Notification | 1 | 5d PTSW | ||||||||||||||||||
| 6 | GENERAL REQUIREMENTS 01 00 00 - 3.12; Notice of Final Inspection | 1 | 14d PTFI | ||||||||||||||||||
| 7 | GENERAL REQUIREMENTS 01 00 00 - 3.13; Construction Near Utility Systems | 1 | 3d PTSW | ||||||||||||||||||
| 8 | GENERAL REQUIREMENTS 01 00 00 - 3.14; Utility Outages | 1 | 14d PTSW | ||||||||||||||||||
| 9 | GENERAL REQUIREMENTS 01 00 00 - 3.18.5; Quality Control Plan | 3 | 15d APA | ||||||||||||||||||
| 10 | GENERAL REQUIREMENTS 01 00 00 -3.20; Form 1354 Checklist (Property Inventory Checklist) | 3 | 10d PTFI | ||||||||||||||||||
| 11 | GENERAL REQUIREMENTS 01 00 00 -3.22; Nuclear Densometers | 1 | 30d PT use | ||||||||||||||||||
| 12 | ENVIRONMENTAL PROTECTION 01 36 00 - 2.3 Environmental Permit Deliverables | 3 | 5d SRO | ||||||||||||||||||
| 13 | ENVIRONMENTAL PROTECTION 01 36 00 - 4.3.A Stormwater Discharge Permit Compliance | 3 | 10d PTSW | ||||||||||||||||||
| 14 | ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.1 Hazardous Materials List Attachment 5 | 3 | 10d SRO | ||||||||||||||||||
| 15 | ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.2 Authorization Request Worksheets, AF Form 3952 | 3 | 10d SRO | ||||||||||||||||||
| 16 | ENVIRONMENTAL PROTECTION 01 36 00 - 8.1.4 Hazmat Final Report | 3 | PTFA | ||||||||||||||||||
| 17 | ENVIRONMENTAL PROTECTION 01 36 00 - 11.3 Monthly Report of Solid Waste Disposal & Diversion Attachment 4 | 3 | 10d SRO | ||||||||||||||||||
| 18 | ENVIRONMENTAL PROTECTION 01 36 00 - 11.1.6 Non-Hazardous Solid Waste Diversion Report Attachment 1 | 3 | 10d ANTP | ||||||||||||||||||
| 19 | ENVIRONMENTAL PROTECTION 01 36 00 - 12.1.4 Recovered Materials Written Determination Form Attachment 2 | 3 | 10d SRO | ||||||||||||||||||
| 20 | ENVIRONMENTAL PROTECTION 01 36 00 - 12.5 Recycled Material Use Report Attachment 3 | 3 | 10d SRO | ||||||||||||||||||
| 21 | Standing Seam Metal Roof - Submittal #1 System Summary Sheet 07410-26 | 3 | 3 | 3 | 3 | 3 | 15d ANTP | ||||||||||||||
| 22 | Standing Seam Metal Roof - Submittal #2 System Summary Sheet 07410-27 | 3 | 3 | 3 | 3 | 3 | 15d ANTP | ||||||||||||||
| 23 | Standing Seam Metal Roof - Submittal #3 Appointment of Quality Controller Sheet 07410-29 | 3 | 15d ANTP | ||||||||||||||||||
| 24 | Standing Seam Metal Roof - Submittal #4 Labor and Material Warranty Sheet 07410-30 | 3 | 15d ANTP | ||||||||||||||||||
| 25 | Standing Seam Metal Roof - Submittal #5 Roof Panel Sample Identification Tags Sheet 07410-34 | 1 | 15d ANTP | ||||||||||||||||||
| 26 | Standing Seam Metal Roof - Submittal #6 As-Built Roof System Summary Sheet 07410-35 | 3 | 15d ANTP | ||||||||||||||||||
| 27 | Joint Sealer, 079005 | 3 | 3 | 15d ANTP | |||||||||||||||||
| 28 | Expansion Joint Cover Assemblies, 079513 | 3 | 3 | 3 | 3 | 15d ANTP | |||||||||||||||
| 29 | Aluminum-Framed Storefronts, 084313 | 3 | 3 | 3 | 3 | 15d ANTP | |||||||||||||||
| 30 | Glazed Aluminum Curtain Walls, 084413 | 3 | 3 | 3 | 3 | 3 | 15d ANTP | ||||||||||||||
| 31 | Glazing, 088000 | 3 | 3 | 15d ANTP | |||||||||||||||||
| 32 | Safety and Security Glazing Films | 3 | 3 | 3 | 15d ANTP | ||||||||||||||||
| 33 | Painting and Coating | 3 | 3 | 3 | 15d ANTP | ||||||||||||||||
| 34 | Painting and Coating | 3 | 3 | 3 | 15d ANTP | ||||||||||||||||
| 35 | Cast-in-Place Concrete 033000, 1.3.C. Test Results | 3 | 15d ANTP | ||||||||||||||||||
| 36 | Structural Steel 051200, 1.3.A. through E - Shop Drawings, Product Data, Mill Certs, Welder Certs | 3 | 3 | 3 | 15d ANTP | ||||||||||||||||
| 37 | Helical Piers 056000, 1.3 A. through E. Installer Qualifications, Product Data, Certifications | 3 | 3 | 3 | 3 | 15d ANTP | |||||||||||||||
| 38 | Helical Piers 056000, 1.2 F. Installation record | 3 | 15d ANTP | ||||||||||||||||||
| 39 | Helical Piers 056000, 1.2 J. Load Test | 3 | PTFI | ||||||||||||||||||
| 40 | RACEWAYS AND FITTINGS 26 11 00 - 1.2 | 3 | 15d ANTP | ||||||||||||||||||
| 41 | CONDUCTORS 26 12 00 - 1.2 | 3 | 15d ANTP | ||||||||||||||||||
| 42 | BOXES 26 13 00 - 1.3 | 3 | 15d ANTP | ||||||||||||||||||
| 43 | CATHODIC PROTECTION 26 42 00 - 1.4 | 3 | 3 | 3 | 3 | 3 | 3 | 3* | 15d ANTP | *Field quality report | |||||||||||
| 44 | LIGHTING FIXTURES 26 50 00 - 1.1.D. | 3 | 15d ANTP | ||||||||||||||||||
| Schedule of Abbreviations: | |||||||||||||||||||||
| AWC | = After Work Completed | EWD | = Each work day AF Form 3000 not required | PTFP | = | Prior to Final Payment | |||||||||||||||
| PTSW | = Prior to Starting Work | PTFA | = Prior to Final Acceptance | PTCW | = | Prior to Completing Work | |||||||||||||||
| AFA | = After Final Acceptance | BMF | = | Before Material Delivery | AFI | = | After Final Inspection | ||||||||||||||
| PTO | = Prior to Outage | SN | = | Advance Notification | PT | = | Prior To | ||||||||||||||
| PTNT | = Prior to Notice to Proceed | SRO | = | After Each Occurrence | PSS | Per Submittal Schedule | |||||||||||||||
| ANTP | = After Notice to Proceed | PTFI | = | Prior to Final Inspection |