Contractor Q As.docx

DOCX document 12 KB Posted

Attached to
Launch Facility Concrete Repair Federal contract opportunity
Solicitation number
FA4626-11-T-0003
Issued by
Department of the Air Force Global Strike Command

About this file

Contractor Questions Answers 10 June 11

View the file

Other files for this federal contract opportunity

Other files attached to Launch Facility Concrete Repair, newest first.
File Type Posted
Contractor Q As Part II.docx DOCX document
FA4626-11-T-0003 Amendment 0001.doc DOC document
Pre-Proposal Site Visit Minutes.pdf PDF
Solicitation FA4626-11-T-0003.doc DOC document
FA4626-11-T-0003 Attachments 1 - 5.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4626-11-T-0003 LF Concrete Repair

Contractor Questions & Answers

1. Is there water available at the sites?

No, there is no access to water at the sites.

2. Is there access to power or do we need to bring generators?

The specifications call for “The contractor shall provide any necessary portable power.”

3. Can we bring heavy equipment and trucks onto the site?

Yes, heavy equipment can be brought on site. It may not be driven on the concrete LSB lid.

4. Page 4 of the drawings, detail 4, for the construction joints, the period of between the lifts is to be 14 days. Will the time for the contractor to be on site be stopped for this period of time?

Any required curing time will not count toward the performance period.

5. The plans also call for the concrete to cure 14 days from the time of the saw cut to the sealant of the joint. Will time be stopped between the saw cutting and the joint sealant?

Any required curing time will not count toward the performance period.

6. At I-3, the south east corner of the area to be removed and replaced appear to be much deeper than the 2.5” as specified in the specifications and plans. Would additional defective materials be paid for under a separate item or is this incidental to the remove and replace line item?

Any additional material to be removed, though not expected, will be incidental to CLIN 0001 AA.

7. What type of material is the old or existing waterproof membrane under the wearing slab?

Personnel will perform tests on a few samples. Test results will be posted once received.