Site_Visit_Minutes.pdf

PDF 132 KB Posted

Attached to
Whiteman AFB Livestock Pipeline Federal contract opportunity
Solicitation number
FA462517R0020
Issued by
Department of the Air Force Global Strike Command

About this file

Attach 3, Site Visit Minutes

View the file

Other files for this federal contract opportunity

Other files attached to Whiteman AFB Livestock Pipeline, newest first.
File Type Posted
17R00200004,_Add_Minutes.pdf PDF
Wage_Determination.docx DOCX document
Livestock_Pipelines_-_Maps.pdf PDF
1700200003_Add_Maps.pdf PDF
17R000200002_Add_Clauses.pdf PDF
17R00200001_Add_Site_Visit.pdf PDF
Acknowledge_Amendments.pdf PDF
SOW_Attach_2,_Tobacco_Use_Policy_and_Map.pdf PDF
SOW_Attach_3,_Drug-Free_Workplace_&_Alcohol_Policy_Letter.pdf PDF
SOW_Attach_4,_Cell_Phone_Use_-_Union_Exemption_Version,.pdf PDF
SOW_Attach_1,_Foreign_National_Access_Policy.pdf PDF
SOW_Attach_5,_REAL_ID_ACT.pdf PDF
FA462517R0020_-_Livestock_Pipeline.pdf PDF
Attach_1,_Livestock_Pipelines_-_SOW.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

509th CONTRACTING SQUADRON (AFGSC)

WHITEMAN AIR FORCE BASE, MISSOURI

25 Jul 2017

MEMORANDUM FOR RECORD

FROM: 509 CONS/LGCA

660 Tenth Street, Suite 222 Whiteman AFB, MO 65305-5344

SUBJECT: FA462517R0020 – Livestock Pipeline

1. This meeting was held by the 509th Civil Engineering Squadron (509 CES), and the 509th Contracting Squadron (509 CONS) to review the statement of work (SOW) and allow potential offerors to view the project site. The following individuals were in attendance:

NAME ORGANIZATION

A1C Zachary Koutz 509 CONS Keith Donaldson 509 CES Tom Corbett Corbett Construction Tyler Smith Tony Smith Construction Judy Terwilliger Oncore Federal, LLC Hank Cunningham Pyramid Exc. And Construction Tom Visser Circle V Harvesting, Co.

Scott Rasa Earthworks Excavating Ted Anderson Ted Anderson

2. The site visit took place at the Visitor Center as most of attendees have completed projects at the site in the past. There were only a few topics of discussion. First, there is a gasline on the north end of the property. The exact location of the line is unknown at this time, however CES will provide as builts to contractor prior to digging. Also, it will be the contractor’s resonsability to coordinate with the Rural water company to tie into.

Lastly, there will be two pipeline systems constructed. Both systems will use 1 ½” pipe.

DANIEL B. YOUNG, SSgt Contract Administrator