Initial Site Visit Minutes

View the file

Other files for this federal contract opportunity

Other files attached to Land Prep Area 3 & Areas 1, 2, 4, newest first.
File Type Posted
Contracor_Q A _14_Sep_15.pdf PDF
SOW_-__Areas_1 2 4_-_31_Aug_2015.pdf PDF
SOW_-_Area_3_-_31_Aug_2015.pdf PDF
Land_Prep_Areas_1 2 3 4_Combo.pdf PDF
SOW_-_Area_3.pdf PDF
SOW_-__Areas_1 2 4.pdf PDF
Tobacco_Use_Policy_and_Map.pdf PDF
Foreign_National_Access.pdf PDF
Generic_RFQ_Form_Land_Prep_Area_3_ _Areas_1 2 4.pdf PDF
Cell_Phone_Use_-_Union_Exemption_Version.pdf PDF
Map_-_Area_3_ _Areas_1 2 4.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

08 Sep 2015

1. The following are answers to questions received at during the initial site visit for Land Renovations of Areas 1,2,3,4 on 03 Sep 2015.

a. Tree removal will only take place as designated in the statement of work. This is to include the areas labeled as “Clear Area”.

b. Brush removal of Area 3 is to include all saplings and trees less than 8” as prescribed in the statement of work.

c. The 30’ pathways designated on the map of Area 3 are to be cleared to ground. This may include cutting, dozing, etc.

d. The Service Contract Act does apply to this contract. Refer to solicitation for details

e. Wellheads, exposed pipes, etc. will be marked prior to work for contractor visual. Contractor shall exercise caution around these items and for those that may be missed.