This document is an amendment to a federal solicitation for the procurement of vertical carousels. The amendment responds to vendor questions regarding the scope of work, including requirements for electrical work, shelf capacity, bin reuse, disposal responsibilities, safety requirements, and other technical specifications. The amendment also clarifies award terms, such as the potential for multiple contract line items to be awarded separately or together. The overall solicitation seeks the removal, disposal, assembly, installation, and testing of two brand name or equal vertical carousel units as well as the assembly, installation, and testing of one brand name or equal vertical carousel unit. The solicitation is issued by the Department of the Air Force Air Mobility Command, with a response deadline of March 29, 2024. The government reserves the right to award all, some, or none of the contract line items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24QA309 Attachment 1 SOW.pdf | ||
| 24QA309 Combo.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXCEPTION OF SF 30, APPROVED BY NARS 5/79
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
FA462024QA309
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
23 April 2024
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY
CODE
FA4620 7. ADMINISTERED BY (If other than Item 6)
CODE
92nd Contracting Sq./PKA 110 W Ent St., Suite 200 SAME AS BLOCK 6 Fairchild AFB, WA 99011 Attn: wendy.smith.14@us.af.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) ( ) 9A. AMENDMENT OF SOLICITATION NO.
X
FA462024QA309
All Offerors 9B. DATED (SEE ITEM 11)
29 March 2024
10A. MODIFICATION OF CONTRACT/ORDER
NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[X] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [] is extended, [X] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning _1_ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [] is not, [X] is required to sign this document and return _1_ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE SUMMARY OF CHANGES
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10 A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
WENDY J. SMITH, Contracting Officer
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105-03 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
04/23/2024
FA462024QA309
Amendment 0001 Page 2
SUMMARY OF CHANGES
The purpose of this Amendment is to respond to vendor questions as follows:
CLIN 0001 & 1001
Q1 – Do you want the contractor to install a new breaker in the government’s panel and run a new power line to the carousels through the cement floor so that they are on two separate lines? Or, are you asking us to split the existing single line that is coming in from the cement now into two lines that feed both machines allowing you to “unplug” one but keep the other one running?
A1 – Out of Appendix B: Provide electrician to disconnect the power to carousel C & D, then separate to make two separate power sources. Then reconnect the power to Carousel C to be operational while Carousel D is dismantled and then a new VC is installed. Once the new VC is installed, the power will need to be reconnected to Carousel D.
Q2 – What weight capacity is needed per shelf level?
A2 – 750-1000 lbs per shelf.
Q3 – Is the government reusing their current bins or do we need to supply all new bins and dividers?
A3 – Yes, government is reusing bins.
Q4 – Will the government be providing dumpsters for the wood crating, cardboard and other packing material to be thrown into or is that the responsibility of the contractor?
A4 – We will dispose of the trash, and we have access to wood recycling bin, BUT contractor must provide the scrap metal bin. Pacific Steel & Recycling has access to the base.
Q5 – Is fire suppression required for any of the carousels?
A5 – No
Q6 – Are the carousels to be designed and stamped with seismic zones or are standard, non-seismically designed and stamped carousels acceptable?
A6 – Seismic Certification not required but is acceptable to the government.
Q7 – Safety overrides allow user to operate a carousel in the event of a safety system malfunction? On some carousels, the access door must be kept open during shelving rotation allowing personnel to be hurt or killed while operating it properly, as acknowledged in their operators’ manual. Other carousels require the access door to be closed before rotating, ensuring there is no chance of injury or death. Are both types of safety override systems acceptable?
A7 – The basic safety concern is that the carousel automatically stops rotation when breached.
Q8 – Are certified technicians required to be located in WA state in order to provide prompt repair response, or can technicians be flown in from other states upon availability?
A8 – Either is acceptable.
Amendment 0001 Page 3
Q9 – What are the floor slab/soil details? (for seismic)
a. Slab thickness?
b. Slab PSI rating?
c. Any reinforcement? If so, can specs be provided?
d. Soil bearing capacity?
A9 – I recommend providing the attached as-built drawings showing the construction of the existing facility.
They provide the contractor with all the information requested.
a. Floor slab is 8” concrete. See attached drawing S2.2.
b. Floor slab is rated as 4,000 PSI. See attached drawing S1.0.
c. Yes, there is reinforcement. See attached drawings.
d. Maximum allowable soil bearing pressure = 3,000 PSF. See attached drawing S1.0.
Q10 – Will this project be permitted with the base or any other authority?
a. If so, will the government require P.E. stamped calculations and drawings?
A10 – This project does not require any permitting; No P.E. stamped drawings or calculations are required.
Q11 – What will be stored in your VLM (in the bins)?
a. Commodity class?
b. Dimensions/Weights?
A11 - a. Most non hazard classes. Small aircraft parts made of metal, plastic, rubber, glass, ect.
b. The bins dimension in Appendix B 24” x 12” x 8.5” are what are used to hold the property, weight can vary.
Q12 – Target rate?
a. # of bins accessed per hour/day/shift?
b. # of bins stored per hour/day/shift?
A12 – Not a stat we track.
Q13 – What are the pain points with the existing vertical carousels?
A13 – Alignment of property penetrating the safety lights.
Q14 – Will the government be providing trash and/or recycling bins for Bldg. 2045?
A14 – Government will dispose of the trash, and we have access to a wood recycling bin, BUT contractor must provide the scrape metal bin. Pacific Steel & Recycling has access to the base.
Q15 – Are the existing individual main power disconnect switches to be reused or new ones supplied?
A15 – The current one will not be used, just the normal power for the new carousel. No materials will be supplied by the government.
Q16 – Is it possible that CLIN 0001, Option CLIN 1001, and Option CLIN 2001 would be awarded at the same time (all at once)? Or is it anticipated that the award is placed for CLIN 0001, with the possibility of funding for option CLINs to come at a later date, if at all?
A16 – The government reserves the right to award all, some, or none of the CLINs in accordance with the solicitation. All prices in quotes are to be held firm until 30 Sep 2024.
Amendment 0001 Page 4
Q17 – Is the government able to award CLIN 0001 and Option CLIN 1001 to a one awardee, and CLIN 2001 to a separate awardee?
A17 – The government will award a contract resulting from this RFQ to the responsible vendor, whose quote is conforming to the RFQ, will be most advantageous to the government, price and other, factors considered. Only one awardee will be made.
CLIN 2001
Q1 – Would single, steel pullout filing trays rather than rollout drawers be acceptable?
A1 – No, due to retaining large files, which would increase weight and would like to keep on a rolling system.
Q2 – Is fire suppression required for this carousel?
A2 – No, the room itself currently has a fire suppression installed.
Q3 – Is there a different way for us to access the room where the VCM needs to go in Bldg. 2071?
a. The existing hallway measured 50” wide with a 34” jamb to jamb measurement. We need a minimum of a
60” clear opening. Please confirm.
A3 – The only other point of entry are the double doors at the main entrance of Bldg. 2071. (The doors you initially came in) They measure 72”.
Q4 – Will the government be providing trash and/or recycling bins at Bldg. 2071?
A4 – We have a dumpster and recycle bin om the back parking lot of the bldg.
Q5 – CLIN 2001 as an office filing system is out of the purview of some vertical storage equipment manufacturers. The specs listed (combination of specs) are unique to Kardex and to those “old” filing carousels.
I’m not sure if there is another manufacturer, outside of Kardex, that makes that W x D x H machine at 110v, intended for filing use.
A5 – The dimensions identified are that of the legacy Kardex unit that was removed; the current space availability was measurable during the site visit along with the available power. Please quote the best solution that will meet the space and power constraints with sufficient detail to evaluate compliance with the requirements of the solicitation.
Fill out blocks 15a, 15b, and 15c and provide a copy with your proposal.