FA462018TA021_Amendment_01.pdf
PDF 33 KB Posted
- Attached to
- B-52 Memorial Refurbish Federal contract opportunity
- Solicitation number
- FA462018TA021
About this file
Amendment 01 for questions and answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA462018TA021.pdf | ||
| B-52_Memorial_Refurb_SOW.pdf | ||
| WD_2015-5537_rev_6.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXCEPTION OF SF 30, APPROVED BY NARS 5/79
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
8 September 2018
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE
92nd Contracting Sq./LGCA 110 W Ent St., Suite 200 SAME AS BLOCK 6 Fairchild AFB, WA 99011 Attn: james.plumlee@us.af.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (√) 9A. AMENDMENT OF SOLICITATION NO.
X
FA462018TA021
9B. DATED (SEE ITEM 11)
6 September 2018
10A. MODIFICATION OF CONTRACT/ORDER
NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[X ] �The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [] is extended, [X] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning _ _1_____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(√) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [] is not, [ ] is required to sign this document and return _ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to answer questions related to the combined synopsis/solicitation, as stated on the attached page.
A copy of this amendment must be signed and returned with the contractor’s quote.
Please remember to complete Blocks 8 and 15 of this amendment.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10 A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105-03 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
FA462018TA021
Question 1: Does the Government have an estimate for the engineer’s portion of this work.
Answer 1: This will be a firm fixed price contract. Contractors will quote one total price for the entire job.
Question 2: Do pick-up truck sized vehicles routinely use the road/trail shown in the front of the monument?
Answer 2: No, however ½ ton or smaller vehicles are allowed on hard surface areas ONLY at the monument site.
Question 3: Verify that the seat walls shown are actually filled-in planters that rest on (different colored) footings?
Answer 3: Correct
Question 4: Would the Government consider removing the seat walls and re-pouring them in matching colored concrete for the main monument?
Answer 4: The scope of work has been defined in the statement of work. Encapsulating the repaired concrete with an epoxy based coating system will ensure moisture does not penetrate and accelerate the efflorescence.
8 September 2018