RFI Q&A Responses

View the file

Other files for this federal contract opportunity

Other files attached to Maintain Base Interior and Exterior Paint FE Warren AFB, WY, newest first.
File Type Posted
RFP_Attch_2_BID_SCHEDULE_R1.pdf PDF
RFP_Attch_2_BID_SCHEDULE_R1.xlsx XLSX spreadsheet
Solicitation_Amendment_FA461319RA0080001_SF_30.pdf PDF
RFP Attch 1 New Paint Specifications - 22 August 2018.pdf PDF
RFP Attch 6 Transmittal Letter for PPQ.docx DOCX document
RFP Attch 3 AF Form 66 PDF
RFP Attch 5 PPQ.docx DOCX document
RFP Attch 4 WD_WY190023.pdf PDF
RFP Attch 2 BID SCHEDULE.pdf PDF
Solicitation - FA461319RA008.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RE: Solicitation FA461319RA008

Questions and Answers:

1. The provided wage determination, RFP_Attch_4_WD_WY190023, does not include a determination for

“Painter”. What wage is to be used in order to be compliant with the Davis-Bacon requirements?

The Wage Determination does not specifically list “Painters”, although a previous request from the DOL provided the following: Wage Rate $17.18 Fringe Benefit Payment $3.20. Once Awarded the Successful

Offeror will need to submit an SF 1444 for current wages.

2. 0001AA Install Plastic: Please explain? What will this line item be used for specifically?

Plastic may be used to protect the floor or other adjacent areas during preparation, texturing and painting.

3. 0001AW and AX Lead Based Surface. Can you explain why the estimated quantities are a lot higher than the last time this project was bid?

RFP Attch 2 BID SCHEDULE R1 Provided

4. 0001BB Why is this estimated quantity of 93,000 sf being used since it was not a line item on the past project?

5. Would it be possible to get the past year’s estimated quantities that were performed on the prior project?

The Bid Schedule was provided with the quantities to assist in preparing bids, which is based upon the final option year.

6. The provided Bid Schedule does not address many of the CLINs included in the previous Interior & Ex-terior Paint contract. For example, what existing CLINs would be used to paint a door or window? The missing CLINs are below:

MISC FEATURES

0001EH Prep and paint window, 1 side, w/trim

0001EI Prep and paint window, 1 side, w/trim, above 10'

0001EJ Prep and paint door, 1 side, w/frame

0001EK Prep and paint wood trim, up to 8" wide

0001EL Prep and paint wood trim, up to 8" wide, above 10'

0001EM Prep and paint metal trim, up to 8" wide

0001EN Prep and paint metal trim, up to 8" wide, above 10'

0001EO Prep and paint misc. feature, up to 6" wide

0001EP Prep and paint misc. feature, up to 6" wide, above 10'

0001EQ Remove window screen to paint; replace after

0001ER Prep, repair and paint column, w/base, crown, and trim

0001ES Prep and paint louver, w/trim

0001ET Prep and paint louver, w/trim, above 10'

0001EU Prep and paint downspout (per story)

0001EV Prep and paint roof edge assembly (soffit, fascia, trim)

0001EW Prep and paint roof edge assembly; complex

0001EX Prep and paint large bay door, 1 side, w/trim

0001EY Prep and paint gutters

0001EZ Floor prep & epoxy coating, 2 base coats plus top coat

0001FA Paint, spray application, 2 coats

0001FB Paint, spray application, 2 coats, over 10'

0001FC Prep and paint metal structural member, over 10'

0001FD Prep and paint wooden railing assembly; complex

0001FE Replace corner guard

2AA Minor Prep of Wood Surface 30 to 80'

2AB Major Prep of Wood Surface 30 to 80'

2AC Minor Prep of Metal Surface 30 to 80'

2AD Major Prep of Metal Surface 30 to 80'

2AE Primer application 2 coat 30 to 80' add

2AF Paint application 2 coat 30 to 80' add

2AG Man lift high reach to 80'

2AH Graphics Letter

2AI Graphics Image

2AJ Graphics application

2AK Polyurethane coatings system add to material cost

7. For ease of use, will an Excel version of the Bid Schedule be provided?

Yes

8. The solicitation documents under Section L, paragraph 4.2.3.1 Subfactor 1, asks to “Submit certification for the Abatement Supervisor, Lead Hazard Abatement Workers and Certified Risk Assessor pursuant to

40 CFR 745, Section 226. Given that this is an “Interior and Exterior Paint” solicitation where lead work is ancillary to the painting work and only has two CLINs for the “prep of Lead Based surface” for exteriors only, would it be more relevant to specify the EPA Renovation (RRP) requirement?

The various options for selection criteria were considered and although all the ones selected to be included in the solicitation may not be the most relevant to the entire contract they are necessary requirements.

9. Due to the Military Family Housing being privatized on a separate contract, is Section 02 83 19.00 10 –

Lead Based Paint Hazard Abatement, Target Housing & Child Occupied Facilities applicable? It addresses projects that are primarily lead abatement and not primarily painting. Including the costs of this section to all CLINs in the event that a project may be done in an applicable structure would greatly inflate the pricing.

Section 02 83 19.00 10 – Lead Based Paint Hazard Abatement, Target Housing & Child Occupied Facilities deals with various facilities other than military family housing that may house age 6 and under children and we never know when one of the buildings will need to be painted.