This document is a Question and Answer memorandum related to a federal contract opportunity for Asbestos Abatement services at Vandenberg Space Force Base.
The key details are:
- The Statement of Work reflects 6,660 sq ft, but the actual amount will be verified by the contractor (approximately 5,600 sq ft).
- Chemical removal is the preferred method for removing the black mastic, rather than mechanical removal. The desired floor finish is bare concrete free of mastic.
- The project will be completed in two phases, to be mutually agreed upon by the facility manager and contractor.
- The period of performance for the contract is 60 days after award.
- Quotations are due by 1:00 PM PDT on Thursday, March 21, 2024. Any questions are due by 1:00 PM PDT on Friday, March 15, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001_Attach 1 SOW.pdf | ||
| Amendment 0001 Attach 2 Pricing Schedule.xlsx | XLSX spreadsheet | |
| Amendment 0001-Combined Synopsis Sol.pdf | ||
| Amendment 0001-B871 Floor Plan - Phases.pdf | ||
| Attach. 1 SOW - Asbestos Abatement.pdf | ||
| Attach. 5 VSFB B871_Site Map.pdf | ||
| Attach. 2 - Pricing Schedule.xlsx | XLSX spreadsheet | |
| Attach. 4 Clauses and Provisions.pdf | ||
| Combined Synopsis Solicitation.pdf | ||
| Attach. 3 SCA WD 2015-5647 Rev 20.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTROLLED UNCLASSIFIED INFORMATION
DEPARTMENT OF THE AIR FORCE
UNITED STATES SPACE FORCE
SPACE LAUNCH DELTA 30
CONTROLLED UNCLASSIFIED INFORMATION
15 March 2024
MEMORANDUM FOR CONTRACTORS
FROM: 30 CONS/PKB
1515 Iceland Ave, Bldg. 8500 Vandenberg SFB, CA 93437-5212
SUBJECT: Questions and Answers
a. Clarify the square footage stated in the Statement of Work. Statement of Work reflects 6,660 sq ft verses the 5,600 sq ft stated at the site visit.
Aproximatly 5,600 ft2. Actual amount to be verified by contractor.
b. Can the floor be bead blasted, or can the mastic be removed with buffers? Which do you prefer.
No the best practice is chemical removal.
c. What is the expected floor finish after the abatement?
Bare concrete free of mastic.
d. Black mastic removal shows hand removal, can’t we grind the concrete floor to leave a better surface area for the concrete finish?
No mechanical means is not considered best practice. Chemical is the accepted norm.
e. Is the project required to be completed in phases? The Statement of Work does not include any verbiage regarding phases as mentioned at the site visit.
Yes two phases to be mutually agreed upon by both facility manager and contractor.
f. The following questions are in regards to CLIN 0003 only.
Does our proposal/quote for these services have to submitted directly to the abatement contractors bidding on this project or to the contracting office?
The Contracting Office is not accepting partial quotes.
How many days/weeks do you estimate the asbestos abatement portion of this project will be?
Per the Statement of Work, the period of performance shall be for sixty (60) days after award of the contract.
Will you have a sign-in sheet provided to everyone who attended the meeting?
Sign-in sheet will be available upon request to vendors that attended site visit.